FOREST SERVICE HANDBOOK CHEQUAMEGON-NICOLET NF (REGION 9) RHINELANDER, WI

advertisement
2409.19_10
Page 1 of 4
FOREST SERVICE HANDBOOK
CHEQUAMEGON-NICOLET NF (REGION 9)
RHINELANDER, WI
PARK FALLS, WI
FSH 2409.19 – RENEWABLE RESOURCE USES FOR KNUTSON-VANDENBERG
(K-V) FUND HANDBOOK
CHAPTER 10 – K-V PROJECT PLANNING
Supplement No.: R9 Cheni 2409.19_10-2008-3
Effective Date: September 23, 2008
Duration: This supplement is effective until superseded or removed.
Approved: JEANNE M. HIGGINS
Forest Supervisor
Date Approved: 09/23/2008
Posting Instructions: Supplements are numbered consecutively by Handbook number and
calendar year. Post by document; remove the entire document and replace it with this
supplement. Retain this transmittal as the first page(s) of this document.
New Document
R9 Cheni 2409.19_10-2008-3
4 Pages
Superseded Document(s)
(Supplement Number and
Effective Date)
R9 Cheni 2409.19-2003-4
4 Pages
Digest: In order by code, summarize the main additions, revisions, or removal of direction
incorporated in this supplement.
11.3 – Updates the process to build and maintain a sound K-V program.
R9 CHENI SUPPLEMENT 2409.19_10-2008-3
EFFECTIVE DATE: 09/23/2008
DURATION: Effective until superseded or removed
2409.19_10
Page 2 of 4
FSH 2409.19 – RENEWABLE RESOURCE USES FOR
KNUTSON-VANDENBERG (K-V) FUND HANDBOOK
CHAPTER 10 – K-V PROJECT PLANNING
11 – DEVELOPMENT OF SALE AREA IMPROVEMENT (SAI) PLANS.
11.3 – Integrated Resource Management. The following is an outline of the ChequamegonNicolet process to insure proper interdisciplinary involvement, adequate documentation, proper
target/budget requests, accomplishment reporting and maintenance of an accurate database to
maintain a sound K-V program. Each district shall designate a K-V program coordinator. The
district coordinator will insure the process is being followed and SAI plans are up to date with
district needs.
Program managers at the SO and districts will coordinate appropriate target levels. The district
program managers will funnel their needs to the district K-V program coordinator. The district
coordinator will be the contact for the SO K-V coordinator, reducing overlapping responsibilities
and the number of contacts required.
Chequamegon-Nicolet K-V Process
1) All potential K-V projects should be identified in the NEPA process. Environmental Impact
Statements, Environmental Assessments or Categorical Exclusions, and the appropriate decision
documents shall be used to analyze alternatives, display the effects, and document decisions.
NEPA is required for all projects and insures an interdisciplinary decision process. Projects
should be consistent with the Forest Plan.
2) When developing a timber sale package, identify project area boundaries and the set of
projects appropriate to the sale area. An interdisciplinary team should develop these project area
boundaries and the set of projects to be listed in each SAI plan.
3) Document the K-V project with a narrative. A narrative should include a description of the
project to be completed and an outline of the direct project costs, including the on-site costs and
program management. Narratives are required for all projects.
4) Develop the SAI plan in FACTS using costs developed in the narrative. Check completeness
of plan with appropriate staff (a suggestion is to have appropriate staff initial off on original plan
and plans which add or delete activities). The FACTS developed K-V plan must be entered in
TSA for every revision. Include all feasible activities on the SAI plan even if there is insufficient
dollars available to do all the projects. Projects shall be prioritized by the order they appear on
the plan. Reforestation activities are always first priority.
5) The SAI plan developed at the time of sale advertisement and award shall be considered the
original plan. Any subsequent changes, including sale overbids, shall be considered a revision.
R9 CHENI SUPPLEMENT 2409.19_10-2008-3
EFFECTIVE DATE: 09/23/2008
DURATION: Effective until superseded or removed
2409.19_10
Page 3 of 4
FSH 2409.19 – RENEWABLE RESOURCE USES FOR
KNUTSON-VANDENBERG (K-V) FUND HANDBOOK
CHAPTER 10 – K-V PROJECT PLANNING
6) Request targets and funds from SO program manager as documented in the SAI plan. If
projects, project acres, unit costs, or overhead costs are not consistent with needs, revise your
SAI plan to reflect current needs (revision must include the narrative as well).
7) Get confirmation of targets and funds from the SO program manager at mid-year review.
8) Implementation of projects should be consistent with narratives. Ensure all projects on the
SAI plan for which dollars were collected are completed within 5 years of sale closure
(exceptions are included in a Regional supplement). When objectives change or alternative
methods are used, be sure to revise SAI plans and make necessary accounting adjustments in
TSA before sale is closed.
9) Report all K-V accomplishments for the year. Ensure MAR targets and reported FACTS
accomplishments are consistent. Be sure reported accomplishments are reflected with a
reduction in the K-V inventory.
10) At a minimum, districts shall annually review current SAI plans for proper unit costs,
overhead costs, and the need for project additions or deletions as indicated in FSH 2409.19,
Chapter 10, Section 16 of the WO amendment 6 dated 3/14/2008. A logical time for an annual
update is just prior to the end of the fiscal year. All SAI plans shall be reviewed prior to sale
closure to ensure accuracy of the list of activities, unit costs, and overhead percentage. This data
shall be consistent with TSA records.
The annual Forest K-V inventory/budget needs and Part A reports are due November 1 (or
earlier) and shall reflect the KV inventory as of September 30.
The Forest K-V program coordinator, along with the Forest Biologist, will periodically review
individual district K-V programs. The schedule will be to review one (1) district annually. The
intent of the review will be:
1) Evaluate compliance with Forest policy and direction related to management and
implementation of the K-V program.
2) Determine if K-V needs are properly identified and documented in Sale Area Improvement
(SAI) plans.
3) Evaluate the level of interdisciplinary team participation in the development of
K-V projects. Evaluate the use of K-V financing for resource projects and programs other than
timber.
4) Review the priority of direct and indirect cost calculations.
R9 CHENI SUPPLEMENT 2409.19_10-2008-3
EFFECTIVE DATE: 09/23/2008
DURATION: Effective until superseded or removed
2409.19_10
Page 4 of 4
FSH 2409.19 – RENEWABLE RESOURCE USES FOR
KNUTSON-VANDENBERG (K-V) FUND HANDBOOK
CHAPTER 10 – K-V PROJECT PLANNING
5) Determine if uses of K-V funds are proper and represent legitimate expenditures.
6) Ensure K-V projects listed in SAI plans have proper NEPA documentation and are in
accordance with Forest Plan objectives.
7) Field review to evaluate the on-the-ground accomplishments of the K-V projects for which
funds were collected.
8) The reviews will be documented and recommendations made by the Forest K-V coordinator
on an annual basis.