University of Colorado - Colorado Springs 1st Floor Renovation University Center

advertisement
University of Colorado - Colorado Springs
1st Floor Renovation
University Center
Bidding Questions
March 21, 2011
Questions received on March 21, 2011 in "Request for Information No. 1"
Question 1:
Item No. 1 of the Supplemental Information for Bidder in Addendum No. 1
references Article 46 of the General Conditions of the Contract, Time of
Completion and Liquidated Damages. The General Conditions are not included in
the Specifications nor are they on the UCCS Projects out for Bids website. Please
provide a copy of the G.C.'s.
General Conditions now posted.
Question 2:
Please provide reinforcing detail or requirements for the Steps, Walks, and Stem
Walls at the new Entry shown on sheet A-601.
Response:
Refer to structural drawings S-100 for structural requirements on all Steps, Walks
and Stem Walls.
Question 3:
Presently, Area C must be completed by May 15, 2011. This area includes the new
Information Desk with the curved Veritas panels. My best information currently is
that the panels will require 1 to 2 weeks for shop drawings, architectural approval
of a couple of days, manufacturing and delivery time of 4 weeks, and installation
of 1 or 2 days. At best case, the General contractor will have to have his contract
in place no later than April 3 to have any chance of making this schedule work.
Please note, this is assuming that the General Contractor receives the shop
drawings in 1 week. When is the anticipated contract date?
Response:
Curved Panels can be installed after the May 15th date as long as desk is
operational by May 15th. Contractor to coordinate exact construction sequencing
with owner.
Question 4:
The Comments on the Door Schedule says to sand and apply stain finish at the
existing doors. Please verify that this is the extent of the repairs that will be
required on the doors.
Response:
The intent is to refinish the doors to the greatest extent possible. Contractor to
work with Architect on final treatment. A dark stain in anticipated to hide
blemishes and a polyurethane final coat is required. All of the existing hardware
will be reused.
Question 5:
Will this project be permitted and inspected thru the City of Colorado Springs or
the State.
Response:
There is no formal permit, instead, a State inspection representative will provide a
Letter of Compliance to be kept on site during construction. The GC is responsible
for scheduling State inspections.
Questions received on March 21, 2011 in "Request for Information No. 2"
Question 1:
Where new opening are being cut into existing walls, will temporary security walls
be required between the work space and the non-work space or will dust protection
be adequate.
Response:
Time sequence of demo and new installation should be kept to a minimum.
Coordinate exact hours of operation with User. Provide temporary security
(plywood sheet, frame, and hasp/lock set with keys as required) at the end of each
work day.
Question 2:
Please provide specs for the PVC column cover located at Area C Info Desk.
Response:
New PVC column cover will be eliminated from scope of new work. Intent will be
to keep existing column cover, patch and repair cover as required. Note 10 on AD100 to be removed from construction documents.
Download