Office of Financial Management Washington State Major Project Agency Number

advertisement
Office of Financial Management
Washington State Major Project
Status Report, December 31, 2007
Agency Number: 699
Agency: State Board for
Community & Technical Colleges
Project Number: #2005-186
Project Title: Grays Harbor – Vocational Building Rehabilitation
Bill Reference: Chapter 26, Session 03X, Section 801
Project Description:
This project is the renovation and expansion of the GHC Vocational Educational
Building. Phase I is for the welding and automotive vocational programs to be relocated
into a 21,750 square foot building, combining both programs under one roof. Phase II
will utilize the freed up space for the vocational carpentry program, yacht building
program, maintenance department, grounds department, and shipping & receiving in the
existing 23,300 square foot 700 Building. This building will be renovated for optimal
usage.
Project Total Cost:
Phase
Predesign
Design
Construction*
Other (Approp/Non
Approp)
Total
* MACC = $3,908,000
Biennium
2003-05
2003-05
2003-05
N/A
Appropriation
Self-Funded
H19
H19
Amount
7,531
521,000
4,850,199
5,378,730
Schedule:
Predesign Complete
Start Design
Bid Date
Notice to Proceed
50% Complete
Substantial Completion
Final Acceptance
Budget Schedule
N/A
11/01/2005
09/01/2006
09/15/2006
04/01/2007
08/15/2007
09/15/2007
1
Actual/Forecast
12/31/2003
12/01/2005 (Actual)
12/07/2006 (Actual)
12/28/2006
6/25/2007
11/26/2007
01/15/2008
Variance (wks)
+4 Weeks
+9 Weeks
+3.5 Months
+7 Weeks
+13 Weeks
+16 Weeks
Project Status and discussion of Critical Path for Construction:
At this point Phase I is nearly done. The project is 99% finished. The most recent
contractor pay application showed 99% of the work completed. All that is remaining are
a few remaining change orders that need to be costed out and approved, and final closeout
needs to be billed.
Contract Award History
A/E Agreement
Original Agreement
Amendments 1-22
Pending Changes
Total
Construction Contract (excl. sales tax)
Site Prep/Pile Pkg.
$ 263,373
Building Pkg.
$3,663,500
Change Orders
$ 112,451
Pending Changes
$ 6,500
Total $4,045,824
Construction
Contingency
$ 47,254
$391,582
$161,709
$ 35,794
$589,085
Total Other Services $ 51,000
Potential for Project Cost Overruns/Claims
Not at this point. We are working through the process of final closeout.
Discussion of Project Quality
Outstanding! This project has gone quite well, and the contractor has done an excellent job
of performing the project with high quality workmanship. We are very happy with the
results. We recently took our Board of Trustees on a tour of the facility and they were quite
favorably impressed.
Project Photographs
The following selected photos illustrate the project to date. A complete chronology of the