OPEN F I L E REPORT 78 COST TO MINE COAL I N NEW MEXICO DAVIDTABET STEVEFROST FRANKKOTTLOWSKI NEW MEXICO BUREAU OF MINES AND MINERALRESOURCES (111 cow ' TO XIXE COAL IN NEW ~ X I C O , 1977 Thz c o s t of ninin3 coal varies with the each operation. . gxeater than Xining cosks for underground and small strip mines a r e for l a r g e strip nines. The r a t i o of overburden t o seam thickness, and t h e mining of a s i n g l e t h i c k ca:;sss differences in costs. mining method ana w i t h seam ormultiple seam mining , Comparison with b7yoming an3 Montana coal- mining costs. must t a k e i n t o account t h e i r t h i c k e r seams a t sha1lo.w' depths, and t h e lower s u l f u r and ash content i n those northern states. . . y o s t new n i n e s i n Mew Mexico w i l l need t o add l a r g e c o s t s f o r c o n s t r u c t i n g r a i l r o a h s to their mine s i t e s . With ongoing i n f l a t i o n i n c o s t s and reclamation (evea with larger of c o a l ) t h e c o s t of equipment, l a b o r , equipment arid mining of l a r g e volumes of s t r i p mined c o a l i s n o t l i k e l y t o d e c r e a s e . from $8.00 per ton. A study done f o r t h e Energy Resources Boardby Paul weir Company on s t r i p mined c o a l c o s t s gave t h e normal New Mexico operating conditions . i n t h e San JuanBasin as follows: (1) subbituminous coalaveraging 9,500 Btu p e r pound; (2) l e n t i c u l a r bedsranging but with the average up t o 25 feet-. i n t h i c k n e s s 5 t o 1 2 feet, 'containing shale partings; t o m u l t i p l e seam mining; (4) s t r i p p i n g t o d e p t h s little or no rehandlingofspoil; burden and the coal; loaders. Including ( 5 ) use o f ( 6 ) blastingtheover- an8 (7) mining the coal with shovels sone reclamation costs, ( 3 ) sinsle from 30 to 150 feet (depending on favorable overburden t o c o a l t h i c k n e s s r a t i o ) ; draglineswith akout. . . ' and frontend and not calculating any profit&;, they arrived a t a c o s t p e r t o n of $7 -53 o r 39.6C per mLllion Btu (for 9,500 Btu c o z l ) . Nostof the reclamation i n t h e a r e a , such a s a t t h e Navajo Wine, r e q u i r e s i r r i g a t i o n , which adds about '30C per ton, for a t o t a l of (without profit) $7.83 per ton or 41.2C per million BtuI The single pu5lic testimony on c o s t s was given by P i t t s b u r g Xidway Coal Mining Consany f o r t h e i r McKinleyMine: ton, cost G 1970 p r i c e $3.41 p e r $3.21; 1971 p r i c e $3.46, c o s t $2.86; 1974 p r i c e $4.10, cost $4.88; and 1975 p r i c e $7.27, c o s t $8.09. Thecompany noted t h a t t h e h i g h c o s t s i n 1974 and 1975 were p a r t l y caused by gearing up for larger production. The ad5ition of heavy ezuipnent andexpanded haulage syskem werc t h e most expensisie 'of additional items. The review of c o s t s b y the Federal PowerCommission OztoSer1976 report, for Zune 1976 (for stean coal Zn t h e i r 15 fed t o t h e San Juan a n d , ~. - ~~ 0 -2- €om- Corner Porsierslants),gave 25.6C p"r.million Btu. purchssed over $4.80 perton(average The Xzvajo ana San Juan blines use large equipnent 10 y e a r s ago, so t h e i r a perio3.of time beginning about c a p i t a l c o s t s a r e nilch lower than f o r equipment c o n t r a c t e d f o r i n 1976. t h e southern ind southeastern part The F r u i t l a n d c o a l s i n San Juan Basin, such a s those near Star $7.53 to $7.82 p e r t o n o r and thus they vrould c o s t 43C t o 44.7C per million B t u t o mine. of t h e S t a r of .the Lake, will more nearly average 5,750 Btu per pound on an as-received basis, addition,thecoals 9,022 Btu/lb) or In . Lake area w i l l probably.require washing t o c u t down on the high ash content, . . and t h i s w+l1cost. $1.50 to $3.00 per ton depending mainly on -costs for obtaining the water from deep wells.. The c o s t of mining c o a l underground is far g r e a t e r t h a n t h a t of strip mining. cokingcoal. I n New Xexico, theonlylarge The expense of t h i s underground mining is compensated f o r by the higher market value of coking coal. . .. Coking c o a l beds i n Nev7 Mexico (1) 4 t o 1 4 f e e ti nt h i c k n e s s ; involvethefollowingparameters: . undergroand c o a l mine is for (2) l e n t i c u l a r b=ds t h i t are e s s e n t i a l l y h o r i z o n t a l b u t . i n t e r r u p t e d b y f a u l t s , r o l l s , andpinchouts; ( 3 ) v a r i a b l e roofranging badly fractured shale; and ( 4 ) contain sporadic fronr hard sindstone to lenses of hardsandstone. Zongwall mining p a n e l s f o r t h e underground mines, continuous mining units, and a coal clean'ing plant are necessary cost parameters f o r coking coal production. For cleaned coal, the P a u l V7eir Company derived 4 d i f f e r e n t t y p e s of operations depending on s i z e of t h e underground mine, type of opening (shaft, slope, .or outcrop opening), and type ofmining- The combination of o p r a t i o n parameters most similar t o t h a t o f t h e p r e s e n t ground mine of Kaiser of cleaned coal. York Canyon under- S t e d Corporation yielded a c o s t of $25.04 per ton The l e a s t expensive mining c o s t t h e y c a l c u l a t e d was $21.11 per ton. Calculations by Paul Weircompany c o s t of money ( i n t e r e s t ) f o r c a p i t a l did not take i n t o consideration equipment, o r c o s t of r a i l f a c i l i t i e s , water sup2ly and otiner o f f - s i t e expenses. Kaiser opms most of the reserves of coking c o . a l . i n t h e Raton Field. They also own and o p s r a t e t h e Sunnyside Mine near Price, Utah. This mine .. . -3has one of t h e best proCuction records