ID Task Name '07 H2 '07 Q2 1 1 2 WASTE MANAGEMENT SERVICE REGULATION, PLANNING, INTEGRATION & MINIMISATION City of Cape Town Integrated Waste Management Policy Develop Integrated Waste Management Policy 4 Implement IWM Policy 5 Review IWM Policy 6 Citizen’s Charter for Waste Management 7 Draft Citizens Charter for Waste Management 8 Perform Public Participation: obtain comments & suggestions 9 Submit report to Council for adoption 10 Communicate Citizens Charter for Waste Management 11 Solid Waste Management (SWM) Departmental Strategy 12 Develop Overarching SWM Dept Strategy 13 Integrate and align operating strategies with City Policies 14 Implement SWM Dept Strategy 15 Monitor implementation of ops strategies (ongoing) 16 Review success of operating strategies and amend 17 Communicate updated SWM Dept strategies and objectives 18 Functional/ operational strategies 19 Review SWM operational strategies, objectives and amend 20 Implement SWM Operational Strategies 21 Review SWM operational strategies 22 Review success of operating strategies i.t.o. objectives, and amend (2006/07) 23 Review Outcomes of SWM Plans and performance (2006/07) 24 Update SWM Sector Plan (for 2007/08 IDP) 25 Update SWM Master Strategy (2007/08) 26 Update 2007/08 IDP (SWM Section) Integrated Waste Management (IWM) Plan 28 Review IWM Plan against targets and achievements (recurring) 29 Revise IWM Plan (short-term, recurring) 30 Amend 2006/07 key performance targets (recurring) 31 Implement revised IWM Plan (recurring) 32 Monitor implementation of IWM Plan (operational plans and projects) 33 34 Planning Branch Report monthly achievement of targets to Portfolio Committee (recurring) Municipal Systems Act S.78 : Service Delivery (SD) Mechanisms 35 Perform MSA S.78 investigation: Service Delivery Mechanisms 36 Perform financial analysis: Sustainability of internal SD mechanism 37 Investigate current SD Mechanisms i.t.o statutory requirements 38 Investigate Alternate Service Delivery (ASD) mechanisms 39 Report on outcome of S.78 SD investigation 40 Implement Council recommendations re S.78 SD investigation 41 Intergovernmental Relations (IGR) 42 Implement plan to liaise, consult & coordinate with National Departments 43 Implement plan to liaise, consult & coordinate with Provincial Departments (ongoing) 44 Implement plan to liaise, consult & coordinate with Western Cape municipalities (ongoing) 45 Implement plan to liaise, consult & coordinate with other municipalities (ongoing) 46 '07 Q4 IWM 2007_08 Plan S.1 (Regulate, Plan, Integrate) 3 27 '08 H1 '07 Q3 Coordinate SWM Research and Development 47 R&D new/ alternative methods & technologies for Waste Minimisation (ongoing) 48 R&D new/ alternative methods & technologies for Collections (ongoing) 49 R&D new/ alternative methods & technologies for Cleaning (ongoing) Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 1 Deadline '08 Q1 '08 Q2 ID Task Name '07 H2 '07 Q2 50 51 Plan for cross-cutting waste management functions with other Council Dept's Prepare SLA's for internal SWM services provided 53 Implement SLA's: SWM services provided 54 Develop and implement Waste Management & Minimisation requirements (Events) 55 Develop and implement Waste Management & Minimisation requirements (Town Planning) 57 Implement Revenue Dept administrative changes to support waste minimisation Institutional Arrangements for Waste Management 58 Develop generic Memorandum of Understanding (MOU) for partnerships 59 Implement operational & service links with CoCT’s regulatory and support Services Authorities 60 Develop and Implement a Partnership/Sponsorship Plan 61 Implement Memoranda of Understanding with Industry, CID's etc 62 SWM Disaster Risk Management Plan 63 Derive new Disaster Risk Management Plan for Soild Waste Management 64 Implement: Appoint, train SWM staff re emergencies and disasters 65 Review/ amend SWM Disaster Risk Management Plan 2 1 2 3 4 5 IWM 2007_08 Plan S.2 (Waste Minimisation) WASTE MINIMISATION Develop and implement Waste Minimisation Plan Develop a Plan for Waste Minimisation Set short-to-medium term targets for Waste Minimisation Develop and Review a waste generation/disposal model 6 Finalise modeling assumptions 7 Determine Total waste generated and disposed of in City 8 Determine waste types per area 9 Establish and Review targets for the reduction of waste to landfill 10 Determine bulk infrastucture requirements (20-year plan) 11 Develop a Plan for the recovery of recyclables 