115 AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE August 6, 2012 FROM: PRESIDENT SUBJECT: Facilities Master Plan Project Status REASON FOR BOARD CONSIDERATION ENCLOSURE(S) ITEM NUMBER INFORMATION Page 1 of 6 D.3 BACKGROUND: Major Projects under Construction (see next page) Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition 116 Facilities Master Plan Major Projects for the period ending June 30, 2012 Projects In Process Health and Wellness Center and Sitework Planned Substantial Completion Date Spring 2011 Building 800 Renovation 1,049,000 12,174 1,506,713 100.0% 100.0% 99.5% 32,072 46,399 2,567,888 848,804 88,295 247,901 118,500 71.6% Spring Measure D 1,105,493 1,105,493 1,039,908 3,652 61,933 110,549 94.1% 2011 Project Sub-total Total Project 2,290,493 2,290,493 1,888,712 91,947 309,834 229,049 27,969,368 27,969,368 27,489,116 124,019 356,233 2,796,937 82.5% 98.3% 100.0% 100.0% 96.7% 98.3% 81.5% 82.6% 82.0% 90.9% 100.0% 100.0% 92.7% 95.0% State Capital Outlay Funds Measure C Measure D Fall 2010 99% Fall 2013 VAPA Remediation Summer 2012 1,051,000 33 1,166,000 2,217,033 931,000 931,000 1,862,000 1,051,000 33 1,166,000 2,217,033 931,000 931,000 1,862,000 1,051,000 33 1,127,403 2,178,436 758,913 768,620 1,527,533 0 0 162 162 0 0 0 0 0 38,435 38,435 172,087 162,380 334,467 105,100 3 116,600 221,703 93,100 93,100 186,200 Project Sub-total Total Project 4,079,033 4,079,033 3,705,969 3,365,000 100,000 6,951,592 162 0 0 50,406 372,902 407,903 Total Project 10,965,000 10,965,000 10,416,592 50,406 498,002 1,096,500 EDA Funds Foundation Measure D Fall 2011 Fall 2012 Project Sub-total State Capital Outlay Funds Measure D Fall 2010 2012 Fall 2013 7/24/2012 0 0 46,399 25,600,404 Summer Total Projects in Process 0 0 32,072 1,185,000 Building 800 Moves South Perimeter Road 10,490,000 121,741 14,988,663 25,678,875 95% Watsonville GTC Equipment Paid to Date Total Project % Change Orders of Budget Paid Contingency to date to date 1,185,000 90% Watsonville Green Technology Center 10,490,000 121,741 15,067,134 Available Balance 25,678,875 Pending DSA approval Building 300 Renovation Equipment 10,490,000 121,741 15,067,134 Encumbered to Date Project Sub-total 98% Building 300 Renovation Funding Source State Capital Outlay Funds Measure C Measure D Original Project Adjusted Budget Project Budget State Capital Outlay Funds 99% Pending DSA approval Health and Wellness Equipment Estimated % Completion 3,365,000 100,000 7,500,000 0 0 498,002 131,186 336,500 10,000 750,000 -152,600 99.7% 400,000 400,000 3,000 27,000 370,000 40,000 0.8% STEM Grant Funds Measure D 1,952,530 1,500,000 1,952,530 2,250,000 143,857 24,792 121,947 136,783 1,686,726 2,088,425 195,253 225,000 3,452,530 4,202,530 168,649 258,730 3,775,151 420,253 248,283 313,283 202,179 47,383 63,721 31,328 248,283 1,915,130 845,605 2,760,735 313,283 202,179 47,383 63,721 31,328 1,915,130 845,605 181,943 0 107,713 0 1,625,474 845,605 191,513 84,561 6% Total Project Measure D Total Project Measure C Measure D Total Project 7.4% 1.1% 4.0% 2,760,735 181,943 107,713 2,471,079 276,074 99% Total Project 140,000 140,000 101,227 7,828 30,945 14,000 8,413 72.3% 50,014,949 50,829,949 42,268,675 623,241 7,938,033 4,721,593 1,074,510 83.2% 1% 3% 98% Total Project 3,365,000 100,000 7,500,000 1,078,021 Total 1 of 2 9,490 64.5% 64.5% 9.5% 0.0% 6.6% 117 Facilities Master Plan Major Projects for the period ending June 30, 2012 Projects Completed VAPA Construction Completed Date Complete Funding Source 100% State Capital Outlay Funds Measure C Measure D Project Sub-total VAPA Equipment Complete 100% State Capital Outlay Funds Measure D Project Sub-total Total Project 7/24/2012 Original Project Budget 20,357,000 5,345,114 51,909,024 77,611,138 1,136,000 1,126,453 2,262,453 79,873,591 Adjusted Project Budget 20,357,000 5,345,114 51,909,024 Paid to Date 1,136,000 1,126,453 20,357,000 5,345,114 51,891,087 77,593,201 1,136,000 1,126,453 2,262,453 79,873,591 2,262,453 79,855,654 77,611,138 2 of 2 Balance 0 0 17,937 17,937 0 0 0 17,937 Total Change Orders 583,784 Total Project '% of Budget Paid to date 100.0% 118 Major Projects under Construction Health and Wellness Project This project is in the final closeout process with DSA. Current Status Update: This project is ready to be submitted to DSA for approval. Staff is waiting for DSA approval of all change orders in order to submit for final certification from DSA for the construction phase of the project. The majority of the equipment for the building has been purchased and installed. There are additional items to be purchased. Building 300 Renovation This project is in the final closeout process with DSA. Current Status Update: This project is ready to be submitted to DSA for approval. Staff is waiting for DSA approval of all change orders in order to submit for final certification from DSA for the construction phase of the project. A majority of the equipment has been purchased and installed, including furniture and classroom computers. Watsonville Green Technology Center The District and the City of Watsonville closed escrow on the purchase of the Watsonville Library on July 15, 2008. Since then, the college has demolished the building in order to construct a 14,000 square foot Community Education Center. The District