Office of Financial Management Washington State Major Project Status Report

advertisement
Office of Financial Management
Washington State Major Project Status Report
June 30, 2008
FINAL PROJECT STATUS REPORT
Agency Number: 699
Agency: SBCTC
Project Number: 05-3-015
GA State Project # 2004-033
School/Campus: Pierce College Puyallup
Project Title:
Health Education Center (COP Project)
Bill Reference(s): Chapter 488, Laws of 2005, Section 909 (5) (m)
HB2573 Laws of 2004 (904) (6) (l) Pierce Puyallup-$8,000,000
Laws of 2005 (909) (5) (m) Pierce Puyallup-$8,000,000
Contact:
Jim Taylor
Director of Facilities
Pierce College District
(253) 964-6588
jtaylor@pierce.ctc.edu
Project Description: This project is located in the City of Puyallup, Pierce County. The project is a studentfunded Certificate of Participation (COP) authorized by the Legislature in the 2004 legislative session and
reauthorized in 2005. The purpose of this project is to construct a student recreation and health education center.
The center is constructed on two levels and comprises instructional space, exercise space, locker rooms,
reception/lobby area, administrative offices, laundry, storage and related custodial, mechanical and electrical
spaces.
Square feet: 16,636 GSF
Scope changes: Due to funding limitations and construction cost escalation, the original project design intent
could not be met. Project plans reflect a reduction from the initial design, including the elimination of a
gymnasium.
1
Project Total Cost:
Phase
Predesign
Design
Construction
Other (Approp/Non Approp)
Total
Biennium
2003-05
2003-05
2005-07
2005-07
Appropriation
Fund 522
Fund 147
R10 Fund 147
Fund 147
Amount
$20,000
$828,182
$4,600,000
$ 977,389
$6,425,571
MACC = $4,123,900
Schedule:
Predesign Complete
Start Design
Bid Date
Notice to Proceed
50% Complete
Substantial Completion
Final Acceptance
Budget Schedule
6/30/02
10/01/03
04/28/05
05/10/05
10/15/05
02/01/06
04/30/06
Actual/Forecast
10/01/03
02/21/07
04/18/07
10/30/07
05/08/08
07/15/08
Variance (wks)
0
95
95
99
109
109
Project Status and discussion of Critical Path for Construction: This project was delayed due to issues
related to the COP debt repayment schedule as approved by the State Treasurer’s Office. Total COP funding
availability was more restrictive than originally envisioned and required building redesign in order to fall within
funding limits. The project was successfully bid completed. All critical path milestones were met during
construction.
2
Contract Award History
The original architect agreement was reduced to the actual amount spent of $270,319, and closed out when the
project was discontinued due to inability to fund the project as designed. A smaller funding amount was
established, and the project was re-initiated with a reduced scope and revised program. The current architect
agreement is described in the table below:
A/E Agreement
Original Agreement
Revised Agreement
Amendments
Pending Changes
Total
Current Design
Contingency
$ 270,319
$ 5,500
$ 565,262
$ 0
$ 841,081
$ 40,000
Construction Contract (excl. sales tax)
Bid Award Amount $4,123,900
Change Orders
$ 155,307
Pending Changes
$
0_____
Total
$4,279,207
Current Construction
Contingency
$ 257,803
Potential for Project Cost Overruns/Claims: No overruns or claims
Discussion of Project Quality: The design phase of the project was executed effectively. The College’s leadership
team and internal constituencies, particularly student leaders, have been engaged in planning throughout the design
process. The firms of MSGS Architects and Opsis Architects were selected to design and oversee construction of
this project. Both firms have considerable experience working with the College and have developed good working
relationships with College personnel. Value engineering and constructability review were incorporated early in the
design phase to benefit quality control and project viability. The College’s infrastructure planning team composed
of representatives from Facilities, Institutional Technology, AV/Media, Safety/Security, Purchasing and our Access
and Disability Services Office has also played a key role in design. The general contractor, Kassel Construction,
has proven to be a very capable contractor and managed the construction phase effectively. The project was
completed ahead of schedule and well within budget.
3
Project Photographs:
4
Download