PURCHASING SECTION 6645 – 148th Street, Surrey, BC V3S 3C7 Tel: 604-590-7274 Fax: 604-599-0956 E-mail: purchasing@surrey.ca ADDENDUM #3 REQUEST FOR QUOTATIONS (RFQ): TITLE: #1220-41-28-09 FIELD HOUSE BUILDING CONSTRUCTION ADDENDUM ISSUE DATE: NOVEMBER 13, 2009 REVISED CLOSING DATE: PREFER TO RECEIVE QUOTATIONS ON OR BEFORE Friday, November 20, 2009. Information for Contractors The following information is provided to clarify information and to answer questions raised by Potential Contractors prior to the deadline for questions or standards and specification clarification. This addendum #3 contains 8 pages in total. REVISED CLOSING: The RFQ closing date is being extended to Friday, November 20, 2009. Standards and Specification Clarification: We require the following clarifications Q1: The correct location of the plumbing rough in in the multi purpose room. Drawing A2 indicates the rough in on the east wall, while drawing M2 calls for it on the West. A1: Correct location for plumbing rough in at the wall between the multi-purpose room and the storage room, as shown on drawing A2. Q2: The correct framing details for the wall between the multi-purpose room and the storage room. Drawing A2 calls for 2X4 studs at 16” o/c while A8 calls for 2X4 studs at 12” o/c. A2: Correct spacing is 12” o/c. Q3: The correct bolt size for the change room bench supports. Drawing A4 detail 1 calls for a 5” bolt with a 6” penetration (which is not possible), yet the detail calls for 4”. Is the 5” bolt with 4” penetration correct, or is it to be a 7” bolt with 6” penetration. A3: Precast supplier will provide inserts. See comments after Answer A16 which indicates in more detail what Precast Supplier will provide. Q4: Coat hooks and supports, as indicated on A4, A4: Description of sizes is referred to in the notes on Drawing A4. Q5: The crezon board is currently only shown to be filled and sanded in the multi-purpose room. Is this to be applied to all rooms? A5: All ceilings to have Crezon boards filled and sanded, and drawing currently shows ceilings at change rooms and washrooms are painted. 1 Q6: Is crezon board to be installed in the storage room? A6: Yes Q7: Door sizing. Addendum 1 still leaves it unclear as to which takes precedence. Drawings call for a 6’8” door height, while the specifications call for a 7’0” door height. A7: Make all man doors 6’-8” high. Q8: We request to change the coating on the steel brackets for the bench supports, as well as the coat hooks, from “powder coating” to “Epoxy Paint”. A8: Epoxy Paint is acceptable. At the site meeting, it was indicated that the block walls will be changed to pre-cast. We require the addendum for the change from block wall to pre-cast panels with the following Q9: Maximum panel weights. A9: Not sure why this is relevant, Precast Supplier is installing the panels. Interior walls will be 75 psf, exterior walls will be approximately 85 psf. Q10: Will coring be required now for the plumbing and electrical? Q10: Some coring may be required for plumbing, will provide block outs if they can be determined prior to pouring precast panels. If block outs are provided, will have to grout in as required. See the comments after Answer A16, indicates Electrical conduits and boxes that will be provided by Precast Supplier. Note conduits will stub up to top of Precast panels. Q11: Will the top plate be preinstalled for the installation of the roof trusses. A11: No, inserts will be provided at top of Precast panel in order to bolt top wood plate to top of precast panels. Q12: Footing/slab/panel connection detail. A12: Precast manufacturer will provide dowel layout, GC will have to supply and install approx. 24 vertical rebar projecting 15” out of the footings, waiting for more details from Precast manufacturer. Q13: S1 shows 7 door openings on the West side. A2 shows 8. A13: Drawing A2 is correct. Q14: S1 shows 2 door openings on interior wall at South end. A2 shows 2. A14: Drawing A2 is correct. Q15: Foundation walls have no Horizontal wall reinforcing shown (2 Bot. of footing and 2 Top of wall and nothing between). A15: Since we are now going with Precast walls, there will be no foundation wall, only Footing. 2 Q16: 15M dowels @ 1200 alternating every 3rd with 20M should read 15M @ 400 alternating every 3rd @ 1200 (see below) A16: Not relevant, since walls are now going to be precast. Precast Panels, that are going to replace all the Block walls. The following is scope of work that will be provided by the Precast Supplier: 1) Exterior wall panels at approx. 