12 13 Implement Waste Minimisation Plan Develop and implement Waste Minimisation Infrastructure, Methodologies and Initiatives 14 Develop and Implement a strategy for community-driven Waste Minimisation Initiatives 15 Develop and Implement a Waste Minimisation Partnership Plan 16 Develop a “community volunteer" database 17 Develop partnerships to assist schools with Waste Minimisation education and implementation 18 Develop recycling and other Industry Partnerships 3 1 2 IWM 2007_08 Plan S.3a (Waste Collection) WASTE COLLECTION Revise and implement Municipal Waste Collection Strategy and Management Plans 3 Optimise collection beats due to growth 4 Implement service delivery plan for backyard dwellings in formal areas 5 Develop and implement plan for waste collection: formalised informal traders on Council-owned property 6 Develop & implement plan for waste collection and regulation of Commerce & Industry 7 Audit CBD's and Industrial areas for commercial and industrial collections contracts 8 Administer contractual compliance (all commercial and industrial entities must have a contract) 9 Sign up commercial businesses (City service option) 10 Link new contracts on SAP 11 12 4 5 '07 Q4 R&D new/ alternative methods & technologies for Disposal (ongoing) 52 56 '08 H1 '07 Q3 Regulate Industrial and Hazardous Waste Collection Facilitate auditing and collation of pesticides (agricultural, pharmaceutical and chemical sectors) IWM 2007_08 Plan S.3b (Waste Cleaning/Cleansing) IWM 2007_08 Plan S.3c (Waste Disposal) Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 2 Deadline '08 Q1 '08 Q2 ID Task Name '07 H2 '07 Q2 1 2 3 '08 H1 '07 Q3 '07 Q4 WASTE DISPOSAL AND PROCESSING Revise and implement Disposal Strategy and Management Plans Develop, Implement and Review a suitable Public-Private partnership model for alternative processing and disposal services delivery. 4 Review and Implement alternative waste processing and disposal technologies 6 Develop and Implement a Plan for cost-effective landfill closures 7 Develop and Implement a Plan for on-going maintenance of rehabilitated landfills. 8 9 10 Develop and Implement a Plan for on-going monitoring and testing of landfill gas and leachate production at landfills. Plan, Design and Establish Bulk and Regional Waste Disposal Facilities REGIONAL WASTE DISPOSAL FACILITY 11 Complete EIA, public participation process and obtain ROD 12 Permit the preferred site 13 Land Acquisition and Rezoning 14 Design and construction of the disposal facility 15 On-going site development and rehabilitation 16 VISSERSHOK LANDFILL (City-owned) - GLB+/H:h 17 Ongoing site development (South) 18 EIA, Public participation and obtain ROD ( North) 19 Permit Vissershok North 20 Rezone and relocate informal settlements 21 Design and construction 22 On-going development and rehabilitation 23 24 25 26 VISSERSHOK WMF (Privately owned) - GLB+ /H:h/ H:H Continue to receive general/hazardous/special wastes COASTAL PARK LANDFILL – GLB+ On-going development and rehabilitation 27 BELLVILLE SOUTH LANDFILL (GLB+) 28 Extension of permit to operate site 29 On-going development and rehabilitation 30 Development of landfill gas (LFG) management system 31 32 33 34 35 36 37 38 39 40 41 42 43 FAURE LANDFILL (GMB+) Formal closure for general waste disposal BRACKENFELL LANDFILL – GMB+ Formal closure for general waste disposal SWARTKLIP LANDFILL Formal closure for general waste disposal CLOSED WASTE DISPOSAL SITES Develop and Implement rehabilitation plans for all identified sites Plan, Design and Establish Transfer Station and Materials Recovery Facilities ATHLONE (ARTS) – 800t/day-1760t/day Amend permit to increase capacity Design and construct 960t/day extension SWARTKLIP (SRTS) – 800t/day-1280t/day 44 Design and construct 480t/day extension 45 OOSTENBERG (ORTS) - 480t/day - 960t/day 46 47 48 Permit site Design and construct transfer station (inl MRF) TYGERBERG (TRTS) –2880t/day 49 ROD and permit 50 Design and construct transfer station with MRF Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 3 Deadline '08 Q1 '08 Q2 ID Task Name '07 H2 '07 Q2 51 EIA process and economic assessment 53 ROD and permit 54 Design and construct transfer station with MRF 56 57 58 Permitting, design and construction of additional transfer stations. Develop a Plan for the provision of Waste Minimisation Infrastructure 60 Develop drop-off sites for informal areas 61 Review Policy and previous study to optimise design and locations of existing and new drop off facilities. 