VCU Project Change Request Form PROJECT NAME PROJECT MANAGER PCR ID Priority 004 Low Increase Bandwidth to University Buildings (G2B) William M. Jones Change Request Identification Short description Remove Temple Room 3303 from scope Date raised 1/17/13 Status Approved for Implementation Raised by Tom Compton Change Request Assessment Detailed description Room 3303 in the Temple Building serves two computer labs. Switches are housed in a floor mounted box in the front of the room. Several faculty members have requested the box be moved as it impacts the use of the white board; Network Services also desires to move the switches to improve accessibility to the switches and better comply with physical security standards. A separate infrastructure project has been approved (HD540070) to re-cable both labs back to a network closet. However, that work may not be completed by the end of the G2B project. Fiber cable to room 3303 is inadequate to allow the current location to come into compliance with G2B standards. This change request is to remove Temple Room 3303 from the scope of the G2B project to avoid unnecessary expenses to improve fiber to a location that will soon be abandoned. When the recabling project is complete this summer, the building will meet all G2B standards. Timescale for analysis Small change January 2013 Yes Assigned to Assigned date Bill Jones 1/17/13 Change Request Analysis Scope Impact Description Removes one fiber run that would have supported 72 workstation ports. Schedule Impact Description No impact to overall schedule. Note that leaving this room in scope will likely result in extending the end date of the project. Cost Impact Description -$10,000. Completion Criteria for Change Request Approval to remove from scope. Estimated effort 1 hours Estimated cost -$10,000 Estimated start date 1/18/13 Estimated end date 1/18/13 Impact level Low Resources 1 Implementation decision Approved by: Bill Jones Change Request Approval Approved Approved on: 1/18/13 Change Request Implementation Date completed Date closed Comments 1/18/13 1/18/13 Closed by Bill Jones Priority: Critical/High/Medium/Low Status: Open / Approved for Analysis / Approved for implementation/ Rejected / Deferred/ Closed Project Change Request 612931151 Page 1 of 1