MnSCU Predesign Guidelines and Review Form Last Revision: February, 2006 PREDESIGN REVIEW DEPARTMENT REVIEWER Predesign Submittal Requirements Predesign Format Predesign Resources / Special Considerations INSTITUTION Facilities Programming and Planning Sally Grans (651) 296-7083 Gillian Machacek (651) 282 5217 PROJECT NAME 01/01/2006 RECEIVED CONSULTANT CONTACT REVIEWED 01/01/2006 1. 50% submittal: 1 copy 2. 100% submittal: 3 copies in binders + 1 pdf. file on CD ▪ Clearly label both front and spine of binders with - institution name - submission status (50%, 100%) - consulting company name - date ▪ Use a text font no less than10 points ▪ Number each page per section ▪ Ensure entire document is black/white reproduceable Organize in the following Sections: 1. Cover Letter (2) 2. Predesign Summary Statement 3. Project Background Narrative 4. Project Description 5. Sustainability: Energy Standards 6. Information Technology Plan/Budget 6. Financial Information – Capital Expenditures 7. Financial Information – Operating Expenditures 8. Project Schedule 9. Appendix Predesign Resources: ▪ Previously submitted Predesigns are filed at the Office of the Chancellor, Facilities Office. These are available for your review; contact Facilities Staff Mailor 651-296-6947 or Nancy 651-2977862 to confirm hours of operation. However, it is important to have professional staff guide and suggest similar or other predesign documents that have similarity or validity for your project. Thus, please contact Gillian Machacek (651) 282 5217 or Sally Grans (651-296-7083) to schedule a time when one of them may assist your review. ▪ MnSCU Facilities website under Predesign heading (www.facilities.mnscu.edu): - Predesign Review Form (Feb, 2006) - Update to the Predesign Guidelines presentation (Jan, 2006) ▪ Predesign Manual for Capital Budget Projects (Revised July 2002) (provide website here) Predesign review sg/gm 02-15-06 Page 1 MnSCU Predesign Guidelines and Review Form Last Revision: February, 2006 1. Cover Letters Review Comments 2. Predesign Summary Statement Following Facilities approval of the 100% review; cover letters to be submitted for inclusion in the document: ▪ Letter #1 – Consultant to campus president affirming that the report meets MnSCU criteria, signed by a registered architect/engineer with accompanying registration number. ▪ Letter#2 – Formal submission letter from the Campus President to Al Johnson, Associate Vice Chancellor of Facilities, MnSCU Provide a concise overview of the project describing: ▪ scope of work ▪ academic and operational programs affected ▪ project size and major components of the work ▪ deferred maintenance, renewal issues and FCI addressed in the project scope ▪ cost breakdown relating to demolition, new construction and renovation where applicable. ▪ project schedule including milestone dates ▪ funding sources for the project. ▪ include the “building Project Data Sheet” in the appendix Explain the basic information: who, what, where, how, why and when? Review Comments: 3. Project Background Narrative Provide the detail relating to the project process and academic and operational programs. ▪ Restatement of the statutory requirements that drive the project’s operational program. Include any past appropriations. State “There are no statutory requirements tied to this project.” if not applicable. ▪ Statement of the relationship between this project and the updated Facilities Master Plan. ▪ Specific academic operational programs being provided for by the project. Note other issues relating to strategic plan: access, enhanced, learning or workforce and economic vitality. List alternative program delivery, site or building options. ▪ Course schedule and academic program information related to the project program. ▪ Summary of the project planning process, participants and significant outcomes during the process. ▪ Facilities systems summary including, - Deferred maintenance backlog - FCI (Facilities Condition Index). FCI=deferred maintenance/replacement value. - Future renewal needs data obtained from the FRRM, Facilities Reinvestment Renewal Model. ▪ Space utilization analysis based on current data: include any pertinent sheets. Verify that the data used is from the most recent Office of the Chancellor studies. Note the requirement for consideration of MINNCOR Industry products for the project. This requirement is set forth in the Laws of 2002, Chapter 393, Section 39 which amend Minnesota Statute 16B.335, Subdivision 3c. Place detailed information, including meeting minutes, in appendix. Review Comments Predesign review sg/gm 02-15-06 Page 2 PREDESIGN GUIDELINES AND REVIEW FORM 4. Project Description 7/28/2016 Provide detailed information relating to the design intent, project program and project process. 1. State the purpose and rationale of the projects. ▪ Explain the project relationship to the updated facilities master and academic plans, workforce and economic development, access goals and objectives. ▪ Describe academic, operational, workforce or access needs fulfilled by the project. ▪ Describe site selection criteria, analyses and evaluation of alternative options. ▪ Include site plan of proposed project site and all other graphics that can visually assist in describing the project. 2. Provide complete program detail. ▪ Physical condition audit and recommendations. Note: any renovation project must include detailed photos of the interior and exterior spaces. ▪ Deferred maintenance backlog and renewal data. ▪ Space Utilization Analysis. Obtain (from campus) and utilize the most current ISRS database information in analysis. ▪ Current conditions, adjacencies, spatial issues and user needs. Incorporate Room Data Sheets for each space. Contact Facilities Planning and Programming for examples of Room Data Sheets. ▪ Specialty Requirements: State design standards, space guidelines and performance characteristics for site and building programs. ▪ Bibliography of applicable codes, standards, cited research and publications referenced. 