11’-6” (most likely will be closer to 11’) high, with "striated broom" exterior finish (and smooth on the interior). (11'-6” wide panels are the maximum width we can ship, without using a pilot car.) Overall insulation value of R20. You may need to tweek the thickness of your footing a bit to get the required elevation for your intended "top of wall" elevation. The panels along the two long walls would be 21.4' long. The exterior corners would be mitred. 2) The interior walls would be 6" solid, with an overall height of 11'-2" (most likely will be 10’-6” high). These 5 walls would span across the building and be supported on the inner face of the exterior walls (by utilizing a weldplate and a supporting ledger angle) at the lower corners. You would not need a specific footing under these panels. You would run reinforcement for your floor slabs through notches in the lower edge of our panels and have a thickened floor slab beneath the panel. Top edge of the interior panels will be at same elevation as top edge of exterior panels. Bottom of these panels will be approx 6” below typical slab elevation at exterior doors. **Note that exterior footings will have to be increased in size to support additional weight of 3 these panels, but revised Structural drawings are not available at this time. Allow in your quotation for the footing size and quantity as shown on Structural Drawing, and if quantity of concrete of final Structural drawings exceeds what is currently specified, this will be treated as extra to your contract. 3) Precast panels at the interior "entry" (acting as "pass-thru's) to the changerooms, that go down to top of footing elevation... you would need a small strip footing here for us to set those panels into final position. Have also allowed for precast panel at sides of urinal, allow for footings below these panels. 4) All panels installed complete with: a) b) 5) Grouting of all underside bearing surfaces. Top of footing to be installed to tolerance of plus or minus 3/16” of required elevation. Panel/panel welding (and all connections are non-visible after caulking is installed).Interior and exterior caulking with a polyurethane (paintable). c) Temporary pipe bracing (until roof diaphragm is established). d) Our sealed shop drawings and Engineering seal Miscellaneous Items", including the following: a) Ferrule inserts (usually 5/8" dia.) cast into the top of our panels at 2-1/2" o/c (Structural Engineer will establish prior to fabrication) for bolting of the top bearing plate (i.e. General contractor to supply and install 2” x 8”), to our panels. b) Man door frames cast into our panels... frames to be supplied, by Others. (Due to timing, most likely General Contractor will have install these to Rough opening provided by Precast manufacturer, and should allow for in General Contractor’s budget) c) Rough Opening for roll-up door at the Storage Room. d) Inserts (or notches for the 6" solid panels) at 3' o/c for tieing the wall panels to the floor slab (using threaded dowels). (Dowels to be supplied by General Contractor.) e) "Electrical embedments" for: - 3 door opener buttons and conduit. - two recessed hand dryers. - 12 exterior lights. - 2 exit signs - 7 wall plug boxes and conduits at Multi-purpose room - 2 wall boxes and conduits for Thermostats in Changerooms f) Thickened concrete interior wythe in region of H/C grab bar, for good anchorage of fasteners. g) Embedded inserts for the benches and coat hooks, so site fasteners are accommodated. The inserts for the benches would be a galvanized-style unit, so that "plated" N/C fasteners can be threaded directly into the insert. Comments: 1) Not applicable 2) Panels would be secured to the footing via a dowel bar/grout sleeve connections. This means that the footing contractor would probably need to install approximately 24 vertical rebars projecting 15" out of the footing. (We would provide a dowel bar layout, with our shop drawings.) 3) Delivery: approx 1-1/2 week to complete shop drawings, and 2 weeks for precasting. We would complete installtion in 2 working days. 4) Panel Finishes: Pricing is based on our standard "striated broom" finish. 4 41-28 Field House Precast Pictures.doc Q17: Concrete specification. A17: Lafarge has reviewed the concrete specification and has the following qualification/clarification request(s). Mix Design Submittals Lafarge will submit a Mix Submittal Sheet (MSS) indicating whether a constituent is present or not in each mix design. The MSS will also indicate CSA concrete classification, air content and category, mix slump, and maximum water to cementitious ratio. O.K. Concrete Properties The air content for the concrete is specified at 5%+/-1%. Lafarge requests that air content for concrete to be changed to an air content of 5.5% +/- 1.5% as per CSA definition of C4 or F2 exposure class concrete. The slump for the concrete is specified at 50mm +- 13mm. Lafarge requests that concrete specified at50mm +-13mm to be changed to 80 +- 20mm. The concrete mix is designed to perform at 80mm slump. However, Lafarge can deliver 60mm slump if 60mm slump is requested when ordering through dispatch. Quotation is based on the acceptance of this request. 