62 Design & construct drop off facilities. 65 66 67 68 69 Organic Waste Treatment Facilities Develop a plan in conjunction with the Policy, to optimise the removal and processing of organic wastes in the waste stream and review on a regular basis. Review operations at the Radnor and Sacks Circle composting facilities Builders’ Spoil and Rubble Facilities Develop & implement a plan for the management of builders’ rubble and spoil. HAZARDOUS AND SPECIAL WASTE MANAGEMENT Generate Develop, Implement and Review a Hazardous Waste Management Strategy and Plan in accordance with National and Provincial Imperatives 70 1) Identify and provide resources and infrastructure for hazardous waste management. 71 2) Identify and include “Special” wastes 72 3) Register new and existing hazardous waste producers. 73 Develop, Implement and Review Performance Indicators for Hazardous Waste Management 74 1) Performance Indicators are to be determined in conjunction with DWAF and DEADP 75 2) Monitor contamination levels at receptors such as landfill sites, groundwater quality, air quality. Monitor biogas generation, carbon loading to atmosphere. 76 77 3) Review of the Performance Indicators by an independent entity to ensure sustainable management of hazardous waste in the City Develop, implement and administer cross-border waste permitting 78 Consult with DEA&DP 79 Amend Permit and Admin System 80 Communicate New Permit System 81 6 1 2 Implement new Permit System IWM 2007_08 Plan S.4 (Resourcing, Funding, Performance Management) RESOURCE PROVISION, FUNDING AND PERFORMANCE MANAGEMENT SWM Dept's Human Resource Development 3 Implement new organisational structure (Project Ikhambi) 4 Departmental Needs Analysis 5 Implement TASK job evaluation system 6 Develop & implement EE Plan for Solid Waste Management 7 SWM Training Programmes Implement Work Skills Plan (ongoing) 9 Procure and introduce Leadership, Development Programmes (Mentorship) 11 Develop, implement & review Change Management Programme (ongoing) Finalise and introduce shifts at key SWM facilities 13 Standardise SWM Transport Arrangements 14 Standardise SWM Allowances 16 17 18 George & Team Special Topics (Projects) in HR 12 15 George & Team George & Team 8 10 '08 Q2 Determine and Review prioritisation, economic assessment and programming of implementation of additional transfer stations. Upgrade Formal Drop-off Sites to accept recyclables and household hazardous waste 64 '08 Q1 PROPOSED AND ADDITIONAL TRANSFER STATIONS 59 63 '07 Q4 HELDERBERG (HRTS) – 400t/day 52 55 '08 H1 '07 Q3 George Roll-out Labour Relations implementation SWM Financial Requirements Develop and revise SWM Financial Funding and Cost Recovery Framework Determine financial constraints and assess risks & impacts Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 4 Deadline ID Task Name '07 H2 '07 Q2 19 20 21 22 Assess risks & impacts (Dept vs Corporate) Generate SWM Budget (3-year MTIEF) Determine Expenditure Budget Determine Capex Budget for SWM 24 Determine Capex project requirements (recurring) 26 Determine SWM Opex Budget direct and indirect costs 27 Determine Opex direct costs (recurring) 28 Determine Staff Budget (recurring) 29 Determine Opex indirect costs (recurring) Determine Income Budget 31 Determine a revenue base with respect to rates, tariffs, levies and grants 32 Audit customer database, billing systems & revenue management systems 33 Identify extent to which current revenue base supports service delivery objectives 34 Undertake rigorous billing & debt collection audit 35 Perform annual Tariff Modelling (recurring) 36 Generate short & medium term budgets (MTIEF) (recurring) Develop and Implement a “full cost accounting” model for Waste Management 38 Determine environmental opportunity costs 39 Determine human health impact costs 40 Determine social costs 41 42 Determine economic opportunity costs Investigate & recommend local authority impacts & implications for National Treasury Draft Policy (Env Fiscal Reform) 43 Workshop item with Water Services and Electricity Services 44 Submit Report to Ikhwezi 45 Submit Report to Executive Mayor 46 Submit final report to National Treasury 47 Review SWM Revenue, Costs and Financing 48 Develop and Implement a Financing Plan for Solid Waste 49 Develop long term cost and revenue forecast, including operational and capital cost 50 Develop and Implement cost optimisation strategies 51 Negotiate structural