i n 'ih.. country, thus are lower thanthose addition, the for the underground YorkCanyon mining costs In Mine near Raton- Sunnyside lline i s about 500 miles by r a i l c l o s e r to the' Fontana s t e e l p l a n t s of Kaiser i n California, and t h e r a i l r o a d t i o n costs are less, . transports- . . . . _ David Tab& . Steve Frost . . Frank Kottloivski New MexicoBureau of :-lines and Xineral Resources d i v i s i o n of mew Mexico Tech This brief review i s a su;nmary of material requested by t h e Xew ~~ Mexico Energy Resources Board t o e v a l u a t e c o s t s of coal mining i n Xew Mexico. Costs a r e based i n l a r g e p a r t on a r e p o r t by Paul F7eir Co,, Inc, 21 February 1977 .. .. M I N I N GC O S TE S T I h I A T E S T Y P I C A LN I N E S( H Y P O T H E T I C A L ) STRIP ANDUNDERGROUND S T A T E OF NEW I . E X I C 0 \ . Paul Weir Company Chicago, Illinois YOIS NO. 2364 IJovember 29,. 1976 ' \p .. x TableofContents , P a g e .. I. . INTRODUCTION 11. 1 SUt*PGRY ' 4 Assumed C o n d i t i o n s . UndergroundHine(s) S t r i p Mine . 4 5 E s t i m a t e d Costs UndergroundMines 6 C a p i t a l Costs ' [ I n i t i a l B r i n g Mine To F u l l Capacity) 6 O p e r a t i n g( P r o d u c t i o n ) Costs 6' S u r f a c e ( S t r i p ) Mines 7 C a p i t a l Costs ( I n i t i a l Bring Mine T o F u l l Capacity) 7 O p e r a t i n g( P r o d u c t i o n ) costs 111. 7 . UNDERGROUND MINES 8 C o s t Estimates, U n d e r g r o u n d & l i n i n g , Coments 10 * IV. Case A Cases B, C, . V. 19 COAL PREPARATION PLANT & 19 20 D STRIP XINE t7 i 21 Table of Content (Continued) Tables . 1. Hypothetical Underground Mines7 . Metallurgical Reserves- New Mexico, - Bring . Initial Capital. Cost Estimate Mine To Capacity(Thousands of Dollars) 2. Hypothetical Underground Mines- . Metallurgical Reserves- New Mexicor Performance Statistics and Costs of Production . Page . . . . . . .. . . 12 . . 13 ~. 3. 4. 5. 6. 7. \ Force 8. Coal (Unwashed) Hypothetical Underground Mines Metallurgical Reserves- New Mexicor. Summary of Depreciation Costs ,- 14 Hypothetical Underground MineMetallurgical Reserves- New Mexico, Alternative (Case) A, Proposed Labor Force Hypothetical Undergroun-d MineMetallurgical Reserves- New MexicoI Alternative (Case) B, Proposed Labor Force .. Hypothetical Underground Mine'Metallurgical Reserves - New Mexico, Alternative (Case) C r Proposed Labor Force Hypothetical Underground MineMetallurgical Reserves- New Mexico, Alternative(Case) D, Proposed Labor . . 18 Hypothetical Strip Mine- Steam Coal, New Mexico, Estimate of Capital Expenditures, 5,000,000 Tons Per Year Of Raw ' 24 f. .. ii . . .. . . . . Table of Content(Continued) Tables(Continued) - 9. H y p o t h e t i c a lS t r i p Mine Stezm Coal, New Nexico, Estimated Cost of Production, 5 , 0 0 0 , 0 0 0 Tons Per Year 10. H y p o t h e t i c a lS t r i p Mine - Steam Coal, New Kexico,Proposed Labor Force . . Flow Sheets (pocket, back cover) Conceptual FlOW Sheet Conceptual Flow Sheet - Case . - . A Cases B , C , ti D L . . iii . MINING COST ESTINATES ’. TYPICAL M I N E S (HYpM”rlET1CAL) STRIP AND UXDERGROLTND STATE OF NEW NEXICO %e Energy Resources Board (EP5), s t a t e of New Mexico, requestes Paul WeirCompany (Weirco) t o maketwo studies of costs associated wLth opening and operating new mines i n Eev7 Mexico. One was t o r e p r e s e n t a strip mine f o r steam coal; the second was t o r e p r e s e n t an underground mine i n the Raton area for metallurgical coal. These were not to be based on “site-specific“ conditions, but ., assumed conditions reasonably representative in our opinion on of t y p i c a l conditions that might be expected, based on our general knowledge of c o a l reserve characteristics-within the state. . Actual detailed m i n k layout (design) was not required, norwere t h e s t u d i e s t o include the degree of detail necessary for a c t u a l ’ impleinentation or operation. The objective was to provide preliminary order of magnitude c o s t e s t i m a t e s a ta confidence level of about 80 percent (4-20percent accuracy). I I While t h e ass& conditions, or combination thereof, obviously would not be those actually encountered in every case, we consider them to k be reasonablyrepresentative are within the desired accuracy and .we believe t h a t t h e cost estimates . based on t h e stipulated assumptions. All c o s t estimtes a r e i n constant November,: 1976, dollars.' . Neither the sco-x of our assignment nor time . available prmitted a cash flow type a detailed econonic p r o j e c t a n a l y s i s p r t i n e n t t o evaluation which would be relevant to, for instance, a s i t u a t i o n vis-a-vis t a analysis. ofcashflowsbased This would r e w i r e a . deta'iled yearly projection onan assmed sales realization figure. our opinion (based on current industry practice), producer today, However, i n we b e l i e v e t h a t a t o p u t i n a new n i n e , would probably e x p c t a projected for a s t r i p mine 15 percent return on equity capital after taxes (sowwhat more predictable) and a comparative 20 percent return minimum for an underground mine (less predictaSle conditions, particularly in the Raton area of New Mexico). W e have assmd t h a t t h e r e would not be any coal.preparation other than crushing for the strip-mined steam coal, but t h a t a l l of t h e underground-min>d c o a l k u l d be put through a preparation plant to yield a product for t h e metallurgical market. ~ Our estimates are presentel d in ..I the folic)wing sect i o n s of this report. Respectfully submitted, PAUL VEIR COPlPAl9Y . Dated: November 29, 1976 PAULW E I R CONPANY 0 . 