TO: FROM: DATE: RE: Lina Swan, Director of Fiscal Operations Stephen H. Clark, Administrative Law Judge September 23, 2005 Request for Direct Payment Under G.L. c.30, S.39F Claimant: Contractor: Contract # City/Town: Amount: PT Corporation (PT) Modern Continental Construction Co. Inc. (MCC) Contract #32153 [CO9C2] Boston (CA/T) $103,826.34 1. PT re-filed this direct payment demand (Demand) on September 1, 2005 following the rejection of its earlier demand on August 17, 2005. As with the previous demand PT appears to have met the formal requirements of G.L. c. 30, s.39F (Section 39F). MCC failed to file a sworn reply within ten days. See Section 39F(1)(d). 2. Section 39F requires that a demand include “a statement of the status of completion of the subcontract work.” See Section 39F(1)(d). Subcontractors may only make demands for direct payment with respect to general contracts awarded pursuant to G.L. c.30 upon “substantial completion” of the subcontract. 1 Here, the Demand states “PT … has substantially completed It’s [sic] work on or about June 15, 2005 referenced [sic] project _ [sic] for work completed through June 15, 2005.” I do not understand this sentence to mean that PT swears under oath that all its subcontract work has been completed. Paragraph 6 of the Demand states “The work on this section of the contract has been substantially completed as of June 15, 2005.” I do not construe that sentence to mean that PT has sworn under oath that it has substantially completed all its subcontract work. There is no showing that the subcontract work has been substantially completed. 3. Section 39F requires that a demand “contain a detailed breakdown of the balance due under the subcontract.” See Section 39F(1)(d). PT purports to meet this requirement in paragraph 5 of its Demand, which states 1 Section 39F distinguishes between subcontractor demands made with respect to general contracts awarded under G.L. c. 30 and those awarded under G.L. c. 149. With respect to a general contract awarded under G. L. c. 149, a subcontractor is authorized to make a direct payment demand after substantial completion of subcontract work and after a general contractor receives a periodic payment from the awarding authority with respect to subcontract work in progress, where the general contractor has failed to pass through payment for the account of the subcontractor. See Section 39F(1)(1st para) in combination with Section 39F(1)(i) and Section 39F(1)(a). By contrast, with respect to a general contract awarded under G.L. c.30, a subcontractor is only authorized to make a direct payment demand upon “substantial completion of the subcontract work.” See Section 39F(1)(1st para) in combination with Section 39F(1)(i) and Section 39F(1)(d). The original subcontract value was $5,198,875.00. The total subcontract value is $5,317,874.95[.] Total due to PT for the above mentioned work at this time is $103,826.95 for partially paid item #722.876. (Emphasis supplied.) 4. The Demand does not provide any further “detailed breakdown” in its sworn statement.2 Instead, it attaches voluminous documents to its Demand, perhaps with the expectation that the Department itself will ferret out the precise data from which a proper “detailed breakdown” could be pieced together. Section 39F places upon the subcontractor the burden to present a coherent breakdown; it is PT not the awarding authority that must discharge this task. I find that PT has not provided a sufficient “detailed breakdown of the balance due here. 5. PT Demand is rejected. Take no further action on this Demand. cc: PT Corporation 480 Broadway Lynnfield, MA 01940 Modern Continental Construction Company, Inc. 600 Memorial Drive Cambridge, MA 02139 District Highway Director, District 4 Deputy Chief Engineer, Construction Marie T. Breen, Esq. Commissioner 2 I note that $5,317,874.95 minus $5,198,875.00 = $118,999.95. Nothing in the detailed statement shows how the amount demanded--$103,826.34—was derived. 2