G e i s i n ge r G ray ’s Wo o d s Ambulatory Care Campus Phase I Erica L. Craig Construction Management The Pennsylvania State - D r. Riley University G e i s i n ge r G ray ’s Wo o d s Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Building Functions 70 Exam Rooms, 16 Procedure Rooms, Imaging Center, Laboratory Services, On-Site Pharmacy Multi-Specialty Out Patient Services: OBGYN Practice, Pediatrics, Family Medicine Building Size: 64,350 SF Construction Costs: $15 Million Construction Dates: April 07’ – June 08’ S t a t e U n i v e r s i t y Specialty Services: ENT, Cardiology, Urology, Ophthalmology E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview P r o j e c t Te a m Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Project Site Plan Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a 52 Acre Lot Off I-99 Interchange S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Structural System CIP Concrete Pier Foundations ASTM Structural Steel Framing Concrete Slab on Composite Metal Decking S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Electrical System Mechanical System 2500A, 480/277 Volt Service 400-Ton Cooling Tower 250 kW, Diesel-Driven Emergency Generator Water-Cooled 250-Ton Electric Chiller Three 19,000 CFM Modular Rooftop Air-Handling Units T8 Lamps, Compact Fluorescent, Occupancy Sensors S t a t e U n i v e r s i t y Gas Hot Water Boiler E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Building Envelope Aluminum Curtain Wall System on Metal Studs Brick Masonry and EIFS on CMU and CIP Concrete Walls Metal Roofing System and Skylights on Metal Studs S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Green Roof System Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Roofing Systems Aluminum Metal Roof System with Skylights on Front Sloped Roof Cool Roof on Main Flat Roof Cool Roof System Metal Roofing System S t a t e U n i v e r s i t y Green Roof on Separate Chiller/Boiler Room Systems used primarily to obtain LEED Credits for heat island effect as well as aesthetics and to reduce the buildings heat gain. E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Green Roof Design Existing Conditions Storm Water Management Views from Future Parking Garage Highly Insulated Extensive System Reduce Heat Island Effect Long Life Span Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Cool Roof Reduce Heat Island Effect Highly Insulated Long Life Span Easy Installation S t a t e U n i v e r s i t y Metal Roof Dramatic Façade Summer Shading Highly Insulated Locally Available Long Life Span E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Proposal Green Roof Design Existing Conditions Critique & Proposal Design Critique Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Green Roof Hidden Behind Building Thermal Benefits of Green Roof Lost S t a t e U n i v e r s i t y Relocate Green Roof to Sloped Roof: Various Green Roof Systems Rendering Geisinger Gray’s Woods Medical Office Building Building Section Thermal Heat Gain Calculations E r i c a L . C r a i g Proposed Green Roof C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Proposed Green Roof Rendering Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Lightweight Extensive System Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Proposed Green Roof Xero Flor Green Roof System Drought Resistant & Low Profile Plants Textile Carrier Design Pre-Vegetate Mat Design Low Maintenance S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Xero Flor Green Roof System Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Proposed Green Roof Green Roof Design American Hydrotech Green Roof System Existing Conditions Critique & Proposal Architectural Impacts Lightweight and Low Profile Extensive System Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Low Maintenance Gardnet Soil Stabilization Plants Include Sedum, Herbs, & Grasses S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview American Hydrotech Green Roof System Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Thermal Resistance Green Roof Design R-Value of Varying Roofing Systems Existing Conditions Critique & Proposal Architectural Impacts Portion of Cooling Load on Equipment Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Roof Area Only : 5015 SF R-Value Difference from Current Design Design Temperature Change : 20° F U n i v e r s i t y Xero Flor Roof Hydrotech Roof 23.48 -1.65 