11. sun Assumed Conditions . . Underground Mine( s ) Cases B,C,D ( 2 ) Case A (1) Annual Production Rate, Raw Coal , Tons 750,000 2,000,000 . 20 Mine L i f e , Years 20 ~8 8 Average Coal. Thickness, Feet 65 Mining Recovery, Percent 50 Tons/Acre-Foot, In Place 1,800 1,800 Tons/Elcre-Foot, Recoverable, Raw 1,170 900 9,350 7,200 Recoverable Faw Tons/Acre Total Fecoverable Reserves P q u i r e d , Tons 40,000,000 Total Reserve Acres Required . Depth t o Coal, Average, Feet . 4,273.5 5,000 Say ' Percent Clean Coal Recovery (Through Washing P l a n t ) Annual Production, Cleaned Coal, Tons Say X5,000,000 2,083.3 3,000 600 600 80% 80% 1,600,000 . ' . Notes: T L o n g w a l l (LW) and Continuous Miner (U.1) , Case A ( 2 ) TWO Examples: Continuous Miner Only, Cases B & C . me Example: LW and C M , Case D .? 600,000 Assumed Conditions .. Strip Mine Annual Production Rate, Paw Coal, Tons ' 5,000,000 Mine Life, Years 30 Average Coal 'ihickness, b i p r Searr, Feet 8 Average Coal Thickness,ImierSeav,Feet 10 Average Interval Between Seams, Feet 40 Both Seams Contain Irregular Partings Averaging, Feet Net FOX Coal Pecovery ( p i t loss & . d i l u t i o n ) % of coal in place 2' 88.2 Tons per Acre-Foot, In Place 1,800 Dip of Coal Seams, Variable up t o , Eegrees 4 Total Recoverable Reserves l?equired,.Tons X50,000,000 21 ,000 Total Area Disturbed by Ialining, Acres Total Area For Exploration, Acres say Minimum Depth of Marketable Coal, Feet 30,000 30 Maximum B p t h of Mining, Feet 150 Virgin, Stripping Ratio, Yd.3 O\rerburden/TonCoal .7 Portion of Overburden to be Rehandled, Percent 25. Effective Stripping Patio, Yd.3 Overburden/Ton Coal 8.75 Average Length of Coal Haul, P i t to Truck Dmp, Miles 3.5 Type of Overburden: Shales, Siltstones and Sandstones Requiring Blasting but providing Relatively C 4 Slop Stability- for Both Flighwalls .and SpoilNaterial . Wage rates: Approximately equivalent to International Union . of *rating Engineers, current rates a t Navajo Mine, based on the latest information we have. k. . . 5; :-. ... ._ e PAULW E I R COXPANU Estimated Costs UndergrocndMines Capital C o s t s . ( I n i t i a l - Bring Mine To Full Capacity) Case A Mine EQuipEent & Facilities, Installed Contingency,158 Sub Total 46,837,500 7,025,600 53,863,100 ' Preparation Plant (additional) ' Case B Case C 18,913,900 2,831,100 21,745,003 11,841,700 1,776,300 13,618,000. 12,000,000 Case I: 22,319,Z 3,347,9 25,667,1 3,600,000 3,600,000 3,600,O . . etc. Fnviromental &pact Studies, 200,000 150,000 150,000 including obtaining mining pernit Lease Acquisition (Royalty Basis) --------see Reduction Costs, Section 111 &serve Evaluation (Exploration, Testing I @tc.) 285,000 171,000 171,000 33.17 42.7841.47 .Per Ton, Rzw Coal (1) TOTAL, CLEANED COAL . 171,G Case B $15.42 $17.07 19.28 0.375 1.45 Costs 23.39 29.23 21e 34 0.30 1.60 Case C . $18.51 23.14 22 0.30 1.60 $24.10 $25.04 $23.24 $21.105 . . 39-45 . 49.31 Costs Case A B r Ton, C l e a n Coal Basis (1) G W . 34.22 . Opxating(Production) Add Prep. Ikpreciation Plant Add Prep. Plant *rating ---- 66,348,100 25,666,000 17,539,000 29,588,l G W D TOTAL Cost Per Annual Ton, Xaw Coal .Cost Per AnnualTon, Cleaned Coal ( @ 80% recovery) I 150,C . Kotes: m x c l u s i v e of preparation plant capital depreciation Please refer to following sections for mre detail, & opratirig costs, Case D . $17.76 * 20 0.30 1.60 ' PAULW E I R COXPAXY e @ EstimatedCosts Surface (Strip) Bines - Brinq . Capital Costs ' ( I n i t i a l Mine t o F u l l Capacity) . wine FQuipnent & Facilities, Installed $ Contingendy, 10% 74,235,000 -7,424,000 Subtotal Lease Acquisition (Royalty Basis) .. .. 800,000 - - - - -.- - - - -'See Production &serve Evaluation (Exploration, Testing, etc.) Costs 3,920,000 Total Raw C o d , - 81,659,000 . . Enviromen&l mpact studies , etc. , Including OStaining Mining Permit Cost Per Annual Ton, I $ "84,379,000 s , . *rating 16-88 . . (Prduction) Costs .. Total Cost Per Ton of Raw Coal, including Allowance for Percentage Ikpletion $ - 7.53 1 Please refer t o following sections for m r e d e t a i l . ..., PAULW E I R COXPAKY e . . a The northern bundary of Colfax County in. the northeastern p r t i o n o f New Kelexico forms p a r t of t h e New Nexico-Colorado S t a t e Line. The coal-bearing 'area in' the north-central' section of t h e county, . . , New Nexico portion desiinated as t h e Raton f i e l d , coinprises a l l of the of t h e Raton &sa region. This region is the sole source of p a t e n t i a l underground metallurgical coal supply in the State. .. Located i n t h e a b v e r e g i o n some 40 miles west o f t.h. e c i t y of Raton and 1 0 miles south of, the Colorado border, Kaiser Steel 1 Cor?. o p r a t e s t h e o n l y underground mine i n New Kexico a t t h e p r e s e n t time. Ihe coal' seam being mined ranges from 1 4 feet t o less than 4. feet i n The l e n t i c u l a r seam is relatively flat-lying thickness. L but interrupted by many f a u l t s , rolls and pinchouts, in an erratic indiscernable pattern. A major j o i n t p a t t e r n running north-south over the coal, the i . imsiiate roof roaterial ranging frum strong sandstones to badly broken s h a l e . T i e d i f f i c u l t . r e s u l t s i n massive roof blocks . mining conditions created by unpredictable roof and f a u l t i n g a r e f u r t h e r aggravated by t h e v e r y h a r d bands of sandstone t h a t occur sporadically within.the coal seam. L Early mining and exploratory data led Kaiser t o c o m i t t o bulk extraction by the longwall method of mining rather than by.the more c o m n L ( it nh e U.S.A.) rwm and p i