Simon Gyde Route Asset Manager, Buildings Simon Gyde Date 00.00.00 1 Riviera stations regeneration Section number to go here Riviera Stations regeneration Major renewals and refurbishment planned at: • Torquay • Torre • Paignton Works programmed late 2013 – April 2014. Network Rail funded works c.£2.8m Date 00.00.00 Create your footer by changing copy in the Header and Footer section 3 Torquay station • Phase 1 - Agreed package of reactive repairs completed 2012. AFC £50k. • Phase 2 - Road bridge at country end of the station to be refurbished. AFC £400k. On site 20 May 2013 for 18 weeks. • Phase 3 - Station footbridge and canopies to be refurbished late 2013 – April 2014. AFC £1.15m. Date 00.00.00 Create your footer by changing copy in the Header and Footer section 4 Torre station • Phase 1 -Refurbishment of listed footbridge completed 2012. Total AFC: £350k • Phase 2 – platform canopy to be refurbished late 2013 – completion by April 2014. Total AFC : £150k Date 00.00.00 Presentation title to go here 5 Paignton station • Ticket office roof repairs complete Spring 2013. • Station footbridge and canopies to be refurbished late 2013. AFC: £1.13m • Works to be completed by April 2014. • New colour scheme proposed to match that of Torquay and Torre. Date 00.00.00 Presentation title to go here 6 In summary.. • Major refurbishment proposals at Torquay, Teignmouth and Torre aim to restore the listed buildings and structures to former glory. • ‘Riviera line’ colours scheme to be adopted at each location. • All proposals will be fully integrated with other Non – Network Rail work items and funding streams. • Work programmes to be shared with stakeholders. • Total expenditure 2013 /14 = c.£2.8m • Plus… similar packages of work proposed in 13/14 at Dawlish and Teignmouth stations. Date 00.00.00 Create your footer by changing copy in the Header and Footer section 7 Riviera station regeneration •Questions? Date 00.00.00 Create your footer by changing copy in the Header and Footer section 8