23.34 -1.51 Heat Flow Rate Calculations Heat Flow Rate = S t a t e Metal Roof Current Design 21.83 E r i c a L . C r a i g Area of Roof x Design Temperature Change R-value of Roof System C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Thermal Resistance Cooling Load on Equipment Mechanical Impacts Higher R-Value = Reduced Heat Gain Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Green Roof Systems Provide About a 7% Heat Gain Reduction S t a t e U n i v e r s i t y Btu/Year Difference from Current Design E r i c a L . C r a i g Metal Roof Current Design 543,191,351 Xero Flor Roof Hydrotech Roof 505,019,898 38,171,454 508,049,152 35,142,200 C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Solar Radiation Green Roof Design Interior Heat Gain Absorptivity of Roof Materials Existing Conditions Critique & Proposal Architectural Impacts 5 Mechanical Impacts Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Interior Heat Gain from Solar Roof Radiation 40 N Lat. - July 21st 4 Metal Roof Green Roof Btu/hr-ft2 3 2 1 0 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Cooling Load for Typical Sunny Day Existing Conditions Critique & Proposal Architectural Impacts 16000 P e n n s y l v a n i a Cooling Load from Heat Gain = 14000 Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e Solar and Interior Heat Gain Cooling Load for a Typical Day 40 N Lat. - Suspended Ceilings Mechanical Impacts Solar Radiation Area of Roof x Cooling Load Temperature Difference (CLTD) R-value of Roof System 12000 Btu/hr 10000 Cooling Load on Equipment 8000 6000 4000 Metal Roof 2000 Green Roof 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time S t a t e U n i v e r s i t y Metal Roof Green Roof E r i c a L . C r a i g Total Btu/Day 177,250 142,000 # of Sunny Days Per Year 215 215 C o n s t r u c t i o n Total Btu/Year 38,108,750 30,530,000 M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Thermal Resistance Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Btu/Year Cost Analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Metal Roof Current Design 581,300,101 Xero Flor Roof Hydrotech Roof 535,549,898 538,579,152 Thermal Resistance and Solar Radiation Total Cooling Load on Equipment Solar Radiation Metal Roof Green Roof S t a t e Total Btu/Day 177,250 142,000 U n i v e r s i t y # of Sunny Days Per Year Total Btu/Year 215 38,108,750 215 30,530,000 Btu/Year Difference from Current Design E r i c a L . C r a i g Metal Roof Current Design 581,300,101 Xero Flor Roof Hydrotech Roof 535,549,898 45,750,204 538,579,152 42,720,950 C o n s t r u c t i o n M a n a g e m e n t Erica L. Craig G e i s i n g Construction Management Ambulatory December 18th, 2007 Final Proposal Dr. Riley Introduction Project Overview er Gray’s Woods C a r e CGeisinger a m pGray’s u sWoods P Ambulatory h a s eCareI Campus Phase I Current Roofing Systems Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Green Roof - Boiler Room + Plants for Green Roof Cool Roof - Flat Main Roof Metal System Initial Building Costs Includes Standard Components Cost analysis Other Components Added for Green Roof Systems Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Patton Township, Centre County, PA Includes Labor and Installation Costs S t a t e U n i v e r s i t y Cool Roof - Boiler Room Cool Roof - Flat Main Roof Green Roof - Sloped + Shipping Costs + Roofing Membrane & Insulation + Tacking and Accessories + Irrigation E r i c a L . C r a i g 5105 SF Cost 25 $/SF 5 $/SF 10 $/SF 16 $/SF PRICE Total 82,250 16,450 242,000 81,680 $422,380 Relocation of Green Roof - Hydrotech Relocation of Green Roof - XeroFlor Amount 3290 SF 24200 SF 5105 SF 5105 SF 5105 SF 5105 SF Amount 3290 SF 3290 SF 24200 SF Cost 10 $/SF 10 $/SF 13 $/SF 0.25 $/SF 8 $/SF 2 $/SF Total 32,900 242,000 66,365 1,500 40,840 10,210 2,500 PRICE $396,315 Cool Roof - Boiler Room Cool Roof - Flat Main Roof Green Roof - Sloped + Irrigation + Plants for Green Roof C o n s t r u c t i o n Amount 3290 SF 24200 SF 5105 SF Cost 10 $/SF 10 $/SF 32 $/SF Total 32,900 242,000 163,360 2,500 $/SF 25,525 PRICE $466,285 5105 SF 5 M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Erica L. Craig Construction Management December 18th, 2007 Final Proposal Dr. Riley Introduction Project Overview Current Roofing Systems Green Roof - Boiler Room + Plants for Green Roof Cool Roof - Flat Main Roof Metal System Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cool