Office of Financial Management Washington State Major Project Status Report December 19, 2007 Agency Number: 699 Agency: State Board for Community & Technical Colleges Project Number: 02-2-685 & 06-3-019 Project Title: Mukilteo Hall and Black Box Theater Edmonds Community College Bill Reference: Chapter 520, Section 5152, Laws of 2007 Chapter 520, Section 5256, Laws of 2007 Chapter 520, Section 5252, Laws of 2007 Chapter 371, Section 222(5)(e), Laws of 2006 Chapter 488, Section 749, Laws of 2005 Chapter 488, Section 909(5)(e), Laws of 2005 Chapter 26, Section 796, Laws of 2003, 1st Special Session Project Description: This project will provide Edmonds Community College with a new Instructional Lab Building (Mukilteo Hall) that includes a black box theatre on our Lynnwood campus. This project will also provide a sprinkler system in the adjacent building as required by City fire code. In addition, a planned remodel of Lynnwood Hall 2nd floor has been combined with the sprinkler system installation part of this project. This was done to take advantage of the existing construction down time in the facility, and minimize disruption to campus students and staff. Mukilteo Hall will provide the College with much-needed additional basic skills labs, specialized computer labs, multi-use classrooms and faculty office space. We are in a continual state of growth, both in the number of students as well as in the number of programs and classes we are offering and this building will help to satisfy our ability to provide quality education that the community has come to expect from Edmonds Community College. Mukilteo Hall will help us to consolidate and improve programs and services to better serve the students and to add faculty office space that is required by contract. Mukilteo Hall will house our Theater Arts program, Developmental Education, International Education and Math lab programs, as well as their faculty and support staff. The black box theatre part of this project will give our campus a facility in which we can train students in theatre and technical production. In addition, the theatre provides us with a flexible performance space for a variety of theatrical and musical productions, as well as a gathering place for special events such as Speaker Series, Film Series, etc. The theatre will be constructed 1 through COP funding along with the construction funds for the original Instructional Lab Building. The project involves working with representatives from each of these areas to help facilities and the architects design the most efficient and effective building for their programs. Project Total Cost: Phase Predesign Design – Building Design Biennium 2001-03 2003-05 2005-07 2005-07 Appropriation F55 - Fund 057 G22 - Fund 057 R10 - Fund 147 H02 – Fund 057 Construction - Building* 2005-07 2005-07 2003-05 H02 - Fund 057 R10 - Fund 147 G22 - Fund 057 R10 – Fund147 H02 – Fund 057 G42 – Fund 955 H12 – Fund 955 H14 – Fund 060 I41 - Fund 060 I17 – Fund 060 R10 – Fund 147 Other (Approp/Non Approp) Other (Approp/Non Approp) Other (Approp/Non Approp) Total 2005-07 2003-05 2005-07 2005-07 2007-09 2007-09 2005-07 Amount 68,838 939,060 481,409 1,163,000 11, 906,000 3,590,000 2,000,000 78,591 1,421,832 94,051 218,313 1,145,000 617,900 275,000 419,462 $24,418,456.00 * MACC = $11,858,885 MACC = $9,366,422 – Instructional Lab Building MACC = $2,492,463 – Black Box Theater Schedule: Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule 4/02 7/03 5/05 7/05 4/06 2/07 4/07 2 Actual/Forecast 4/02 5/04 5/06 5/06 4/07 12/07 1/08 Variance (wks) 0 40 52 40 52 40 36 Project Status and discussion of Critical Path for Construction: We have substantial completion at this time and contractor is finishing up punch list. We have occupied the facility. Critical Path: Certificate of occupancy from local jurisdiction. Contract Award History A/E Agreement Original Agreement Amendments Other Agreements Pending Changes Total Current Design Contingency Construction Contract (excl. sales tax) Bid Award Amount $13,972,200.00 Change Orders $ 2,718,231.89 Pending Changes $ Total $16,690,431.89 $ 22,660.00 $ 1,407,433.38 $ 195,841.00 $ $ 1,625,934.38 $ Current Construction Contingency $ 153,296.59 18,474.62 Potential for Project Cost Overruns/Claims No further cost overruns are expected. Discussion of Project Quality This project follows established campus building standards, and includes current City and State code and practice. Project Photographs: Mukilteo Hall: exterior of building 3 1st floor entry/lobby: Black box from above: Learning Support Center: Math Lab: Part time faculty offices: Classroom: Computer lab: 4