Construction continues for Charlotte-Mecklenburg Storm Water Services’
Westridge/Allenbrook Storm Drainage Improvement Project. The pipe work
on Westcliff Drive, Westridge Drive, Lanewood Place, Allenbrook Drive and
Willard Street is complete. The channel stabilization is complete on Westridge
Drive, Lanewood Place, Ranch Road and Willard Street.
In the next few months, the contractor will perform some channel
stabilization work between Marble Street and Interurban Avenue. Once
complete, crews should start clearing the channel and doing some channel
stabilization work downstream of Allenbrook.
As stream channel work progresses, we will be putting up yard fence and
restoring the yards along the channel as it is being built.
For more information about this project, please visit our website to view
project updates and exhibits at: http://stormwater.charmeck.org. Click on
Storm Water Projects drop down menu in the green bar, then Active Projects
and Westridge/Allenbrook.
Please know the Westridge/Allenbrook project is working in conjunction
with the Thomasboro-Hoskins Phase IV neighborhood project. For questions
related to Thomasboro-Hoskins Phase IV, please call Kristie Kennedy at
704-336-6194.
Channel stabilization work is complete
downstream of Westridge Crossing.
If you have any questions, please contact one of the following members:
On-site Construction Inspector:
Project Manager:
Scott Ackerman: 980-721-3653
Jackie Bray: 704-336-6770
Email: sackerman@charlottenc.gov
Email: jbray@charlottenc.gov
Construction Supervisor:
Frank Cantrell: 704-336-7034
E-mail: flcantrell@charlottenc.gov
A construction inspector will be on site daily to address any questions or concerns.
Please note efforts are taken to minimize disruption to nearby properties.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Westridge/Allenbrook Project Update
HIGHLIGHTS
Download