Change 4

advertisement
VCU Project Change Request Form
PROJECT NAME
PROJECT MANAGER
PCR ID
Priority
004
Low
Increase Bandwidth to University Buildings (G2B)
William M. Jones
Change Request Identification
Short description Remove Temple Room 3303 from scope
Date raised
1/17/13 Status
Approved for
Implementation
Raised by
Tom Compton
Change Request Assessment
Detailed description
Room 3303 in the Temple Building serves two computer labs. Switches are housed in a floor mounted
box in the front of the room. Several faculty members have requested the box be moved as it impacts
the use of the white board; Network Services also desires to move the switches to improve
accessibility to the switches and better comply with physical security standards. A separate
infrastructure project has been approved (HD540070) to re-cable both labs back to a network closet.
However, that work may not be completed by the end of the G2B project. Fiber cable to room 3303 is
inadequate to allow the current location to come into compliance with G2B standards.
This change request is to remove Temple Room 3303 from the scope of the G2B project to avoid
unnecessary expenses to improve fiber to a location that will soon be abandoned. When the recabling project is complete this summer, the building will meet all G2B standards.
Timescale for analysis
Small change
January 2013
Yes
Assigned to
Assigned date
Bill Jones
1/17/13
Change Request Analysis
Scope Impact Description
Removes one fiber run that would have supported 72 workstation ports.
Schedule Impact Description
No impact to overall schedule. Note that leaving this room in scope will likely result in extending the
end date of the project.
Cost Impact Description
-$10,000.
Completion Criteria for Change Request
Approval to remove from scope.
Estimated effort
1 hours
Estimated cost
-$10,000
Estimated start date
1/18/13
Estimated end date
1/18/13
Impact level
Low
Resources
1
Implementation decision
Approved by:
Bill Jones
Change Request Approval
Approved
Approved on:
1/18/13
Change Request Implementation
Date completed
Date closed
Comments
1/18/13
1/18/13
Closed by
Bill Jones
Priority: Critical/High/Medium/Low
Status: Open / Approved for Analysis / Approved for implementation/ Rejected / Deferred/ Closed
Project Change Request
612931151
Page 1 of 1