SMOV Status & Planning Meeting Notes 7/28/09 - Summary: - Observatory Status WFC3 has completed 72% of the planned SMOV4 visits; the science results are mostly nominal or better. (UVIS dark current is worse than expected.) COS has detected two FUV problems and has proposed near-term workarounds, one of which requires an intercept load this week. STIS MAMA operations resume today. The NICMOS Cooling System (NCS) was successfully restarted this morning. A new ERO proposal has been generated to replace the target whose visits failed last week due to guidestar issues. o - All subsystems nominal SI Status o WFC3 Science (SDuestua) WFC3 has completed 72% of the planned SMOV4 visits o Science results are mostly nominal or better than expectations UVIS dark current is higher than expected o Engineering results are nominal except for a focus motion anomaly o Much analysis is ongoing o For details, see the attached WFC3_SMOV_Summary_28July09-1 Team has requested manual scheduling of bright earth crossings during 6 IR Dark exposures in 11447 o Two can be scheduled in SMS215 After overriding the links o Other visits may require proposal updates UV Contamination Check (11426) POSTARGs o POSTARGS are no longer needed once SIAF update is in place in the SMS215 o It was decided against removing the POSTARGs for the 215 occurrance of this monitor. For subsequent weeks, the POSTARGs will be removed from the proposal Cycle 17 Contam monitor picks up afterward o COS Science. TKeyes FUV External Wavecals (11487) o Experienced a local-rate-check (LRC) anomaly on Mon. morning Understood to be detection of the zeroth order on the detector To be mitigated by restricting usage of FP-POS = 4 Requires removal of FP-POS = 4 from 11487 o Also requires intercept load o New ERO has been proposed to replace failed visits of 11502. Proposal underwent PIT review yesterday. FGS/OTA Nominal The guide star acquisition failures (HSTARs 11948, 11950, and 11951) that occurred over the weekend were all due to the same dim star that caused the failure documented in HSTAR 11944. o ACS o - FUV Segment B Detector Features: the “Divots” o Possible mis-registration of charge for high-gain events; detailed analysis ongoing by IDT o Proposal to mitigate by reducing to ~ 150V Test in SMS215 with patchable constant update The revert back to normal voltage for subsequent visits in the week. Permanent change, if necessary, in SMS222. For details on the above and on upcoming COS activites, see the attached COS_SMOV_update_28July2009 o o - ERO Requires removal of FP-POS = 4 from later SMOV programs and from Cycle 17 STIS ACS SMOV is complete. Science. CProffitt Nothing new to report. MAMA observations resume this afternoon NICMOS/NCS Forward Plan NCS restart has occurred. o Successful compressor start at 209/13:24. o All initial telemetry indicated a nominal turn on o Cooling has begun P&S Status o Calendar/SMS builds SMS215 is built o Replans SMS208 intercept Being generated to address COS LRC anomaly, above Operations o FOT Nominal o PACOR Nominal o OPUS (TEllis) Nominal o Archive Nominal