UNDER CONSTRUCTION
Westridge/Allenbrook
STORM DRAINAGE IMPROVEMENT PROJECT
Dear Resident:
January 2014
Construction continues for Charlotte-Mecklenburg Storm Water Services’
Westridge/Allenbrook Storm Drainage Improvement Project. The pipe work
on Westcliff Drive, Westridge Drive, Lanewood Place, Allenbrook Drive and
Willard Street is complete. The channel stabilization is complete on Westridge
Drive, Lanewood Place, Ranch Road, Willard Street, Interurban and Marble St.
In the next few months, the contractor will perform some channel
stabilization repair work between Marble Street and Interurban Avenue.
Crews will begin channel stabilization work downstream of Allenbrook Drive,
this is the last phase of the project.
We are in planting season, so plantings are being installed along streams on
Westridge Drive, Lanewood Place, Ranch Road, Willard Street, Interurban
Avenue, Marble Street and Allenbrook Drive.
For more information about this project, please visit our website to view
project updates and exhibits at: http://stormwater.charmeck.org. Click on
Storm Water Projects drop down menu in the green bar, then Active Projects
and Westridge/Allenbrook.
Please know the Westridge/Allenbrook project is working in conjunction
with the Thomasboro-Hoskins Phase IV neighborhood project. For questions
related to Thomasboro-Hoskins Phase IV, please call Kristie Kennedy at
704-336-6194.
Looking downstream from Lanewood Place
headwall during 100 year storm event.
If you have any questions, please contact one of the following members:
On-site Construction Inspector:
Project Manager:
Scott Ackerman: 980-721-3653
Jackie Bray: 704-336-6770
Email: sackerman@charlottenc.gov
Email: jbray@charlottenc.gov
Construction Supervisor:
Frank Cantrell: 704-336-7034
E-mail: flcantrell@charlottenc.gov
A construction inspector will be on site daily to address any questions or concerns.
Please note efforts are taken to minimize disruption to nearby properties.