DW MINUTES FROM 4/21/10 I Call To Order Mae Sakamoto called the meeting to order at 11:00am on April 21, 2010. II Attendance Present: Komal Bandyopadhyay, Brent Gilmore, Jay Field, Janice Miller, Eva Bagg, Mae Sakamoto III Agenda Items 1. DW Implementation schedule discussion As there had not been any discussion regarding implementation timeframes prior to this meeting the group discussed what the expectations were. Janice expressed that she would like to see the delivered reports from Phytorion rolled out to the Deans/Dept Head by first week in August with training being conducted during this time. The group also proposed having the Core team training done during weeks of 5/31 and 7/5 with business analysts training on week of 7/12. Mae would contact Phytorion to work out schedule time frames with them and get back to this group. There was some concern expressed with the tight schedule and other projects concurrently occurring but the agreement was that the rollout would be the delivered canned reports and not necessarily the capability to create ad-hoc reports by Deans. There were also concerns regarding the level of support and training which may be needed in rolling the canned reports at the beginning of the Fall term. It was also not expected that the Business Analysts would necessarily be able to generate requested reports out of the warehouse by this time as there is a large learning curve in understanding the data. Phytorion’s original schedule was to be completed at LBCC by end of May. Due to resource constraints on LBCC side, delays have pushed out the schedule to roughly August. In order to not delay further, this schedule is being pushed to allow Phytorion to wrap up LBCC project in a timely manner. Testing of 9.0 with data warehouse still needs to be conducted. Phytorion would be providing their estimate of differences and what it would take to make the corrections. It is expected that we will be taking the data warehouse down when the PS 9.0 upgrade is occurring. Notifications will be sent out accordingly. Janice expected to complete current validation efforts by early June. She has been meeting with various business analysts to review data. She also indicated that she had started to run a few delivered reports and packages as she is somewhat familiar with the Cognos tools. As all business analysts have busy schedules already, it was mentioned that we need to consider their overall schedules in this schedule planning. Brent also has planned another rollout for EP data come early June which hopefully will go smoother than the last run. The last run was significantly negatively impacted due to incorrect advice from consultants regarding system configuration. IITS teamed with IBM for 2 weeks to get this issue hopefully resolved so we’ll see in the next cycle. We rely on Brent to provide the validation of the process. IV. Adjournment Mae adjourned the meeting at approximately 1:00 pm. The next meeting will be scheduled after Phytorion’s response is received regarding scheduling.