received a grant for $2.5 million from Economic Development Agency for the project, and the grant was augmented by $865,000 to help fund an upgrade to a Platinum Level LEED certified “green” building. The Division of State Architect (DSA) approved the plans in June of 2010 and EDA approved the plans and specifications in July 2010. The project went to bid in August 2010. In October, the Board approved Dilbeck and Sons as well as an augmentation to the budget of $517,000. A deductive change order for the value engineering items discussed at the October Board meeting was approved at the November Board Meeting. The District has received a generous donation from the Ley Family of $100,000 for construction to add back some of the items that were placed on hold. Current Status Update: This project is substantially complete. Data wiring and data connections are complete, network equipment is in the process of being ordered which will connect these two new buildings to the existing campus network, as well as the acquisition of furniture and equipment. This project is ready to be submitted to DSA for approval. Staff is waiting for DSA approval of all change orders in order to submit for final certification from DSA for the construction phase of the project. Staff is also working with Economic Development Agency to receive the remaining grant funds and provide the necessary close out documentation for the project. 119 Building 800 STEM Remodel: Building 800 will be fully remodeled. There are two funding sources for this project. There is a Federal Grant (STEM Grant) from the Department of Education in the amount of $1,952,530 to fund design and partial construction. Fund 47 bond was slated to fund $1,500,000.00 for the balance of the construction pending the engineer’s estimate. Current Status Update: Due to the increase in square footage to the project, the Engineer’s estimate revealed that the District should plan for a total construction cost of $3,354,294. This will require an additional $750,000 contribution from Bond funds and will bring the estimated total project cost to $4,202,530. This will allow for an additional 11,860 S.F. of space to be renovated and complete all necessary modifications to the entire 20,892 S.F. of the 800 building. The project is in the Construction Documents phase and plans and specifications were presented to DSA in June. Demolition is currently scheduled for the Fall of 2012, construction Fall 2012 through summer 2013 with classes to begin in Fall 2013. 800 Bldg. Moves Phase I: Complete The 800 building moves were initiated in December and substantially complete in the beginning of February. This phase of the project required all administrative offices and categorical programs such as, Fast track to work, Student Job Placement, Puente and Cap to be relocated to SAC west and other programs and offices to be relocated. 800 Bldg. Moves Phase II: Additional programs were identified and will be relocated as part of the “800 Bldg. Moves Phase II” portion of the project. These programs include DSPS (Disabled Student Programs & Services), the Physics Department and remaining furniture purchases. The overall budget for this project is $313,283 Measure D funds. The original project was $248,283, but was increase $65,000 in June, 2012. Arts Education Classrooms Project This project is in the final closeout process with DSA. One change order remains to be approved by DSA. Staff will submit the complete closeout package to DSA for final certification upon receipt of final change order. Current Status Update: Received DSA Final CERTIFICATION - This Project is officially closed effective June 19, 2012. Awards of Informal Bids under the Uniform Construction Cost Accounting System (UCC): By adopting the Uniform Public Construction Cost Accounting System, the Board authorized the President or his/her designee to enter into agreements with low bidders using the informal bidding process with the provision that the successful awards would be presented to the Board as an information item. This system enables the District to 1) informally bid projects under $175,000 to prequalified contractors, 2) more efficiently and effectively manage small to medium sized projects, and 3) contract with local contractors who are deemed “qualified” bidders. 120 Awarded Bid: B12-09 South Perimeter Road Repair, Phase II (Informal Bid) There was one non-bond related bid to be awarded in June in the amount of $92,400 to Earthworks, Inc. South Perimeter Road Repair, Phase II Project will begin just past the entrance to the CEED parking lot around the bend and past parking Lot “M” exit. Four pre-qualified contractors attended the mandatory Job walk but only two contractors bid on the project as follows: Earthworks, Inc.; $92,400 and John F. Otto Inc., dba Otto Construction; 98,700. Request for Formal Bid No. B12-12: AEC VAPA Buildings 2000 & 3000 HVAC Acoustics Even though a large portion of this project is HVAC there is additional construction including but not limited to Structural Steel, Metal Stud Framing, Drywall, Painting, Plumbing, Fire Sprinklers, Electrical and Fire Alarm work that is needed; therefore, the Bidder must have a valid (A) or (B) Contractor License. Bid Due Date was Tuesday, July 10, 2012.