cost drivers 52 53 54 Technical Support Services Determine fixed asset, vehicle and plant capex requirements (recurring) 25 37 Identify alternative revenue strategies Develop and implement integrated Performance Management system Develop & implement internal performance measurement system 55 Develop & Implement performance measures for service delivery agents (Collections, Cleaning, Disposal, Waste Minimisation) 56 Implement regular benchmarking (financial management, cost recovery, asset deployment, service delivery and social and environmental impacts 57 Realign Organisational and Personal Performance Management System 58 Establish uniform Performance Monitoring System 59 Align operating strategies to legislative requirements (all environmental legislation safety & health standards & performance measures) 60 Communication considerations w.r.t. external and internal stakeholders 61 06/29 Undertake a Stakeholder Analysis and develop relevant strategies 62 Perform consumer survey 63 Investigate engagement model for labour & industrial relations 64 Undertake registration & accreditation of private waste service providers 65 66 67 68 '07 Q4 Develop a Solid Waste Management Dept Financial Management Plan 23 30 '08 H1 '07 Q3 Monitor Collections Performance Monitor complaints (ongoing) Monitor Cleaning Performance Monitor complaints (ongoing) Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 5 Deadline '08 Q1 '08 Q2 ID Task Name '07 H2 '07 Q2 69 70 71 72 Monitor complaints (ongoing) Capture waste data (Private landfill operators & recyclers) 3 IWM 2007_08 Plan S.5 (Provide & Manage Assets) MANAGEMENT AND PROVISION OF ASSETS: Solid Waste Management Dept Develop and implement a SWM Asset Management policy Develop asset repair, replacement and scrapping policies for different asset categories 4 Develop SWM Asset Management Policy 5 Finalise SWM Asset Management Policy 6 Approve SWM Asset Management Policy 7 Amend & incorporate Corporate Asset Management Policy guidelines with SWM policy 8 Implement Asset Management Policy 9 Analyse historic asset performance and strategies (owned vs. leased) 10 Dispose of Equipment and Fleet 11 Develop equipment and fleet disposal strategy 12 Implement equipment and fleet disposal strategy 13 Determine annual allocation of vehicles and plant (ongoing) 14 15 Technical Support Services Technical Support Services Update & review asset register for all SWD assets Verify Inventory items for Asset Management Register 16 Categorise assets (different asset categories) 17 Develop and implement SWM Asset Management Strategy 18 '08 Q2 Monitor Waste Minimisation Performance Compare data on diverted waste with modeling & actual data 2 '08 Q1 Audit Disposal Sites against Minimum Guidelines (annual) 74 1 '07 Q4 Monitor Disposal Performance 73 7 '08 H1 '07 Q3 Develop acquisition strategies for different asset categories 19 Document SWM "unofficial" strategies for different asset types 20 Clarify roles and responsibilities (large value-assets vs. "inventory", Technical Services vs. Finance) 21 Finalise SWM Asset Acquisition Strategy Technical Support Services 22 Approve SWM Asset Acquisition Strategy Dir SWM 23 Implement acquisition strategies for different asset categories 24 25 8 1 2 Maintain and manage SWM Fleet and Plant Monitor and report on performance of Assets (ongoing) IWM 2007_08 Plan S.6 (Waste Info, Communication, Education & Awareness) WASTE INFORMATION, COMMUNICATION AND EDUCATION Waste Wise Programme: Waste Minimisation Education and Communication Initiatives 3 Education, Awareness, Training and Communication Tools 4 Develop Waste Education, Awareness and Training Plan 5 Implement & Review Waste Education, Awareness and Training Plan 6 Communication, Marketing and Training 7 Develop plan for waste communication 8 Implement & review communications, marketing and training plans 9 e Schools’ Waste Awareness and Education Plan 10 Develop schools projects/ research strategies on environmental management & waste minimisation 11 Develop, Implement and Review a Schools' Waste Awareness and Education Plan 12 Develop Schools' Waste Awareness and Education Plan 13 Develop & review training materials 14 Get accreditation for existing schools training program 15 16 17 Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Implement Schools' Waste Awareness and Education Plan Engage with LGWSETA regarding training and internships Facilitate teachers' training workshop (as per FCA) to form part