l l a r methods. Entry developnent employs continuous miner u n i t s . . . >:: PAUL \vEXR COMPANY (I) Tne known g e o l q y of the Faton Field suggests that. the Kaiser experience might be typical of the conditions t o be expected i n any- underground nine developed within this f i e l d . It may be possible, however, i n c e r t a i n a r e a s t o i s o l a t e s m a l l e r b l o c k s o f r e s e r v e s where . . mre uniform conditions rjould permit a more regular and productive . performance. . ... mine size, therefore, 'might range from a In our opinion, small e f f i c i e n t 0.75, million-ton per-year highly productive olpration i n uniform conditions t o a l a r g e r less efficiently productive mine i n sporadic widely varying condftions ' b u t with s u f f i c i e n t equipment capacity t o s u s t a i n s a y 2 million tons per year annual production. . . . Lack of any . %e estimates we presentconsiderbothcases. d e t a i l e d or site-specific geological information and th2 short t h e available for preparation of these estimates necessitate that the .. estimates be.based on a s e t o f assumed conditions and parameters, generally as f o l l o w : 1. The average mining heights will vary from 6 t o 14 feet, r e s u l t i n g in anoverallaverage 2. mining height of 8 feet. . Mining conditions w i l l be such t h a t t h e averageproduction from a * continuous miner u n i t will be 500 tons of raw c o a l p c r u n i t s h i f t i n the small, more e f f i c i e n t mine, and only 400 tons of raw c o a l when used for development only i n t h e l a r g e r l e s s e f f i c i e n t m i n e (Case A). 9: 3. Tne above conditions w i l l p e r s i s t over an area of reserves capable of supporting a mine producing 2.0 million tons per year 0.75 million tons p r year (Cases (Case A ) o r B, C, D) for a period of a t l e a s t . . 20 years. . . . 4. . Access t o any of the minable seams will be obtained.through a slope or . . v e r t i c a l s h a f t s t o apgxoximately a 600-foot depth of cover except f o r Case C - see below). . 5. within the confines Cost estimates are liqited t o those costs incurred of .the mine. . The cost estimate tables also footnote other exclusions made in these estimates. 6. Construction and e g u i w m t c o s t s r e f l e c t c u r r e n t NovemSer, 1976 prices. "here is no allowance f o r future inflation for replacenents of short-life of equipment or for extension 7. mining facilities. .. Current UEP?A wage rates and benefits have.been applied, including the .. welfare fund, b u t blacklung 8. CostEstimates, k n e f i t s a r e excluded. UndergroundMining, ' Comments . The estiaated capital costs are presented Tne estimated oprating costs are ' i n Tab& No. 1, following. summarized i n Table No. 2. In addition to t h e two basic mine capacity alternatives ( 2 m tpy and 0.75m tpy), we have attempted t o r e f l e c t i n a l t e r n a t e Case C t h e e f f e c t o f a more conservative t. . ....... . I (continuousminer) u n i t s h i f t Brforrnance on t h e smaller (0.75 million ton . per year.) mine, where a l l mine openings t o t h e surface a r e t h o u g h o u t c r o p openings ( a s a t t h e p r e s e n t Kaiser mine). Case D is a f o u r t h a l t e r n a t i v e which assumes a coinbination of longwall and continuous mining t o p r d u c e t h e 0.75 million annual tons run-of-mine coal. . . for : Table No. 3 is a depreciation schedule, inchding provision replzcementof . . short-life items during l i f e of mine. . . Table Nos. 4, 5, 6 and 7 preseni manning tables. f o r Cases A, B, . C and D, respectively. - . . C u r r e n t e x p r i e n c e i n ucderground coal mining i n New Mexico and i n . . operations in Colorzdo suggests that while local high production performance canan3 will he obtained, it w i l l not represent the field average. Any .. ..: .. high performance i n t h e p a s t h a s normally been'obtained by v e z y s e l e c t i v e mining, leaving large reserve areas with changing seam t h i c k n e s s and/or ' varia3le mining conditions (roof and f l o o r ) f o r l a t e r mining, From what is currently known of coal deposition in t h e +ton Field, we believe that the adverse effects t o be expected as a r e s u l t of the many .. v e r y l o c a l v a r i a t i o n s i n the coal seams and i n roof and floor conditions a r e m r e l i k e l y t o result i n production costs that are closer t o t h e more conservative projections (Cases Cor D). L. '11; Table No. 1 - HYPOTNETICAL 1IE:DERCROUND MIXES- E l ~ T ~ ~ L L U R ~ I C A 1 , ~ R E S E R V NEIJPIEXTCO I~S INITIAL CAPITAL COST ESTII.IATE - ]$RING MINE TO CAPACITY (TIIOUSAWJS OF DOLLARS) . , .. -A CASE 0.75 2.0 AENUAL PRODUCTIO~RAW COAL (KILLIOX TOSS/YEAR) -C -B . . 0.75 . -D 0.75 Item NO A . 1 2-3 4 5 6 7 8 9 10 11-12 13 . 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Land A c q u i s t i o n t S i t eP r e p a r a t i o n NineBuildings & Facilities Water Supply & Sewage Treatment Surface. E l e c t r i c P o c eDr i s t r i b u t i o n Intake A i r Shaft Return A i r S h a f t Emergency Man Hoisting System Mine Fan Mine Slope Mine SlopeEqsipnent Mine SlopeMoistSystez Surface Nobile Equipnent Underground Face Equiprent Main-Line Underground Conveyors Underground Rock liandlinz Equipaent Underground Road :,:aintenence Equipment . Underground Electrical Porier D i s t r i b u t i o n Underground Plain-Line Tra-sport Equipment Underground Rock D u s t E q u i p l e n t Underground Comunicatibns Equipment Underground Safety, Rescue, F i r s t A i d Underground Water Handling Facilities Rotary Breaker Preparation Plant seeseparateestinate S t o r a g e L R . R . L o a d i n gs-esee p a r a t e e s t i m a t e - $ ' 175. 