80 mm slump is ‘acceptable’ Q18: Exterior Blocks Walls: - the elevation drawings show both a standard concrete block and a split-faced concrete block. Is it one or the other? Or is there course of bands of split-faced blocks and standard block? If so what's the pattern? A18: Not relevant, since Precast walls will replace all block walls. Q19: States that the Contractor will not be required to provide: services, excavation and backfill, landscape and asphalt. Yet the Schedule B Appendix 2 Supplementary Specifications appears to indicate that the Contractor shall provide site services, testing of excavation and backfilling. We intend to provide our quotation as per the Special Provisions unless advised otherwise. This would include that the backfilling to the underside of the slab on grade is not required to be done by the Contractor. A19: City has provided Excavation and backfill to underside of footing. General Contractor (i.e. GC) to proof roll and call for Geotechnical inspection (i.e. initial inspection paid for by City) prior to installing Footings. GC to supply and install balance of backfill material to underside of building slabs and within 6" of finished grade at exterior of building (assume backfill at exterior of building to 6" below top of slab at exterior door locations) GC Should review site conditions prior to providing quotation, and review Geotechnical report. Q20: It states that the City of Surrey shall install the site hoarding and will be maintained by the Contractor. Yet other documents appear to indicate that the hoarding be provided by the Contractor. We do not intend to provide this hoarding. A20: As per site meeting, City has installed and will pay for fencing, GC to maintain fencing while they are responsible for the jobsite. Q21: Permits and Fees; It appears clear however other documents indicate that the Contractor shall include for any deposits for the site services but yet the site services are not within our scope of work. Also the extent of inspection costs which the Contractor shall include for is unclear. What specifically is the Contractor to include for? Example; soils testing, concrete testing, painting inspections, roofing inspections. A21: City pays for Building Permit and permits related to underground services that they have provided. GC pays for all trade permits not paid as part of Building Permit. City will pay for initial inspection fees. Should re-inspection be required, the cost of re-inspection will be paid by the GC. 5 Q22: It states that the City shall supply the plumbing fixtures, yet other documents indicated some fixtures supplied by the plumbing contractor. We will include that the City will provide the plumbing fixtures as stated which includes the faucets which are plumbing fixtures, unless advised otherwise. A22: The City to provide list of Fixtures that City is going to order. This information is currently unavailable. The City will continue its best efforts to obtain this information and release it in a future addendum. Schedule B – Appendix 2; Supplementary Specifications. Q23: It states that the roofing shall conform to RCABC but yet it does not state that we are to include for a RCABC warranty. As you probably know a RCABC warranty can be pricy and some clients do not wish to have this warranty. Are the Contractors to include for a RCABC warranty? A23: RCABC Warranty is not required. Roofing contractor is to provide written 5 year warranty on roofing, flashing and snow Guards. Q24: It states that “Field Engineering is not to allowed”. What does this mean? A24: Not sure where this is specified, all engineering services will be provided by City, unless specifically specified otherwise. Q25: It implies that the Contractor shall perform a degree of site preparation, yet the Contractor is not required to perform the excavation and backfill. We do not intend to include for any site preparation unless advised otherwise. A25: Site preparation has been provided by City to underside offootings. See Answer A19. Q26: It states that the Contractor shall pay for the meter and connections fees, yet in Appendix 1 the Contractor is not responsible for anything beyond 4’-0” from the building. We do not intend to include for any connection fees, inspections or meter costs for work beyond 4’-0” from the building unless advised otherwise. A26: City will pay for meter and connection fees Q27: Please