3. Provide process and options information. ▪ Detail the project process. Include supporting materials such as meeting minutes, studies, etc. ▪ Provide project alternative analyses relating to program delivery, site options, building options, etc. Review Comments 5.Sustainability/ Energy Standards ▪ Address energy conservation and sustainability issues/solutions that may or could be applicable to this project. ▪ Factor in additional funding in response to legislation that will outline sustainability guidelines for all state projects. Beta (test) guidelines are available at www.csbr.umn.edu/B3. ▪ Note that the B3 Guidelines are applicable to all new buildings and must also be implemented where feasible in renovations. The following list outlines the major sustainability categories: - energy modeling of building design and operations - energy load reduction - increased efficiency, mechanical systems - use of renewable energy sources - improving air quality - building materials; conservation of building material resources - managing water; emissions to air, water - enhancing bio-diversity and ecology - site design and operations - waste reduction and recycling - designing for increased flexibility - improving human design factors Review Comments Predesign review sg/gm 02-15-06 Page 3 PREDESIGN GUIDELINES AND REVIEW FORM 6. Information Technology/Plan Budget Review Comments 7. Financial Capital Expenditures Review Comments 8. Financial Operating Expenditures 7/28/2016 ▪ Briefly summarize the institution’s Technology plan and current Information Technology infrastructure. ▪ Describe the technology applications and associated budget detail included in the scope of this project. ▪ Describe the impact and improvements, including cost effectiveness, that the project will have on current and future infrastructure. ▪ Detail additional positive outcomes that may be a direct or indirect consequence of technology implementation associated with this project. Example: providing more services electronically increases access (internet courses) which increases student enrollment. A longer term outcome of this may be a potential reduction in space requirements. Estimate the capital expenditures for the project. ▪ Include a cost plan using the approved state forms and a schedule displaying all capital funding requirements through the life of the project. Campus and Office of the Chancellor to assist in the various non-construction categories. ▪ Provide project gross square footage and separate line items for new construction cost and renovation costs. ▪ Document budget and schedule impact for atypical considerations/circumstances that may affect the project. Note: if any variances to the MnSCU Design Guidelines are assumed to be part of this construction budget then approval from Office of Chancellor required. ▪ When available, include actual cost histories, adjusted for program variations, that support the proposed budget. ▪ Identify project funding sources including state capital bond, revenue bond, etc. ▪ Reference other cost estimation examples - i.e. other campuses or other regional facilities whose construction cost impact relate to the project. ▪ Identify any alternative delivery methods such as design build, construction management, etc. that impact the schedule or overall budget. ▪ Estimate the project effects on operating budgets associated with the design, construction, occupancy and on-going operation of the project area. ▪ Quantify the on-going operating expenditures and revenues. Use a state form to describe and schedule operating revenues and expenditures associated with the occupancy and operation of the project area. ▪ Include staffing levels and corresponding salaries, building repair, replacement and maintenance. Example 1: impact of additional maintenance engineers required during and/or after new building construction. Example 2: Operating cost for energy (HVAC, electrical and other utilities). $5-$9 is suggested to reflect these associated costs. ▪ Campus to address debt capacity and the institution’s ability to pay debt. Verify information with Facilities Business Support Unit. Review Comments Predesign review sg/gm 02-15-06 Page 4 PREDESIGN GUIDELINES AND REVIEW FORM 9. Project Schedule 7/28/2016 ▪ Graphically convey a realistic schedule for all project stages including site selection and acquisition, required government actions and proceedings at all levels, designer selection, design approvals, construction occupancy and commissioning. ▪ Suggest incorporation of a bar chart as this best illustrates the project schedule from schematic design through completion. ▪ Include review time after each design phase for the appropriate campus staff, project manager and Office of the Chancellor Program Manager: 2 weeks to 6 weeks depending on size and complexity of project. ▪ Approval by the Office of the Chancellor of all projects after Schematic Design phase is required. This is a two step process. Project documents are submitted to the Program Manager and two-three weeks following there is a meeting with the consultant and campus. Issues are discussed and upon agreement there is a formal presentation for actual approval of the Schematic Design to the Associate Vice Chancellor for Facilities and the Vice Chancellor CEO. Schedule to note 16.B335 Legislative approval after Schematic Design which runs concurrent with Design Development - but which must be approved from Legislature prior to starting Contract Documents. ▪ Designer Selection Board required on projects over $2 million in cost. Selection of a designer may begin prior to the actual appropriation (although no work can begin until it is approved). Review Comments Appendix All supporting information should be included in appendices that will assist in the development of the project as it proceeds into design, construction and on-going operations: Include all research and reference material meeting minutes, academic master plan reference material, technology master plan reference material, ISRS Space Utilization data, FRRM Data, workforce or demographics data, other studies or related supporting information, project visit notes, websites. Additionally, in the appendix place minutes of meetings as appropriate which document who was involved and how the decision making process was derived. Include any pertinent notes of other informational pursuit, project visits, websites, etc. Review Comments General Comments Predesign review sg/gm 02-15-06 Page 5