SMOV Status & Planning Meeting Notes 8/28/09 - Summary - Some anomalous dark spots have been seen in WFC3 IR images. The cause is unknown and the investigation is ongoing. The COS team has determined the optimum FUV focus and has prepared the command arguments for uplink. NUV sensitivity, imaging performance, and NUV/FUV target acquisition analyses are ongoing. FGS2R Dark/Background analysis has completed; results are nominal and in family with other FGSs. STIS window glow continues to be monitored. The NICMOS Dewar temperature stability is being monitored while the tiger team discusses plans for set point and circulator speed adjustments. NICMOS SMOV likely to start in SMS257 (Sep. 14). - Observatory Status o - All subsystems are nominal SI Status o WFC3 Science (SDeustua) Some anomalous “blobs” have been seen in high-S/N IR images o Cause unknown May be particles on CSM o Investigation is ongoing For details, see the attached WFC3_SMOV_Science_21Aug.ppt o COS o Engineering COS single-sample lamp violation earlier this week is under investigation o Not considered serious Science (TKeyes) COS SMOV visits are 81 % complete COS FUV re-focus (11484) analysis is complete o New focus positions for G130M, G160M, G140L have been determined o Ops request to command the new positions has been prepared For uplink prior to start of next SMS Other Recent Results and Analyses o NUV Sensitivity Reference File Update Delivery plan for Sep. 14 (5 days after ERO press release) Need to coordinate with Archive for interim data products o NUV Imaging Performance Preliminary Analysis o Target Acquisition Parameter Updates For details, see the attached COS_SMOV_update_28August2009.ppt FGS/OTA (ABradley) Nominal o o ACS STIS FGS2R2 Dark/Background analysis has completed Results are nominal and in family with other FGSs For details, see the attached FGS 2 Dark & Background Determination 2009-2.doc ACS SMOV is complete. Science. (DLennon) NUV continues to be monitored o Window glow changing slowly - as expected. CCD Stability Test (11389) o Team is likely to request a 2-orbit repeat of this test. To characterize CCD whan MAMAs/LVPSs are on - o NICMOS/NCS NICMOS instrument in SAAOper today Dewar temperature stability being monitored Tiger Team plans for set point and circulator speed adjustments NICMOS SMOV likely to start in SMS257 (Sep. 14) o ERO P&S Status o o - Last two visits (1150851, 1150351) are scheduled for Monday Calendar/SMS builds SMS243 is delivered SMS250 Work is starting now Replans None Operations o FOT Nominal o PACOR Nominal o OPUS (TEllis) One WFC3 association for proposal 11647 error in calibration due to different readout sample sequences being used for the member exposures. o Howard Bushouse filed TRANS OPR 63367 to prevent associations of this type from being formed o manual database changes will be required to allow us to reprocess the members of the association as unassociated exposures. We also had 3 WFC3 associations for proposal 11934 error in calibration a new flat field reference file delivery is needed for these. o 63 more COS associations failed in the DADS catalog updates (known problem). On Wednesday quick-fix 2009.2k was installed. This included a new version of CALACS o allowed us to process 10 ACS associations for proposal 11889, which had errored in calibration with segmentation violations. It also included a new version of CALWF3 o enabled us to process 2 WFC3 associations (proposals 11570 and 11685) with Previous errors in calibration due to member exposures with different values of NSAMP. We also reprocessed 97 COS associations and 1 unassociated COS exposure which had previously failed in the DADS catalog updates. No fast-tracking for the remainder of this week. Archive Nominal