700 150 ' 850 1,500 1,500 450 300 2,750 1,500 650 . 500 27,700 1,500 160 150 500 600 170 60 250 200 GOO 200 $ 150 500 120 600 1,500 1,500 450 150 2.750 $ - - . . -. 150 --- 1;ooo 650 400 5,500 800 100 I00 275 275 80 30 100 100 200 : 400 6,600 1 .OD0 100 100 300 300 90 40 100 100 - $17,330 . . Engineering (27. C o n s tC r uocsttiso)n Overhead t Adnin. (5% C o n s t r u c t i oCno s t s ) Total 875.5 2,188.7 $46,837.5 353.5 883.8 . $18,913.9 $11,841.7 FSi eulpde r v i s i o n Con s tsst r u Tcotteadl (2% Direct Costs) Contingency 15% . GRAND TOTAL (a) . CapitalCost/AnnualTon (MineOnly)(R.O.M.) NOTES: (b) $10,850 346.6 217 $17,676.6'$11,067 7,025.6 2,831.1 353,863.) $21,745.0 $26.93 - $28.99 - 221.3 553.4 1,776.3 $13,618.0 $34.22 $18.16 = ( a ) Exclusive of c o s t o f money ( i n t e r e s t ) and i n f r a s t r u c t u r c s u c h a s rail facilities;watersupply; mainincoming power s o u r c e t o mine si'te; h o u s i n go rw o r k e rt r a n s p o r t a t i o nt o mine; r a i l r o a d to mine.For costs of exploration, environmental studies, mining permit see Summary, S e c t i o n 11. (b) See Summary f o r A d d i t i o n a l C o s t s C a p i t a l i z e d . >*: - $ -' ,150 500 120 GOO 1,500 1,500 450 150 2,750 1,000 650 400 8,300 1,000 100 IO0 300 350 90 40 LOO 100 . 200 $42,915 858.3 $43,773.3 T o t a l Direct Costs I50 500 120 GOO -. $20,450 409 $20,859 417.2 1,043.0 $22,319.2 3,347.9 $75,G67.1 - 0 . Table No. 2 HYPOTHETICAL ~'GZRCXOLIiiDMINES- METAL1,URCICALRESERVES PERFORWXE . - NEW MEXICO STATISTICS AND COSTS OF PRODUCTTON n ' A CASE c D . A l l on Raw Coal Basis Production,, Tons PlillioE Annual 2.0 0.75 215 Annually Days Operation 215 9,302 Production, Tons Daily Average -7 - . 6 . . 215 . 3,486 Unit Shifts ProductionIDay 11 0.75 215. 3,486 Continuous >liner Longwall . 0.75 .. 3,486 - 10 G 2 TonslonitShift Continuous Hiner Longwall ,. 400 814 350 . .- - 500 . . .. 320 81.4 Units of EquiDaent Recuired Operatin; . Continuous :.liner Longwall ' . -- 6 Spare ContinuousMiner Longwall Total Total .I -1 - ContinuousMiner - Longwall Daily Elan Power Required a t >line 'Average CostIXan-Day . - -- 1 -6 " 5 243 193 232 208 $100 $100 $100 $100 18.07 21.99 . 16.76 Ls.03 - Raw CoalBzsislTon Labor S u p p l i e s & Power UEfW Welfare Fund FacilitiesExtension & Insurance Property 6 OtherLocalTaxes A d m i n i s t r a t i v e C o s t s a t :.line Royalty T o t a l Cash Cost of Production D e p r e c i a t i o n - ( s e es c h e d u l e ) Depletion T o t a l C o s t of Production XOTES: - .. 7 4 TonsfMan-Day Cost of Production 5 G 3 . ,. 4.54 3.40 1.29 0.25 0.30 0.15 0.75 2.94 1.80 $15.42 5.53 4.15 1.40 . 0.25 0.30 0.20 0.75 , 0.20 0.75 5.9G 3.75 1.45 0.25 0.30 0.20 0.75 $12.58 $14.68 $12.G6 . $10.68 li - 6.65 5.00 1.53 ' 0.25 0.30 2..69 1.80 2.03 1.80 $17.07 $18.51 . . (a) I n c l u d e s d i r e c t wagesand s a l a r i e s and a l l f r i n g e b e n e f i t s . (b) Dbes n o t i n c l u d e : (1) A d m i n i s t r a t i o n o r s e l l i n g c o s t s away from the mine. (2) T r a n s p o r t a t i o n c o s t s mine t o p r c p a r a t i o ~ ' p 1 a n t and ' . 3.30 1.60 $17.76 Table No. 3 HYPOTHETICAL UKDERGROUNDWTSES - METALLURGICAL RESERVES - N E W MEXICO SUKMRY OF DEPRECIATION COSTS Annual ' Iten YKS. No. Life " 1 2-3 4 5 6 7 8 9 10 11-12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 $ 20 10 10 10 8,750 70.000 15;OOO 85,000 150.000 I50;OOO 22,500 30,000 137,500 150,000 32,500 100,000 3,957,150 125,000 . 22,S57 . 21,428 . 50,000 10 10 20 10 20 10 20 5 7 12 7 7 10 10 20 20 5 20 20 20 20 . . .. .S -- D 7,500 50,000 12,000 60,000 x50,000 150,000. 22,500 . . X37,,MO 100,000 32,500 80,000 . 1,185,715 83,333 ' -- - ' -- 14,285 30,000 30,000 4,500 2,000 ., 5,000 10,000 -. " . 547,405 Total DepreciationlTon, Raw . --- 30;ooo see separateestimate see separate estimate 7,500 $ ..7,50o .50,000 50,000 12,000 12,000 60,000 60,000 150,000 150,000 22,500 15,00015,000 15,000 137,500 100,000 32,500 80,000 80,000 785,715 942,857 66,667 83,333 14,285 14,265 14,285 14,285 14,265 27,500 30,000 27,500 30,000 4,000 4,500 1,500 2,000 20,00020,000 20,000 5,000 5,000 10,000 10,000 ' 8,500 3,000 $5,836,590 . -.. . . - .. $ 60,000 Supervision, Engineering Administration Overhead & Contingency _. ..- .Annual Annual c Annual A 220,750 260,855 138,400 $2,014,202 $2.94 - - .... .. $1,519,160$2,476,973 $2.03- $3.3q . . Table No. 4 PROPOSED IADOR FORCE Per - Facc(Continuous Miner) Operator Miner Continuous Continuous Miner Helper Shuttle Car operator Roof BoltingNachineOperator Utility Ventilation ' Mechanic Total Face (Longwall) Shearer Operator Chock Man Head & T a i l g a t e Utility Mechanic To t a l I- - Undercround General Supplies Drainage & Water Supply Ventilation Maintenance Extension of F a c i l i t i e s Belt Patrol Roadway Maintenance , Timbering Rock Dusting Day'Men (General P o o l ) Rock Handling Fire Boss Examiner Tot81 - I L L Underqround Supervision General Mine Forenan A s s i s t a n t MineForeman 2 S e c t i o n Foreman Maintenance Superintendent Maintenance Foreman LongwallSuperintendent S e r v i c e s Foreman Total Surface Bathhouse Attendant Hoist Operator Lamp A t t e n d a n t EquipmentOperator Laborer b Miscellaneous Shop Total SupervisionSurface (EachMine) Mine Superintendent Surveyors Technicians S u r f a c c Foreman k'archouse Clerical Shop Forcman To t a 1 TOTAL I'I'.OI'OSI:D 1 1 2 2 1 1 1 9 - SShhi if ft t - 3rd - . Shift . . 5. -. ' Total _ I 2 1 5 10 10 5 5 5 45 - " . - 5 ' 5 10 10 5 5 5 45 ' .Zn< 1st Unit - ' 12 11 22 24 11 2 ' 4 I. .I .. ' 11 105 " 4. . " 14 I 15. .' '. .. 