SMOV4 REQUIREMENTS KICK-OFF MEETING 8 MAY 2003 Carl Biagetti/STScI AGENDA SMOV4 PLANNING PROCESS DEVELOPMENT SCHEDULE SMOV4 CONCEPT PLANNING GUIDELINES SMOV4 PLANNING PROCESS FLOW SMOV CONCEPT STATEMENT STSCI, SMOV Mgmt Team STScISMOV Team, 441 SMOV Planning Team REQUIREMENTS DEFINITION BASELINE PLAN STScISMOV Team, 441 SMOV Planning Team PROPOSAL SUBMISSION STScISMOV Team, 441 SMOV Planning Team PROPOSAL IMPLEMENTATION OPERATIONS PLANNING SMOV OPERATIONS STScI Proposal Implementation Team SMOV Ops Working Group, 441 SMOV Planning Team SMOV Ops Team, SMOV TTRB (& SMOV CLOSURE) Carl Biagetti/STScI 2 SMOV4 PLANNING TEAMS & INTERFACES NASA H/Q SMOV Policies, Oversight, ERO HST PROJECT STScI SMOV Policies, Oversight, ERO PROJECT CONTAMINATION WORKING GROUP (CWG) SMOV Policies, Oversight, ERO SMOV TTRB DO, HST,INSTRUMENTS, ESS, ODM, OPO,441 SMOV MGMT TEAM 441 Pepe STScI - Biagetti 442 - tbd STScI SMOV PLANNING TEAM SERVICING MISSION OPS WG (SMOWG) 441,442, STScI, ACS, COS, STIS, NICMOS GSFC SMOV PLANNING TEAM 441 - Pepe (lead) 442 - tbd STScI SMOV TEAM CHAMP/MOSES IPT, IDT, BASD Lead – Biagetti ACS – DeMarchi, Cox COS – Keyes FGS – Nelan NICMOS/NCS - Noll STIS – T. Brown WFC3 – Stiavelli , Lupie, MacKenty Eng. Spt. – Wheeler, Miebach, Roberts ERO – tbd, OPO Planning & Scheduling - Reinhart, Chapman, Roman,et al. OPD – Ellis, et al. COOLING SYSTEMS WORKING GROUP 441, 442, STScI, ACS, COS, STIS, NICMOS STScI SM4 OPS W/G HST,INSTRUMENTS, ESS, ODM, OPO,441, 442, COS, WFC3 SMOV PIs PROPOSAL IMPLEMENTATION TEAM HST,P&S,INSTRUMENTS, ESS, ODM, OPO,441, 442, COS, WFC3 SMOV PIs SMOV OPS TEAM DO, HST,P&S,INSTRUMENTS, ESS, ODM, OPO,441, 442, COS, WFC3 Carl Biagetti/STScI 3 SMOV4 PLANNING CURRENT APPROACH • Proceed with planning driven by Nov04 launch – Requirements over the summer • Less subject to rework in case of launch delay • Project Requirements Review = 31July03 • ACS/NICMOS/STIS complete activity summaries by Sep03 • Await confirmation or change of launch date – Proceed with or rephase SMOV planning accordingly Carl Biagetti/STScI 4 SMOV4 PLANNING DEVELOPMENT SCHEDULE FOR NOV04 LAUNCH (30APR03) Task Name SMOV PLANNING - ACS/NICMOS/STIS/FGS REQUIREMENTS IDENTIFICATION ACTIVITY SUMMARIES PROPOSAL IMPLEMENTATION REQUIREMENTS DEVELOPMENT - WFC3/COS/VEH REQUIREMENTS DEVELOPMENT REQUIRMENTS REVIEW COMPREHENSIVE PLAN DEVELOPMENT Start Tue 12/10/02 Qtr 4, 2002 Qtr 1, 2003 Qtr 2, 2003 Qtr 3, 2003 Qtr 4, 2003 Qtr 1, 2004 Qtr 2, 2004 Qtr 3, 2004 Qtr 4, 2004 Qtr 1, 2005 Qtr 2, 2005 Qtr 3, 2005 Finish Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Sat 1/3/04 Tue 12/10/02 Thu 2/20/03 Fri 2/21/03 Sat 9/20/03 Sun 9/28/03 Sat 1/3/04 Mon 4/7/03 Thu 8/7/03 Mon 4/7/03 Thu 8/7/03 Thu 7/31/03 Thu 7/31/03 Fri 8/1/03 INITIAL ACTIVITY SUMMARIES Fri 8/1/03 Fri 11/28/03 INITIAL SMOV PLAN Sat 8/9/03 Sun 12/7/03 BASELINED SMOV PLAN SPECIAL CMDING DEVELOPMENT & TEST Tue 1/20/04 Thu 4/8/04 Wed 1/1/03 Fri 8/6/04 FGS SMGT Thu 4/15/04 Thu 4/15/04 COS SPEC CMDING Wed 1/1/03 Tue 3/2/04 COS SMGT Wed 3/3/04 Thu 3/4/04 WFC3 SPEC CMDING Mon 9/22/03 Thu 7/1/04 Thu 8/5/04 Fri 8/6/04 WFC3 SMGT 7/31 Thu 4/8/04 SMOV4 PROJECT REVIEW Mon 1/19/04 Mon 1/19/04 SMOV OPS PLANNING & SCHEDULING Tue 1/20/04 Sun 10/3/04 PROPOSAL IMPLEMENTATION Tue 1/20/04 Thu 9/30/04 STSCI OPERATIONS PLANNING Wed 5/26/04 Sun 10/3/04 STSCI READINESS REVIEW for SM4/SMOV4 Mon 10/4/04 Mon 10/4/04 SM4 Thu 11/18/04Sun 11/28/04 SMOV4 OPERATIONS Fri 11/26/04 Mon 5/30/05 SMOV4 CLOSURE REVIEW Thu 6/30/05 Thu 6/30/05 4/15 3/3 8/5 1/19 10/4 6/30 