of Curriculum Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 6 Deadline ID Task Name '07 H2 '07 Q2 18 Evaluate & measure training programmes against benchmarks e.g. questionnaires to teachers 20 Implement reward programmes for schools Waste Education and Awareness Plan for non-residential sectors 22 Develop Plan for Waste Education and Awareness with respect to Institutions & Tertiary Educational Institutions 23 Develop Eco-labeling campaign with DTI, DEADP, etc for awareness raising 24 Implement Plan for Institutions and Tertiary Educational Institutions 25 Roll out of Cleaner Production best practices to different stakeholder groups 26 Promote waste recovery at source, location of sorting facilities/infrastructure for new industrial/commercial developments 27 Review Plan for Institutions & Tertiary Educational Institutions (include hospitals, universities, etc) 28 Waste Education and Awareness Plan for residential sectors 29 Develop Plan for Waste Education and Awareness for residents 30 Implement Plan for Waste Education & Awareness for residents 31 Roll out of WM best practices to different stakeholder groups 32 Promote waste recovery at source, location of sorting facilities/drop-off sites 33 34 Review Plan for Waste Education & Awareness for residents Plan for Special Projects relating to Waste Education, Awareness and Training 35 Develop special projects plan 36 Develop Plan for Awareness Raising for public events 37 Design education and awareness training for associations (NGO’s) & other bodies e.g. Navy, City Police. 38 Implement special projects plan 39 Implement Plan for Awareness Raising at public events 40 Implement education and awareness training for associations (NGO’s) & other bodies e.g. Navy, City Police 41 Actively promote “Clean City” Awards, special events, etc. 42 Review special projects plan 43 44 '07 Q4 Review a Schools' Waste Awareness and Education Plan 19 21 '08 H1 '07 Q3 Review a Plan for Awareness Raising for public events Waste Management Guidelines 45 Develop Solid Waste Management Dept Fact Sheet 46 Develop "Waste Management at Events" guideline 47 Develop Guideline for Residents 48 Develop Guideline for Commerce and Industry 49 Communicate Guidelines 50 WASTE INFORMATION MANAGEMENT 51 Establish and maintain a Waste Resource Centre 52 Establish and maintain Waste Resource Centre 53 Develop Environmental Education database – key NGO’s in areas, key stakeholders, service providers, etc. 54 55 Complete a Directory of Cape Town Recycling stakeholders Waste Information Management System (WIS) 56 Perform Waste Characterisation Study 57 Develop a waste classification system 58 Develop and Implement a Waste Information Management System 59 Mapping of As-is business processes 60 Evaluation and recommendation of As-is business processes 61 Purchase and implement SAP module and other software for WIS 62 Establish weighbridges with suitable software for capturing & analyzing of load data at all large waste receiving facilities 63 Implement standard visual recording system at smaller facilities such as drop-offs 64 Develop and maintain a SWM Website 65 Develop new SWM Website 66 Upgrade and regular maintenance of the Waste Exchange website service 67 Upgrade and link WasteWise website to SWM website Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 7 Deadline '08 Q1 '08 Q2 ID Task Name '07 H2 '07 Q2 9 1 '08 Q1 '08 Q2 SIGNAGE AND BY-LAW ENFORCEMENT Investigate and introduce Regulatory and Co-Regulatory Instruments 3 Contribute to and Implement mandatory national framework outcomes 4 Develop Extended Producer Responsibility instruments 5 Introduce Extended Producer Responsibility Measures to local industry and commerce 6 Develop and Implement regulatory instruments for Waste Minimisation 8 '07 Q4 IWM 2007_08 Plan S.7 (Signage, Bylaws) 2 7 '08 H1 '07 Q3 Develop City of Cape Town “Green/Environmental Procurement Policy” Develop City of Cape Town Integrated Waste Management By-law 9 Draft IWM By-law 10 Perform public participation process for draft IWM By-law 11 Liaise with public bodies regarding new by-law 12 Adopt new IWM By-law 13 Promulgate IWM By-law 14 Communicate new IWM By-law to Internal Departments 15 Train Law Enforcement Staff re By-law 16 Introduce Waste Management signage (information and control) Project: Cape Town IWM Plan 2007_0 Date: Fri 07/05/04 Council Task Progress Summary External Tasks Split Milestone Project Summary External Milestone Page 8 Deadline