Uploaded by dperalta

Report Demolition upper warehouse Sept 07

advertisement
BIDVEST PORT OPERATIONS
REPORT ON DEMOLITION OF
TOWER SECTION OF QUAYSIDE WAREHOUSING
AT MAYDON ROAD,
MAYDON WHARF
Prepared by
S. Osborn Pr Eng
SKP Engineers cc
21 September 2007
File No: 1381/17
Bidvest Port Operations – Report on Demolition to Upper Section of Quince Warehouse
1.
SKP Engineers cc
TERMS OF REFERENCE
SKP Engineers cc were requested by Bidvest Port Operations (BPO) Operations Manager
(Mr N. Watson) to carry out an inspection of portion of Quayside Warehousing at Maydon
Road, Maydon Wharf. The old warehouse has recently been acquired by BPO, and is
currently undergoing partial demolition and remedial work.
During demolition works it was noticed that the part of the structure to be demolished could
be supporting the roof, and hence an inspection was required to confirm that the structural
integrity of the building would not be compromised during this work.
2.
SITE INSPECTION
A site inspection was undertaken on 21 September 2007. The following observations were
made:
•
•
•
•
•
The warehouse roof structure is fabricated from arched concrete members at 4,5m
centres along the warehouse, fixed at the sides and butting at the top. These
members support steel purlins and roof sheet.
There is a reinforced concrete mezzanine floor approximately 4.5m high across the
warehouse which is currently being demolished.
There is an open bay 4.5m wide near the western side of the building, where there
is a structural steel frame (columns & beams) with columns supported on the
concrete mezzanine floor, extending approximately 7m above the arched roof. This
is referred to as the “tower” section.
There is evidence that there previously was mechanical equipment fixed at the roof
level of this tower, with the loads being transmitted down the structural steelwork
and into the concrete columns supporting the mezzanine floor.
The tower section and the arched roof structure are independent and there are no
structural interconnections.
Page 2 of 3
Bidvest Port Operations – Report on Demolition to Upper Section of Quince Warehouse
3.
SKP Engineers cc
CONCLUSIONS
Since there are no connections between the tower structure and the arched roof, the
tower structure and its supporting mezzanine floor may be demolished, without affecting
the structural integrity of the warehouse.
After removal of the tower section, it will be necessary to provide additional galvanised
steel purlins and aluminium roof sheeting to reinstate the weather proofing of the
structure. This will include the installation of the upper ventilation section, to a similar form
as the existing roof.
A quotation has been requested from Avellini Bros for this work, which will be forwarded
on receipt.
Report prepared by:
S. OSBORN
_________________
S. Osborn Pr Eng
SKP ENGINEERS
Page 3 of 3
Download