Carl Biagetti/STScI 5 SMOV4 CONCEPT SM4 PLANS • • • • • • • • • • Current launch date = 18 Nov. 2004 Launch Readiness = 1 Nov. 2004 WFPC2 is replaced by WFC3 COSTAR is replaced by COS FGS3 is replaced by FGS3R ASCS installed, attached to ACS, STIS, COS All six gyros are replaced All six batteries are replaced DSC is installed NOBL installed on Bays 5, 7, 8 Carl Biagetti/STScI 6 SMOV4 CONCEPT ASSUMPTIONS AND INITIAL CONDITIONS AT RELEASE • SPACECRAFT SUBSYSTEMS – PCS • 4-gyro complement at least through gyro calibration activity • CVZ pointing (North or South TBD) for Bright Earth Avoidance (BEA) – EPS • New batteries on line – TCS • ASCS in Safe • Noble installed in Bays 5,6,7 – OTA – Normal operating mode • Heaters Off • One new (uncalibrated) FGS – FGEs Off – DMS • DMU Side A • HST486 in VSS mode • SSR configured for normal science ops – I&C • Normal TDRS configuration • Unrestricted SSAT use Carl Biagetti/STScI 7 SMOV4 CONCEPT ASSUMPTIONS AND INITIAL CONDITIONS AT RELEASE • Science Instruments – – – – COS in Safe WFC3 in Safe ACS in Safe NICMOS in Safe • NCC off • ESM in Operate – STIS in Safe – ASCS in Safe • CPLs in Safe – FGSs in Operate Carl Biagetti/STScI 8 SMOV4 ASSUMPTIONS – CONT’D • All new, uncalibrated gyros – May require some slewing restrictions – Similar to SMOV3A • All new batteries – Passive SMOV commissioning • ACS/STIS “post-baseline” Noise Tests Carl Biagetti/STScI 9 SMOV4 CONCEPT PLANNING DRIVERS/RESTRICTIONS • Bright Earth Avoidance (BEA) – 12 days starting from Release – ACS/STIS MAMA for End-BEA Check? • NCS/NICMOS Cooldown – No high-voltage restrictions per HSTP – No ACS/STIS/FGS pre-requisites Carl Biagetti/STScI 10 SMOV4 Planning Guidelines The Generic SMOV Program • A SMOV program is associated with each servicing mission • Generic SMOV goals – Timely recommissioning of the Observatory for science operations • Commission newly installed science instruments • Recommission existing science instruments – Recommission Observatory systems for normal operations – Validation of other on-orbit replacements & installations – Early Release Observations • Demonstrate upgraded science capabilities to astronomical community and general public Carl Biagetti/STScI 11 SMOV4 Planning Guidelines Existing SIs • ACS draft requirements: http://www.stsci.edu/smov/smov4.html • NICMOS draft requirements in work • STIS draft requirements: http://www.stsci.edu/smov/smov4.html • FGS draft requirements in work Carl Biagetti/STScI 12 SMOV4 Planning Guidelines REQUIREMENTS PROCESS • Determine SMOV tests/measurements needed to recommission Observatory & SIs (channel-by-channel) – Goal to validate or augment ground-based calibration data bases – Ready Observatory for EROs and normal GO/GTO science operations • Circulate for SMOV team internal review • Present to management review/blessing Carl Biagetti/STScI 13 SMOV4 Planning Guidelines REQUIREMENTS • Determine engineering parameters that need adjustment or measurement for commissioning • Requirements statements should specify quantitative results only where necessary for commissioning – Define goals where appropriate • Avoid explicit citing of CEI specs • Determine special commanding needs ASAP • Avoid implementation plans at requirements level – Unless unavoidable Carl Biagetti/STScI 14 SMOV4 Planning Upcoming Stuff • Next SMOV4 Planning Meetings – June tbd – July 17 • SMOV4 Requirements Review – 31 July 2003 – HSTP/STScI Management Review of our requirements analysis and determination Carl Biagetti/STScI 15