Brigham Young University Provo City Council Neighborhood Symposium January 29, 2013 Existing Conditions Main Items of Work: New pedestrian plaza between Law Building and Wilkinson Center Additional parking near Harris Fine Arts Center Improved pedestrian access through parking lots Convenient drop-off access in front of Wilkinson Center Schedule: Construction begins May 1 Substantial completion by August 15 Phase 1 Work Zone Traffic Impacts: Permanent closure of East Campus Drive south of Heritage Drive Phase 1 Permanent Closure Traffic Impacts: Permanent closure of East Campus Drive south of Heritage Drive Lane restrictions and partial closures during Phase 1 construction Phase 1 Lane Restrictions Phase 1 Completed Main Items of Work: New sidewalk on south side of 1230 North Improved intersection at 450 East New pedestrian drop-off at Hinckley Center Schedule: Construction to begin summer of 2014 Phase 2 Work Zone Traffic Impacts: Lane restrictions during construction Phase 2 Work Zone Phase 2 Completed Main Items of Work: New roundabout entry north of the Administration Building Additional parking near the Museum of Art Improved pedestrian access from student housing to central campus Schedule: Construction to begin summer of 2015 Phase 3 Work Zone Traffic Impacts: Permanent closure of East Campus Drive/Heritage Drive intersection. Phase 3 Work Zone Phase 3 Completed End of Construction