Section 900 - Submittal Procedures

advertisement
SECTION 900 – SUBMITTAL PROCEDURES
SUBMITTAL PROCEDURES
PART 1 – GENERAL
1.01
Section Summary
A.
1.02
General procedures for submitting documentation during the course of the
Contract.
Sequencing and Scheduling
A.
Upon receiving submittals, the Engineer will require ten (10) days to review
the submittals. A period of fifteen (15) days will be required if an outside
consultant must be used.
B.
Allow enough time for review of the submittal by the Engineer, no Contract
Time extension will be granted for failure to transmit submittals in advance
of the work.
PART 2 – PRODUCTS
(Not Used)
PART 3 – EXECUTION
3.01
3.02
Contractor’s Construction Schedule
A.
Submit preliminary schedule and progress schedule at the preconstruction
conference consistent with Section 235 of the Specifications.
B.
At least once a month, provide the Engineer with a revised schedule.
Identify areas where progress is ahead or behind schedule.
Emergency Contact List
A.
3.03
Before work can begin, submit a typed list of 24 hour on-call personnel for
the Project. This list shall include all key personnel.
Shop Drawings and Manufactures’ Information
A.
Conform to the general requirements of Section 206 of this Specification,
except as modified herein.
B.
The minimum sheet size shall be 8-1/2 inch x 11 inch. No sizes above
11x17 will be allowed. Non-legible copies will not be reviewed.
2013 City of Minot
1
Section 900
Submittal Procedures
C.
D.
3.04
2.
Date of submission and date of any previous submission.
3.
Names of: Contractor, subcontractor, supplier, and manufacturer.
4.
Identification of product and Specification Section number.
5.
Identification of revisions from previous submittals.
6.
A 4x4 inch blank space for the Engineer’s stamp.
Engineer will stamp shop drawings and indicate requirements for
Contractor’s review or resubmittal as follows:
1.
No Exception Taken
2.
Make Corrections as Noted
3.
Revise and Resubmit
4.
Rejected See Remarks
Conform to the requirements of Section 1400 of this Specification.
Submit 1 copy of all inspections, tests, and approvals required in the
Specification.
Specification Section Submittals
A.
3.07
Project title.
Test Reports
A.
3.06
1.
Operation and Maintenance Manuals
A.
3.05
Submit a minimum of 2 copies of shop drawings, plus the amount of copies
the Contractor wants returned. Each copy shall contain the following
information:
Each section in this Specification may have submittals required for the work.
Follow the requirements of this section and section 206.
Measurement and Payment
A.
All work and costs of this Section shall be incidental to the Project.
END OF SECTION
2013 City of Minot
2
Section 900
Submittal Procedures
Download