Roof - Boiler Room Cool Roof - Flat Main Roof Green Roof - Sloped + Shipping Costs + Roofing Membrane & Insulation + Tacking and Accessories + Irrigation Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Amount 3290 SF 3290 SF 24200 SF 5105 SF 25 5 10 16 Cost $/SF $/SF $/SF $/SF PRICE Amount 3290 SF 24200 SF 5105 SF 5105 SF 5105 SF 5105 SF Cost 10 $/SF 10 $/SF 13 $/SF 0.25 $/SF 8 $/SF 2 $/SF PRICE Initial Building Costs Total 82,250 16,450 242,000 81,680 $422,380 Relocation of Green Roof - XeroFlor Cost analysis Geisinger Gray’s Woods Ambulatory Care Campus Phase I Patton Township, Centre County, PA Total 32,900 242,000 66,365 1,500 40,840 10,210 2,500 $396,315 Current Roofing System $422,400 Initial Cost Difference S t a t e Amount 3290 SF 24200 SF 5105 SF 10 10 32 5105 SF 5 U n i v e r s i t y Cost $/SF $/SF $/SF $/SF PRICE Total 32,900 242,000 163,360 2,500 25,525 $466,285 Relocation with Hydrotech $466,300 $43,900 Ye a r l y O p e r a t i n g C o s t s Relocation of Green Roof - Hydrotech Cool Roof - Boiler Room Cool Roof - Flat Main Roof Green Roof - Sloped + Irrigation + Plants for Green Roof Relocation with Xero Flor $396,300 -$26,100 Yearly Operating Costs Difference E r i c a L . C r a i g Current Roofing System $15,680.00 Relocation with Xero Flor $14,530 -$1,150 C o n s t r u c t i o n Relocation with Hydrotech $14,480 -$1,200 M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Aesthetics Play a Huge Part in Decision Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Green Roofs Reduce Heat-Gain but Research Not Inclusive Initial Cost Savings of Xero Flor Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Current Roofing System $422,400 Initial Cost Difference Yearly Operating Costs Difference Relocation with Xero Flor $396,300 -$26,100 Relocation with Hydrotech $466,300 $43,900 Relocation with Xero Flor $14,530 -$1,150 Relocation with Hydrotech $14,480 -$1,200 Current Roofing System $15,680.00 Ye a r l y U t i l i t y S a v i n g s o f E i t h e r G r e e n R o o f G r e e n R o o f Tr a i n i n g T i m e v s . M e t a l R o o f Installation Time Structural Implications S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation T h e P e n n s y l v a n i a Existing Conditions Premium Cost of Lightweight Concrete Lightweight Concrete on Composite Metal Decking Proposal (26) 30’ x 30’ bays Current System Lightweight Concrete on Composite Metal Decking Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks Design Critique Normal Weight Concrete on Composite Metal Decking Normal Weight Concrete on Form Decking and Joists S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation LW to NW Concrete Normal Weight Concrete on Composite Metal Decking Composite to Form Decking Normal Weight Concrete on Form Decking and Joists (26) 30’ x 30’ bays (26) 30’ x 30’ bays Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Cost Difference $347,942 $382,481 $34,538 $331,339 -$16,604 N W a n d F o r m D e c k O N LY for Typical Bays Negligible Schedule Changes for Structural System Floor Sub System Structural Impact System 2"Decking with LW Concrete - Current Design 2" Decking with NW Concrete 9/16" Form Decking with NW Concrete Overhead MEP Installation and Coordination S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Geisinger Gray ’s Woods Conditions Delayed the Start of Construction Project Involved with About Six Agencies Entire Process Took Over a Year – 13 Months Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Schedule to Start December ‘06 Actual Start April ‘07 S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e Critique Proposal Time Delays Continuing Education for Codes Owner Occupancy and Revenue Delayed Increase Number of Code Review Officials Causes Frustration and Aggravation for All Research of Other Permitting Processes U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact International Code Council Services of ICC Founded in 1994 Approvals & Permitting Project Conditions Critique Permitting History Develops Codes for Commercial and Residential Buildings • Education and Certification Programs • Plan Reviews • Magazines and Newsletters • Tra i n i n g a n d I n f o r m a t i o n a l Videos • Code Change Publications Combitnation of BOCA, ICBO, and SBCCI Non-Profit Organization Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Permitting in Central Pennsylvania Name Position