VCU Project Change Request Form PROJECT NAME PROJECT MANAGER PCR ID Priority 001 Low Increase Bandwidth to University Buildings (G2B) William M. Jones Change Request Identification Short description Remove Education Annex and VISSTA Buildings Date raised 5/31/11 Status Approved for Implementation Raised by Bill Jones Change Request Assessment Detailed description Remove Education Annex and 102, 104, and 106 North Linden (VISSTA) from scope as they will be demolished to make way for the new academic classroom building. Timescale for analysis Small change June 2011 Yes Assigned to Assigned date Bill Jones 5/31/11 Change Request Analysis Impact analysis Scope Impact Description Removes 4 small buildings from scope. Schedule Impact Description Changes end date from 8/20/2013 to 4/23/2013: - 17 weeks Cost Impact Description - $24,440 Recommend moving to contingency budget. Completion Criteria for Change Request Project documents updated and team notified. Estimated effort Estimated start date Impact level 1 hour 6/1/11 Low Estimated cost Estimated end date Resources Implementation decision Approved by: Bill Jones Change Request Approval Approved Approved on: 0 6/2/11 1 Date 6/1/11 Change Request Implementation Date completed Date closed Comments 6/2/11 6/2/11 Closed by Bill Jones Priority: Critical/High/Medium/Low Status: Open / Approved for Analysis / Approved for implementation/ Rejected / Deferred/ Closed Project Change Request 401280755 Page 1 of 1