ADDENDUM No. 1 FROM: James Schumacher, CMR Facilitator DATE: November 30, 2015 PROJECT: CONSTRUCTION MANAGER AT RISK SERVICES (CMR) FOR CONCOURSE A NORTH TERMINAL EXPANSION PHASE I Project # TM15-019 The following items are being issued herein for clarification, addition and/or deletion and are incorporated into the Request for Qualifications issued November 6, 2015. Questions & Answers: 1. Question: Can you please share available information on the schedule for preconstruction and construction services? What is the target for terminal activation? Answer: Preconstruction services are expected to begin in February 2016, construction of early packages for utilities and foundations in summer 2016, and occupancy in early 2018. 2. Question: Has a design team been selected, can you tell us who? Answer: The design team is a joint venture of Perkins & Will/C Design 3. Question: What is the current status of design? Answer: Schematics 4. Question: Is a written reference required for each project in criteria #1 and #2? Some owners have a blanket policy of not providing written references. Answer: In the absence of a written reference, the contact name, phone number and email can be provided. 5. Question: Will a SBE Certification issued by the North Carolina Department of Transportation be accepted towards the goal for this project by the City of Charlotte? Answer: No. See Section 5 of the RFQ. 6. Question: Will second tier MWBE/SBE participation count towards the goal? Answer: Second tier MBE and SBE will count towards the goal. End of ADDENDEM No. 1