Municipality, Company Michael Rupert Senior Building Inspector Centre Region Code Administration Donald Fure Code Enforcement Officer Swatara Township Ned Liggett Commercial Plan Examiner Centre Region Code Administration Rod Smay Manager Bureau Veritas Albert Wrightstone Building Inspector Susquehanna Township Dan Slatt Building Inspector Lower Paxton Township Handled by the Municipality in which the Project is Located Two Approaches: In Office Reviews Project Conditions Critique Permitting History Third Party Reviews Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact In-Office Reviews Third Party Reviews Used by Regions: 1 Plan Reviewer/554 SM Used by Small Municipalities: 1 Plan Reviewer /9 SM On All Projects: Of Any Size On Large Projects: (> 5,500 SF) Used in Rural Areas Smaller Projects Reviewed In-Office 30 Day Time Limit for Approvals Approvals & Permitting 30 Day Time Limit for Approvals Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e Easily Navigated Website with Documentation Basic Website Design with Limited Information On-Site Meetings and Inspections On-Site Meetings and Inspections U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Approvals & Permitting Green Roof Design Aesthetics Play a Huge Part in Decision Initial Cost Savings of Xero Flor of $26,000 Yearly Utility Savings of Either Green Roof of $1,000 Floor Sub System NW and Form Deck ONLY for Typical Bays to Save $16,000 Overhead MEP Installation and Coordination Preliminary Meeting Scheduled Early in Design Phase Communication Key Between All Parties Involved Prepare Complete Permitting Packages Continuing Education on Codes Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation S p e c i a l T h a n k Yo u To : Alexander Building Construction, LLC EwingCole Geisinger Health System PSU AE Facutly Family and Friends Industry Members Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t G e i s i n ge r G ray ’s Wo o d s Ambulatory Care Campus Phase I T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Solar Radiation Solar Heat Gain Factors for a Roof 40°N Lat. - July 21st 350 300 Btu/hr-ft2 250 200 150 100 50 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Approvals & Permitting Project Conditions Critique Permitting History Industry Survey Conclusion & Recommendation Structural Impacts CURRENT CURRENT DESIGN SizeDESIGN LW Concrete LW Concrete 3.5" Concrete PlacingConcrete<Placing 6" thick Steel Decking Steel Decking 2" LOK Steel Beams Steel Beams W 16x26 Steel Girders Steel Girders W24x55 Steel Columns Steel Columns W10x68 Fireproofing Fireproofing Size 3.5" < 6" thick 2" LOK 3W 16x26 1W24x55 2W10x68 3 1 2 NW CONCRETE NW CONCRETE Size CURRENT DESIGN Size Size FORMDECK NW Concrete NW Concrete 4.5" LW Concrete 3.5" 4.5" < 6" thick Concrete Concrete PlacingConcrete <Placing 6" thick < 6" thick Placing Steel Decking 2" LOK Steel Decking 2" LOK 2" LOK Steel Decking Steel Beams Steel Beams W14x22 W 16x26 4W14x22 3 Steel Beams Steel Girders Steel Girders W24x68 W24x55 1W24x68 1 Steel Girders Steel Columns Steel Columns W10x88 W10x68 2W10x88 2 Steel Columns Fireproofing Fireproofing Fireproofing NW Concrete Concrete Placing Steel Decking Steel Joists Steel Girders Steel Columns Steel Dunnage Fireproofing 4 1 2 Size 3" < 6" thick 9/6" FD 18K9 W24x76 W10x88 10 1 2 Final Remarks T h e P e n n s y l v a n i a S t a t e U n i v e r s i t y E r i c a L . C r a i g C o n s t r u c t i o n M a n a g e m e n t Geisinger Gray’s Woods Ambulatory Care Campus Phase I Introduction Project Overview Green Roof Design Existing Conditions Critique & Proposal Architectural Impacts Mechanical Impacts Cost analysis Conclusion & Recommendation Floor Sub System Structural Impact Case Study: Department of Planning and Development (DPD) Design Review Program Located in Seattle, Washington 35 Members, 5 for each of the Seven Districts Approvals & Permitting Perform On-Site Inspections and Approves Land and Construction Related Permits Permitting History Industry Survey Conclusion & Recommendation Final Remarks T h e P e n n s y l v a n i a Easy to Navigate Website with Documentation Available Meet Two Times a Month Project Conditions Critique No Financial Compensation for Members S t a t e U n i v e r s i t y E r i c a L . C r a i g Design Review Process Designed to Open Lines of Communication, be Flexible, and Encourage Great Design C o n s t r u c t i o n M a n a g e m e n t