CURRENT SMOV3B STATUS • SMOV ACCOMPLISHMENTS TO DATE – Spacecraft Subsystems – STIS

advertisement
Carl Biagetti
TIPS 15Aug02
CURRENT SMOV3B STATUS
• SMOV ACCOMPLISHMENTS TO DATE
– Spacecraft Subsystems
• Recommissioned in March
– STIS
• SMOV completed in early May
– WFPC2
• SMOV completed in early April
– ACS
• SMOV completed - last activity 21 July
– Coronagraphic ERO visit
Carl Biagetti
TIPS 15Aug02
CURRENT SMOV3B STATUS
• SMOV REMAINING
– NICMOS
• Coronagraph optimization (8984)
– SMS231 Visits 14-2Z (last SMOV visits)
– October – Visits 1-3 (booked as Cycle 11 calibration)
– EPS
• Battery 1 capacity test
– SMS231
Carl Biagetti
TIPS 15Aug02
SMOV3B PROGRESS
TOTAL
SCHEDULED
ACTUAL
PERCENT
PLANNED
COMPLETIONS
COMPLETIONS
COMPLETE
as of 14 AUG
as of 14 AUG
ACTIVITIES
by 14 AUG
EXTERNAL
ORBITS
(to tal SM OV)
SPACECRAFT
20
20
20
100.0
22
ACS
30
30
30
100.0
171
ERO
3
3
3
100.0
87
NCS
2
2
2
100.0
0
NICMOS
21
21
20
95.2
75
STIS
10
10
10
100.0
14
7
7
7
100.0
31
WFPC
FGS
TOTAL
5
========
98
5
========
98
5
========
97
100.0
========
99.0
19
========
419
Carl Biagetti
TIPS 15Aug02
SMOV3B RESOURCES
• Observatory Resources
– Total external orbits = 419
• Not including 2-week BEA pointing
• SMOV Team
– STScI/GSFC/IDT/Ball
– Job well done, many long hours, not a “routine” SMOV
– 51 “morning meetings” Mar12 to Jul24 (165 days)
• average of one meeting every 63.5 hours (daily 1st 2 weeks)
Carl Biagetti
TIPS 15Aug02
POSSIBLE OPERATIONAL
CHANGES (Spacecraft)
• Electrical Power System (EPS)
– Sun Incidence Angle constraint may be relaxed
• Since SA3 provides more power
– May involve sw upgrade but no science impacts
• Thermal Control System (TCS)
– Off-nominal roll constraint may be made more
restrictive
• Needed because Bay 5 is warmer post-3B due to
higher data volumes (SSR & xmitter usage)
• No significant impact to Cycle 11 yet identified
Carl Biagetti
TIPS 15Aug02
SMOV LESSONS LEARNED
• Lessons Learned document in work
–
–
–
–
Lessons
Lessons
Lessons
Lessons
1- 6
7 – 10
11 – 15
16 – 17
SI Operations
Flight Ops
Data Processing
SMOV Planning and
Ground Testing
• To be finalized by 30 Aug.
– Will be included in SMOV Closure Review
Carl Biagetti
TIPS 15Aug02
PLANS
• SMOV Closure Review
– 30 Sep. 02, 1-4 pm, STScI Auditorium
– Assessment of original SMOV3b requirements
– Final documentation of lessons learned
• SMOV4 Requirements
– Sep. 02 - Analysis phase begins
– Assuming early-mid 2004 launch