2 4 6 . 3 2 3 1 , 4 . 9 - 11 . 4 3 4 6 . 6 4 4 9 9 5 28 5 28 . 4 - -- 12 3 12 20 24 4 ' 10 . I. 2 3 - . . 8 " 5 8 3 : 3 . 66 53 - 3 26 c - - 7 1 6 2 :3 - . . 9 8 10 10 20 8 9 145 - 10 2 .10 1 2 7 1 1 28 ' 3 8 ' 12 27. 15 84 5 12 5 . 6 . 12 :18 , ' .. 17 . 1 1 . . 1 1 1 1 1 - 1 3 3 2 10 18 2 2 10 - * - . ' . 1 1 1 3 2 ' 3 11 - .." 3 ' 3 3 9 6 15 39 1 6 4 1 1 .. x 15 L/&OI< >Oi;CE .. 1 1 1 3 1 3 3 2 20 - _. - Table No. 5 HYPOTIIETICAL UNDERCROIISD NINE * - METALLURCICAL RESERVES - NEW MI<XICO ALTERNATIVE (CASE) D PROPOSED LABOR FORCE Per Unit Face (Continuous Miner) Continuous Elin'er 0pera:or Continuous Eliner Helper S h u t Operator t l e Car Roof B o l t i n g Machine Operator Utility Ventiliation 1,lechanic Total 1 st 1 1 2 2 1 1 1 3 3 3 27 -9 - TOTAL PROPOSED LABOR FORCE 9 3 2 4 3 4 - 12 7 . 2 4 6 4 6 1 - 2 31 - S u p e r v i s i o n S u r f a c e (Each Mine) Hinesuperintendent surveyors Technicians S u r f a c e Foreman Warchoune . Clerical ShoIl Forr.:o:rn , ToLnl 9' 68 ---- 3 4 - 1 1 3 1 6 6 . 10 G 5 78 .-... ,l 3 8 1 ---6 14 1 3' 1 3 1 1 1 2 ' 6 12 - L .O 0 1 G -8 - 22 i 1 3 3 2 2 1 1 1 2 1 10 - 86 .- ' 7 . ---- - Surface Bathhouse Attendant Hofst Operator Lamp A t t e n d a n t TruckDriver Laborer & Miscellaneous Shop Labor Total 14 16 7. .- L . - 8 .. 7 6 Face (Longwall) Shearer Operator Chock Nan Head & T a i l g a t e . Utslity . Mechanic Total Underground Supervision General MineForeman ' A s s i s t a n t MineForeman S e c t i o n Foreman MaintenanceSuperintendent Maintenance Foreman LongwallSuperintendent S e r v i c e s Foreman Total Total 3 3 6 _ . Underground General SuDolies Drainage & Water Supply Ventilation Elaintenance Extension of F a c i l i t i e s Belt. Patrol Roadway Maintenance Timbering Rock Dusting Day Men (GeneralPool) Rock Handling F i r e Boss Examiner Total - Shift - 1 1 1 11 193 - . -. c . T a b l e No, G IISPOTIIET 1:ST)T:RGROUSDI4JNE - METALLllRGIChL ERV‘ES - R i W NEXICO ALTI:liXATIVE (CASE) C PROPOSED LABOR FORCE i Face (Continuous Continuous Eliner Operator 2nd Shift 1st , Shift Miner) 1 Continuous Miner Helper S h u t Operator t l e Car Roof BoltingNachineOperator Utility Ventiliation . Mechanic 45 Total c I . Per -Unit - 1 2 2 1 1 -19 5 . 5 5 5 . 10 2 - . . . Total 12 10. 21 22 10 10 12 97 - -5 - I . - . - -- -2 1 10 10 5 5 10 . 5 5 5 . 45 --- (Longdall) Face Shearer Operator Chock Plan Head 6. T a i l g a t e . Utility Mechanic Total . 3rd Shift I ... I . I - Undersround General Supplies Drainage h Water Supply Ventilation tlaintenance Extension of Facilities Belt Patrol Roadway P!aintenance Timberinl Rock D u s t i n g Day Men (GeneralPool) . Rock Handling F i r e Boss Examiner Total , 9 3 6 12 8 6 . 4 8 6 10 - 2 35 . 8 2 15 - 35 5 85 --6 1 3 1 17 2 - 10 22 1 - Undercround Suoervision ’ General Kine Forezan A s s i s t a n t Mine Foronan S e c t i o n Foreman MaintenanceSuperintendent Naintenance Foreman LongwallSuperintendent S e r v i c e s Foreman Total ~~ . ~~~~ Surface . Bathhouse Attendant HoistOperator Lamp A t t e n d a n t Truck Driver Laborer h I{iscellaneous Shop Labor Total Supervi.sion Surface(Each Mine S u p e r i n t e n d e n t Surveyors Technicians S u r f a c e Foreman Warchouse Clcricnl Shop I’orcraan TO L a 1 .. ‘ 8 13 Mine) TOTAL PROPOSED LMOR FORCE 1 3 2 . 1 ’ 1 1 1 10 1 .2 5 .” .... - --- - . T a b l e No. 7 HYPOTHETICAL U!!DERCKOUND EIINF. ' - *. METAI,LUI<GTCAI. Rk.:SIdWES - REU EIIIXICO ALTERNATIVE (CASE) I) PROPOSED IAUOR FORCE Per .-Unit Face (Continuous Continuous EIiner Operator Miner) Continuous Miner Helper O p eSCrhaurt totrl e Roof B o l t i n g Machine Operator Utilitv Yentifiation Mechanic Total - . Total 7 1 3 1 2 3 6 6 6 3 3 13 2 1. 1 Face (Longwall) Shearer Operator Chock Nan Head & T a i l g a t e Utility Hechanic Total 1st: Shift 14 8. 6 .3 27 2 2 k ' 3 2 3 2 3 1 11 3 1 6 k 9 . . . _ . - Underground General Supplies D r a i n a g e & Water Supply Ventilation Maintenance Extension of Facilities Belt Patrol Roadway Naintenance Timbering Rock D u s t i n g DayMen (GeneralPool) Rock Handling Fire Boss Examiner Total - - Underpround Supervision ' General Hine Foreman A s s i s t a n t MineForeman S e c t i o n Foreman MaintenanceSuperintendent H a i n t e n a n c e Foreman LongwallSuperintendent S e r v i c e s Foreman Total Surface Bathhouse Attendant Hoist O p e r a t o r Lamp A t t e n d a n t EquipmentOperator Truck Driver ShopLabor Total . S u p e r v i s i o n . S u r f a c e (Each Mine) Mine S u p e r i n t e n d e n t Survcyors Tec.hnicians S u r f a c e Foreman Warehouse Clcrlcal Shop I.'orcmnn Total ' TOTAL PI\OP&ED LABOR FORCE 8 62 -91 - 11 . -.5 28 7 2 - 3 2 4 4 - 12 3 3 2' 5 4 .. 4 6. . 6' 6 10 1 - '4 4 .-1 30 3 70 - 1 1 1 3 4 10 .1 1 --E 1 1 3. .. 17 3 3 1 1 1 1 I 1 4 2 6 12 - 8 20 1 4 2 1 1 1 1 .4 1 11 . "- 99. .. 2 1 1 1 . 1 11 208 - _. .. 10. N. COAL PREP?G?ATION PLANT - Preparation Plant Capital Cost Case A 2,000,000 Ton-pr-Year Mine, Fun-of-tline, (Underground Mining) . 750 Ton-pr-Hour Rated Capacity Note: Rotary BreakerCost Under.Mining Costs A. . Overall Raw Cos1 Storage & Equi,ment (10,000 Tons) Preparation Plant (750 Tons W L Hour) Heat dryer Clean Coal Storage (15,000 %ns) fa1 and loadins Unit. Train Refuse D i s p s a l & i?ater Suppiy. Total $ 1,000,000 8,000,000 1,000,000 1,500,000 Note: W i o t including Railroad trackage SEE FMN SHEET B. . . - CASE A - ( I n pocket, back cover) CapitalDistribution $ 'ikkuipnent & piping S t r u c t u r a l & Sidings . Foundations & Site Electricals Refuse disposal & Water supply . Erection Engineering @ 78 Two (2) trucks; One (1)bulldozer ' 4,000,000 900,000 260,000 -_ 1,500.,000 500,000 ' mtal 3,600,000 840,000 400,000 $ T2,000,006 ' .. Fer Ton Preparation Plant *rating Costs (Direct) Clean Coal Labor : Lubricants Materials: reagents 37 men @ $lOO/day & d i e s e l fuel Flotation Chemical flocculents and magnetite Kaintenance supplies & replacement Heat drver fuel I.. @ $20/ton fuel) for' . . Power @*6000 kwh Clean Coal = 1,600,000 tons per year @80%Yield from "of-Mine 2 Shift Operations, 1 S h i f t Maintenance/day, 215 days/year $ 0.50 0.08 0.04 0.10 0.40 0.18 0.15 $ W . ..