INTEROFFICE MEMORANDUM To: Lina Swan, Director of Fiscal Operations From: Stephen H. Clark, Administrative Law Judge Date: September 29, 2005 Re: Demand For Direct Payment ----------------------------------------------------------Claimant: Aggregate Industries (Aggregate) Contractor: Roads Corporation (Roads) Contract: MHD #32082 City/Town: Interstate 495 Amount: $804,63.99 1. Aggregate filed this direct payment demand (Demand) on September 7, 2005 through a letter dated September 6, 2005 pursuant to G.L.c.30, s.39F (Section 39F). The Demand is properly sworn under pains and penalties of perjury and was sent to the Department by certified mail with a copy to Roads, also by certified mail. 2. Aggregate’s Demand states that it is “a materialman entitled the protection [sic] of M.G.L. Ch. 30, s.39F.” “Subcontractor” is defined for purposes of Section 39F with respect to general contracts with the commonwealth not awarded under G.L. c. 149, s.44A to 44H as a “person contracting with the general contractor to supply materials used or employed in a public works project for a price in excess of five thousand dollars.” Section 39F(3)(iii). 3. Section 30F(1)(d) requires that a subcontractor’s demand contain “a statement of the status of completion of the subcontract work.” The Demand states that Aggregate’s “portion of the project is complete” but does not expressly state a date of substantial completion. The date of completion is material since Section 39F(1)(d) provides in substance that the right to make a direct payment demand does not accrue until 70 days after the subcontractor has “substantially completed the subcontract work.” Here, the date of the last invoice is August 26, 2005. See invoice #4529316. Based on a “substantial completion” date of August 26, 2005, it is plain that Aggregate’s September 9, 2005 Demand was filed before 70 days had elapsed since substantial completion. 4. Section 39F(1)(d) requires that a subcontractor’s “demand shall contain a detailed breakdown of the balance due under the subcontract.” The Demand here states “Asphalt and stone provided on a unit cost basis and a liquid asphalt escalation charge.” The Demand further states: “The nature of the materials provided by Aggregate Industries to Roads Corporation for the project located at I-495, Mansfield to Franklin, is detailed on the attached schedule.” (Emphasis supplied.) The attached schedule, which is not sworn and which is not expressly incorporated by reference into the sworn Demand, consists of a list of 67 numbered invoices, for example MATERIAL INVOICE # ORIG. DATE OPEN AMOUNT MATERIAL 4514448 4514449 07/25/05 07/25/05 $29,287.79 $ 2,339.96 ASPHALT STONE 5. The schedule of 67 invoices is offered in the Demand to show the “nature” of the materials provided. Neither the schedule nor anything else in the Demand states the terms of the subcontract, the payment item(s) in Roads’s general contract to which the Demand refers, the unit prices bid in the general contract, the quantities of material supplied by the subcontractor or the amount (or calculation) of the “liquid asphalt escalation charge,” if any. 6. The schedule in the Demand also includes category titled “ESCALATION” under which one invoice (#273355) is listed as an “open amount” of $30,548.94. There is no reference to a payment item in the general contract (or any unit price therein) for “escalation.” There is no written statement in the Demand that explains the $30,548.94 demanded or the basis on which the Department may pay that sum to Aggregate. 7. The Demand does not contain a balance due under the subcontract that is derived from the financial data of the general contract or subcontract. The Demand is a list of 67 “open invoices” totaling $804,634.99. 8. Roads filed a sworn reply to the Demand (Reply) on September 20, 2005. See Section 39F(1)(d). The Reply states that Roads has paid Aggregate for 168,505.22 megagrams of bituminous concrete but the Reply does not specify the sums paid Aggregate nor which of Aggregate’s invoices it paid. The Reply also states Aggregate is requesting payment for which materials Roads itself has yet to be “reimbursed” by the Department. Roads’s Reply agrees that the paving work “has been substantially completed” but like Aggregate does not specify a date. The Reply states that “Roads accounting with Aggregate Industries will be fully reconciled upon payment to Roads by MassHighway for the remaining bituminous concrete products delivered to the project.” 9. The Demand fails to meet the requirements of Section 39F. It failed to provide a detailed statement of the balance due under the subcontract. The Demand was filed prematurely. 10. Kindly take no further action on this Demand. cc: Aggregate Industries Northeast Region, Inc. 1715 Broadway Saugus, MA 01906 The Roads Corporation 241 Treble Cove Road North Billerica, MA 01852 District Highway Director, District 5 Chief Engineer Commissioner