note that the Division 16 is headed as Mechanical. We realize that the intent is Electrical. A27: Division 16 headings should read “Electrical”. Q28: Why is it stated that the Plumbing Contractor shall design the domestic water, sanitary and storm systems when they are defined on the drawings. We assume this is an oversight and do not intend to include for design work unless advised otherwise. A28: Mechanical engineer will provide design of water, sanitary and storm systems. Q29: Which wiring connection box is the electrical contractor expected to design? A29: See Electrical drawings, these will take precedence Q30: What type of Heavy Duty Galvanized Roll up Door shall we include for? A30: See Addedum # 1 for details. Q31: On drawings M-2 and M-3 it states to provide separate pricing. Where and how do you wish this identified on the tender document? A31: Firstly, this is NOT a tender document. Please do NOT identify it as such. Note, perimeter drains are not required. Add your separate pricing in Schedule C – Section 2. Q32: A cross section of the exterior wall states “glass blocks” yet no glass blocks are shown on the elevations. Are there glass blocks and if so where? A32: No glass blocks are required, obsolete note on Structural Drawing. 6 Q33: Details required for the snow guards. A33: Roofer to size appropriately, they can look at Roof that was provided at Tom Binnie Field House Building in Whalley, adjacent to BC Lions training facility. Q34: We assume that the ceiling design meets the design requirements for the fire rated ceiling. Please advise if this is not the case. A34: 5/8" drywall to be installed as specified on drawings, complete with fire taping. Clarifications: 1. General 1. Page 4, Section 17 Bonding. This section is deleted in its entirety. 2. Page 6 and Page 23 drawing Numbers (As per drawings on FTP site), Architectural Drawings: Drawing A1 rev 2 October 21 2009.pdf Drawing A2 rev 2 October 21 2009.pdf Drawing A3 rev 2 October 21 2009.pdf Drawing A4 rev 2 October 21 2009.pdf Drawing A5 rev 2 October 21 2009.pdf Drawing A6 rev 2 October 21 2009.pdf Drawing A7 rev 2 October 21 2009.pdf Drawing A8 rev 2 October 21 2009.pdf Electrical Drawing E1 Drawing E2 Drawing E3 Drawings: rev. 5, October 23, 2009 rev. 5, October 23, 2009 rev, 5, October 23, 2009 Mechanical Drawing M1 Drawing M2 Drawing M3 Drawings: rev. 7, October 21, 2009 rev. 7, October 21, 2009 rev. 7, October 21, 2009 Structural Drawing: Drawing S1, (no date) 2. 3. Page 10 delete clause 3.4 in its entirety. 4. Page 16, clause 23 makes reference to “Consultant”, change to “Contractor”. 5. Page 25, clause a) ii no perimeter drain tile is required. 6. Page 26, clarification, Forum Projects is not registered company bidding. CF Projects Inc. will be submitting a quotation. 7. Page 41, item .1 delete all reference to Master Municipal Construction Document (MMCD) specifications and general terms and conditions. 8. Page 43, item 9.2 delete reference related to river sand, leave comments related to refer to Geotechnical report. 9. Page 47, item #03300.7 add comment “rigid insulation under membrane”, see Architectural drawings. 10. Page 52, Division 7, Section 07110 (Elastomeric Waterproofing) –Delete this section; Section 7210.1 (Building Insulation), delete 2 nd sentence in its entirety. 11. Page 53, Division 7, Section 07410.4, (Metal Roofing), delete 1st. sentence in its entirety. 12. Page 64 to 68, Division 16 page heading should be changed to “Electrical”. Doors and Frames: 1) Add Kick-plate GSH 80A 10 x 34 STSMS 32D Required for Doors 1 to 7 7 3. 2) Add latch protector 804 11" x 3" CAD, Required for Doors 1 to 8. 3 For doors no. 8, allow for Heavy Duty ND Series, passage set would be ND10S RHO 626, no dead bolt required. 4) Clarify that all man doors to be 16 ga. and door frames to be 14 ga. 5) Clarify that Electric strikes are to be provided by City. GC to confirm with Parks Department prior to ordering frames as to specification for the Electric Strikes and prep the door and frames appropriately. 6) All door hinges to be FBB199 4-1/2" x 4-1/2" NRP 32D. 7) Provide welded reinforcement at all hinge locations in Door frames. Roofing contractors, underlayment specification has been changed by the Metal Roofing supplier. Please refer to the following pdf files. 41-28 Nova Seal Data 1 of 2.pdf 41-28 Nova Seal Data 2 of 2.pdf 41-28 Westform Reference.pdf PAINTING ALL WALLS AND CEILING In Schedule C – Section 2 indicate optional price for painting all walls and ceiling (Assume same colour as Change-rooms) at Multi-purpose room and Storage room, plus concrete seal coat on concrete floors at both of these rooms. END OF ADDENDUM All Addenda will become part of the Contract Documents. 8