- . Preparation Plant. Capital Cost - Cases E, C, and D 750,000 Ton-yxr-Year Hine, hn-of-Mine, (Underground Mining) 300 Ton-pzr-Hour Rated Capacity Note: Rotary Breaker Cost Under Mining Costs Overall A. '. . . Raw Coal Storage & Equipment (4,000 Tons) Preparation Plant (300 Tons ger Hour) Heat dryer Coal Clean Storage & Handling (a) Refuse Dispsal & V7ater Supply '%tal $ .. - CASES B, C, D - .. -0. ' 400,000 200,000 $ ~,600,000 , SEE FLOP1 SHEET 500,000. 2,500,000 (In pocket , back cover) . ' CapitalDistribution B. Ecpi-ment & piping Structure & Sidings Foundations & Site Electricals Refuse dis,psal & Water supply Erection hgineering One (1)t r u c k ; One (1)bulldozer $ 1,000,000 ' . lbtal 75,000 100,000 975,000 200,000 800,000 225,000 -225,000 $ 3!600,0m - . Costs (Direct) Preparation Plant *rating Fer Ton Clean Coal Labor : Materials: 23 men @ $lOO/day Lubricents & f u e l Flotation reagents - . 'Chemicals & IMagnetite. Maintenance suFplies & replaceaents . Power @ 2,OCO kwh * Clean Coal = 750,000 @ 80% = 600,000 tons per year 2 Shift Operations, 1 S h i f t Maintenance/day, 215 days/year ... . .... . . . ..- . ~ . ~... . . . .. . .. . $ 0.60 0.10 0.05 '. , . 0.15 0.50 0.20 . $m ' V. STRIP MINE A few s t r i p mines are c u r r e n t l y o p r a t i n g i n t h e northwestern portion of New Kexico. Others have been proposed. New t.Iexico will &cone an even It is likely t h a t more important source of .coal for eiectric pwer generation and for processing .into synthetic fuels. The c o a l s of t h e San Juan Basin are mostly sub-bituminous in rank and are non-coking. Tie beds are lenticular,, typically varying in thickness from zero to 20 feet o r more. .Also typical is the existence of one or more p a r t i n g s of variable thickness. Presently, mjninq is sometines i n a s i n g l e c o a l bed o r seam, sometines in.mu1tiple seams with varying intervals between seams. Typicaloverburden c o n s i s t s of sandstones, s h a l e s and s i l t s t o n e s i n d i f f e r i n g p r o p r t i o n s . The strata o f t e n d i p downward from o u t c r o p , with "average" dips of a few degrees, sometimes locally steeper. .. . . . .. Coal near outcrops is p a r t i a l l y oxidized by weathering, sometimes burned, t o average depths of some 25 t o 30 f e e t . we have usually considered coal For estimating purpses, under less than 30 feet of cover to b e non-merchantable. Tne nature of the overburden and the relative continuity, of coal deposits is such a s to be p a r t i c u l a r l y amenable to s t r i p mining with'large .. dragline typ excavators. With single-seam mining, a t depths of up t o 100 o r 120 feet,’ and with proper selection of equipmcnt, it can be pssible t o remove the overburdenwith material. l i t t l e or no rehandling of Mining might be feasible with draglines a t greater depths; much qreater however, t h e amount of rehandling of spoil increases rate than the increase in virgin overburden thickness.. -rating radius, t o boom-length) aze digging depth and dmping height (ali related critical factors. .Also i m p r t a n t , economically, is t h e s t r i p p i n g ratio. per .recoverabble ton of coal. u s u a l l y s t a t e d a s ‘cubic yards of overburden Tne maximum depth of s t r i p mining could b’e determined by (a) economics, or (b) p5ysical limitations of ‘factors. Tentatively, machines., or (c) some conbination of those 150 f e e t is a Gracticable l i n i t , we f e e l t h a t &.but although no dragline stripping of coal i n NewNeexico reached that depth as yet. . is known . t o have . . Mine s i z e could influence production costs, We f e e l t h a t there would be l i t t l e , i f any, economics of scale above 5,000,000 t o n s of coal per yeas under conditions typical of t h e San Juan Basin. . . For purposes of estimating capital and o p e r a t i n g c o s t s o f a hylpthetical strip mine, we have assumed conditions as l i s t e d i n t h e On t h e b a s i s of those assumptions, t h e estimated capital costs The estimated operating costs are presented in Table KO. ‘8, following. ... . ~. . . - . .. The summary ofpersonnelrequirements a r e summarized i n Table No. 9. are presented i n Table Eo. 10. It will & noted t h a t we show land reclamation cost $0.30 per ton of coal. The land affected wuld year, so t h a t cost is equivalent to i to be be about 7OO'acres F r $2,143 per acre. Our estimate for. land reclavation includes returning the land to approximately t h e original type of t e r r a i n , p l a c i n g a t l e a s t a p r t i o n of t h e "topsoil" type L . . material on . the surface, seeding, fertilizing If i r r i g a t i o n is required t o establish erosion (not wind erosion). vegetative cover, the cost orderof and controlling major water w i l l be s i g n i f i c a n t l y more, perhaps on t h e $1,500 t o $2,500 p e ra c r ea d d i t i o n a l .a o s ec o s t s mU1.d a t . least partly depend o n a v a i l a b i l i t y and location of a water supply, on the cost of distributing the water, and thelengthof time irrigation . would k continued. i t . t i - ._" . __ .. . ." .. . __ ,. . . . .. .. .. . T a b l e No. 6 tNPOTlIETICAL STZIP N l X E - STEAM COAL N W MEXICO ESTIEIATE OF CAPITAL EXPENDITURES 5,000,000 T O 3 PER YEAX OF R N (UWASHED) COiL Years . No. Life Rewired - Itea - 15 3 Overburden Drills, for 12" t o 15" DiameterHoles 30 2 Loading Coal Shovels, 3 1 5 Front-End Loader C o a l Hauling T r u1c2kT0sr,-aTc t o r - T r a i l e r L a r g e Eozers, E9 S i z e 0 $220,000 Each 0 5 S i z e @ $80,000 Each Dozers, Small 5 . 