QUICK SPEC STRUCTURAL TRANSITE PANEL – ROOF MATE Method

advertisement
 QUICK SPEC
STRUCTURAL TRANSITE PANEL – ROOF MATE
NOTE: The following “Quick Spec” is an abbreviated specification and is not meant to replace the detailed specification. Read
the entire 3-Part CSI System Specification prior to starting the project.
Method

Spray, roller, or brush
Requirements




Moisture survey recommended.
Roof must be clean, dry, and tight.
Adhesion test required to ensure proper adhesion to substrate(s).
Apply at 50°F (10°C) and rising with no rain or freezing temperatures in forecast for 24 hours.
Application
Instructions
1.
Repair or replace damaged or deteriorated sections with like materials, allowing cementitious
products to cure properly.
Power wash roof. It is recommended to use GAF United Cleaning Concentrate (UCC) to clean
the roof. Allow the roof to completely dry.
Treat expansion joints with backer rod and urethane or silicone sealant. Control joints and
transite gaps in excess of 1/16" (1.6mm) shall also be caulked.
Treat all roof penetrations, drains, curbs, and scuppers.
Apply coating per the chart below:
2.
3.
4.
5.
TRANSITE PANEL SPECIFICATION
ROOF MATE
Primer
Product Epoxy Primer 10 Year
Epoxy Primer Epoxy Primer 15 Year
Primer (Gal/Sq)
0.50
0.50
Product (Choose one)
Roof Mate
Roof Mate QS
Roof Mate HT Roof Mate TCM
Epoxy Primer 0.50
Roof Mate
Roof Mate QS
Roof Mate HT Epoxy Primer 0.50
Roof Mate TCM
0.50
1st Coat
Coating
2nd Coat
1.50
3rd Coat
Warranty
Limited Emerald Diamond Warranty Pledge
Pledge
Coating
(Gal/Sq)
DFT*
1.50
3.00
25.5
Yes
Yes
No
1.50
1.50
3.00
25
Yes
Yes
No
1.50
1.50
1.50
4.50
38
Yes
Yes
No
1.50
1.50
1.50
4.50
37.5
Yes
Yes
No
1.50
1.50
1.00
4.00
40
Yes
Yes
No
* Dry Film Thickness (DFT) does not include Primer, uses the average % solids by volume between the two coatings, is rounded to nearest mil, and is theoretical. Actual DFT will vary dependent on substrate profile, application technique & waste factor.