STUDENT DEVELOPMENT COMPLEX HVAC CONTROLS REPLACEMENT MAY 11, 2016

advertisement
ADDENDUM #1
PROJECT 24-16-04
STUDENT DEVELOPMENT COMPLEX
HVAC CONTROLS REPLACEMENT
MAY 11, 2016
Contractor shall list all addenda by number on the bid form to ensure conformity in the bid.
Drawings, Specifications and/or Proposals are herein amended, expanded and/or modified, as
hereinafter described, and become a part of the Contract Documents with the same force and effect as
if incorporated, herein, originally. Any contrary provisions contained, or referred to, in Drawings and/or
Specifications, shall remain applicable unless overridden by this Addendum. Revised or contrary
provisions herein shall not affect any other part of the Contract Documents and any deletions, additions,
substitutions and/or revisions mentioned, shall include all labor, materials, methods, modifications, etc.
required for complete performance of the work.
CONTRACT DOCUMENT MODIFICATIONS AND CLARIFICATIONS
1. Table of contents modified (there are no drawings for this project).
End of Addendum
MICHIGAN TECHNOLOGICAL UNIVERSITY
STUDENT DEVELOPMENT COMPLEX – HVAC CONTROLS REPLACEMENT
24-16-04
TABLE OF CONTENTS
Division 0 - Procurement
000101 Cover Page
000111 Table of Contents
001113 Invitation to Bid
004200 Bid Proposal Form
005200 Draft Contract
Division 1 – General Requirements
010000 General Conditions
010001 Supplementary General Conditions
010002 Payment Procedures
010003 AIA Document G702 Sample
010004 AIA Document G703 Sample
010008 Certificate of Substantial Completion
010010 Final Completion Checklist
010012 Guaranty
010014 Consent of Surety to Final Payment
010016 Sworn Statement
010018 Full Unconditional Waiver
010020 Certificate of Final Completion
010022 Change Order
011000 Summary of Work
013300 Submittals
Division 26 – Electrical
230923 Facilities Management & Control System
Attachment 1: Prevailing Wages for this Project.