2 5 4 S c r z p e r s , 40 Cu. Yds., 5 3 Motor C r e d e r s 0 $120,000 3 Coal Drills 0 $85,000 5 Trucks 3 5 2 5 and3 Water 1. - 25,200 2,200 160 1,160 360 lX,OOo and A c c e s s o r i e s 1,600 510 . 375 1,675 130 650 160 900 125 140 2,025 600 2so 550 2,750 1,200 0 900 0 I n i t i a l Hiae Roads and Grading 650 0 1,000 0 I n vI ne ni ttioarl y , -. C o n t i n & e n c i eas n, d . 255 EIettricsl (Office, Buildings 30 800 5,600 300 Miscellaneous 30D i s t r i b u t i o n - 5,050 Crane Pit G 3,2110 6,750 -. Truck 0 750 ' @ SG5,OOO . Lube Trucks @ $60,000 Trucks @ $7,500 30P i c k uapnSG de revniecrea l . 360 , . 2,100 2,400 6 Cu. Yds. @ $150,000 TrucXs Explosives 5 (AVS.) Warehouse) 30 Shop, $125,000 s . 2,100 , 550 HP, 0 $290,000 10 $43,800 ~ @ $280,000 18 10 P10 mps Stripping ( f o r u t i l i t y andcleanup), 5 3 System coal), 15 C u . . Y d s . (for Front-End Loader Fuel ' @ $700,00b Each 13 CU. Yds. @ $1,200,000 5 10 Equipxent 345' Boon @ $14,600,000 Each D r a g l i n e s , 63 Cu. Yds., 3 w. I 3 30 Thousands o'f Dollars Repl;vx:;wnts Jni t i a l L Extensions Wer 30 Years .. Supplies Parts and z,aoo Preproduction . SC t oocakl pR i lei nc g l aL ,Ti om U r aniidninitgn,g Engineering 107. 3,424 $81,659 Total D e p r e c i a b l eC a p i t a l 8,000 = $153,567,000 ( E x c l u d e s I n i t i a l I n v e n t o r y , P a r t s $153 567 no0 hverage D e p r e c i a t i o n = 1 5 0 , 0 0 ~ , o oTons ~ = $1.024 P e r ' R e c o v e r a b l e Ton NOTE: Sec Somary for a d d i t i o n a l c a p i c n l i z c d i t c m s . 6. S u p p l i e s ) . o 0 . Table No. 9 .HYPOVIETICAL STRIPNINE NEIi NEXICO - S T E M COAL . . ESTIMATED COST OF PRODIICTIOS 5,000,030 TOSS PLR YEAR . . . DollarslTon of Coal Fork Category Labor - Bank Preparation Overburden Removal Coal Shootingand Loading and Parting Removal Coal Hauling Supplies Power Tota1 $0.19 $0.42 .$0.61 (a) 0.42 0.55 0.97 (6) (r 0.19 0.26 0.45 0.23 0.36 0.59 Road Maintenance 0.08 0.04 Lend Reclawation Shop-Garage (General Kaintenance) 0.14 0.16 0.20 0.11 0.31 Warehouse and Office Coal Stockpiling, Reclaiming, Processing NIne Supervision and Enginsering. 0.03 0;oz 0.05 0.07. 0.43 0.50 Subtotal Contingency (5% of aboue) Property and Local Taxss and Insurance 0.12 . 0.30 ' - - - $1.78 $2.35 $4.13 $0.09 $0.12 0.23 0.23 0.21 . Land, Legaland Outside Ensizeering Royalty Subtotal - Cash Costs Depreciation Percentage Depletion Xine . . Allowance . . - Total Costof Proeuction (? >line, Including Percentage Depletion NOTES: '0.12 0.03 '. (? (c) (a) Approximately equivalent Lo $0.09 per bank cubic yard overburden. (b) Approximately equivalent t o $0.11 per bank cubic yard overburden. ( c ) Approxinately equivalent to $2,143 per acre of disturbed land. 'This if required vouidbe an addilionnl cost excludes irrigation which, o f $l,SOO t o $2,500 per acre. 1.10 $5.59 .1.02 . - 0.92 $7.53 . : t b 9 . . . Table No, 10 - HYPOTHETICAL STRIP MINE STEAM COAL NEW MEXICO PROPOSED LABOR FORCE Operating Personnel Work Category Bank Preparation Overburden Removal . Service and Maintenance Personnel 22 15 46 ' Total - 37 83 Coal Shooting and Loading 24 37 -~13 Coal Hauling 30 16 46 Road Maintenance 10 18 5' 15 . Land Reclamation Shopand . . Coal Stockpiling, Reclaiming,Processing Mine Supervision and Engineering Total .. 37 . 9 . 27 , . Garage (General Maintenance) Warehouse and Office , 40 12 I 8 6 40 .. 1 2 14 - 40 - - . . 40 210 241 351 I 1 f j. BASIC FLOW SHEET 2,000,000 T P.YR R 0 M ( 9,302 T.P D ) PLANTRATED CAPACITY 750 T.P.H. RAW COAL PREPARATION PLANT R.O.M. CASE A _I TRAMP ROCK BIN ROTARY BREAKER 41 - I I EL 6"x 0 1 750-T OPENSTOCK PILE 1 0 , 0 0 0 T CAPACITY W/TUNNEL 8 CRUSHER c I k T R A M P IRON MAGNET 150TP H 600TPH 1 MAGNETITE PULP 3 - 4 CELLCIRCUIT I IO - H M i 1 MAGNETITE RECOVERY 4 * I FROTHFLOTA CYCLONES I I l "I' -?' MAGNETITE RECOVERY * TlON C E L L S 120TPH FI LTE :RS .a TAILINGS 30TPH & F l J BIN REFUSE DISPOSAL BY TRUCK b C L A R I F I E D WATER V2"x 0 RECIRCULATED TO PLANT 9 HEAT DRYER FILTER CLEANCOAL I 4 600TPH I OPEN, 15,000 TONS C L E A NC O A L ENERGY RESOURCES BOARD Nor€: CLOSED WATER CIRCUIT UNIT STATE OF NEW MEXICO T R A I N LOADING @ 3,500 T P H CONCEPTUAL I I FLOW SHEET NOVEMBER, 1976 DESIGNED BY REZ CHICAGO ILLINOIS R.O. M. I 1- TRAMP ROCK ROTARY BREAKER I 750,000 T P Y R R . 0 M ( 3,488 T.P.D. ) PLANTRATEDCAPACITY 300 T.P.H. R A W C O A L PREPARATION PLANT I I 3 0 0 T P H CAPACITY I 6"x 0 300 T P H OPEN STOCK PILE STORAGE 4,000 T CAPACITY WITUNNEL a FEEDERS PILE CRUSHER I 1/2" x 0 I v2" x 0 I F P L A N TW A l I I PREWETSCREENS 1 I 7 c TRAMPIRONMAGNET 240TPH MAGNETITE PULP I B,C,& D BASIC FLOW SHEETCASE i I . ER 0 5mm x 0 + WATER 60TPH T SUMP 8 PUMP I CIRCUIl 1-4 C E L L I FROTH FLOTATION CELLS t 1 * MAGNETITE RECOVERY MAGNETITE RECOVERY SINK SCREENS TAILINGS I MAGNETITE RE CIRCUIT I. 7 3 1 V THICKENER I7 CENTRIFUGE G DISPOSAL BY TRUCK I CENTRIFUGE "-"---1240TPH C L A R I F I E D WATER RECIRCULATED TO P L A N T FILTER I lc ENERGY RESOURCES Nor€: CLOSED WATER CIRCUIT BOARD S T A T E OF N E W M E X I C O R A I L R O A D C'nR LOADING NOTUNITTRAINCONCEPT CONCEPTUAL FLOW SHEET NOVEMBER, 1976 PAUL w INCORP0MTED DESIGNED BY. R.E Z CHICAGO MPANY lbLlNQlS