02-05-2014 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
February 5, 2014
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Assembly Building (Sanctuary): Design and Construction of sanctuary
building of approximately 6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
August 2013
Design Development October 2013
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Design Committee attended a
kick-off meeting on December
20, 2013. Follow-up meeting
was held on January 29 to
review design development.
2.
New Housing Clubhouse Building: Design and Construction of a new Clubhouse to
service the housing units in the core campus. Program calls for a 15,000 GSF building to
contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450
students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900
students.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
August 2012
Design Development October 2012
Select CM
January 2013
Construction Docs.
March 2013
Construction
May 2013 to July 2014.
Changes from last month:
Project is currently under
construction and on schedule.
There are no issues at this
time.
Zak Ovadia
1
3.
Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking
deck over part of an existing lot south of the FAC. Consultant tested the feasibility of
adding additional parking levels to tie to the existing Fine Arts Garage. Program calls
for a minimum of 170 stalls to serve the residential population. Currently the design
provides over 550 stalls.
Tentative Schedule:
Programming
August 2013
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
Completed
Design Development October 2013
Select CM
January 2014
Construction Docs.
March 2014
Construction
Must be occupiable by January
2015
Changes from last month:
CM short-listing concluded on
January 23 with three firms
invited for interviews.
.
6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball
courts and general extensive renovations to the Aquatic Center to eliminate the pool.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. November 2013
Program Verification December 2013
Schematic Design
January 2014
Design Development February 2014
Select CM
March 2014
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Project Committee attended a
kick-off meeting on December
10. Schematic Design started.
ZO reviewed concept with
RDB on January 24 before the
committee meeting.
Zak Ovadia
2
7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size
pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
President endorsed the
nomination of EMO
Architects as prime
consultant. Kick-off meeting
will be scheduled shortly.
8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming,
Schematic Design, Feasibility Study to re-purpose this building. Program will
include Skinner-Jones Hall SOUTH as well as other buildings having related
departments (Math, Engineering, Health, etc).
Tentative Schedule:
RFQ for Consultants August 2013
Short List for interview September 2013
Programming
November 2013
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Kick-off meeting was held on
Friday January 17.
Discussion of space needs
occurred. Meeting Minutes
distributed for concurrence.
7. Library Learning Commons: Reconfigure First and Second Floors to create a studentcentric learning commons. Co locate the Help Desk from Bldg 15, and remodel
entry lobby.
Tentative Schedule:
Programming
February 2014
Program Verification March 2014
Schematic Design
March 2014
Design Development April 2014
Construction Docs.
May 2014
Construction
July 2014
Changes from last month:
This is a new space and
function needs to be
completed ASAP in 2014.
Zak Ovadia
3
9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of
magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule:
NO CHANGE.
10. Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
Zak Ovadia
TBD
TBD
December 2012
NO CHANGES
4