SMOV4 KICK-OFF MEETING 26 Oct 2006 Carl Biagetti/STScI AGENDA SMOV4 PLANNING PROCESS DEVELOPMENT SCHEDULE SMOV4 CONCEPT PLANNING GUIDELINES Some SMOV Info • Definitions – SM = Shuttle Servicing Mission to HST • SM4 = SM #4 (actually the 5th one) – SMOV = Servicing Mission Observatory Verification • STScI/GSFC Plan for commissioning HST after a SM • SMOV4 = SMOV associated SM4 • Charge Number for all SMOV planning work – P0003.06.02.01 (Ops Commissioning Plan) – WFC3 team has a separate number Carl Biagetti/STScI 2 SMOV4 PLANNING PROCESS FLOW SMOV CONCEPT STATEMENT STSCI, SMOV Mgmt Team STScI SMOV Team, 441 SMOV Planning Team REQUIREMENTS DEFINITION BASELINE PLAN STScI SMOV Team, 441 SMOV Planning Team PROPOSAL SUBMISSION STScI SMOV Team, 441 SMOV Planning Team PROPOSAL IMPLEMENTATION OPERATIONS PLANNING SMOV OPERATIONS STScI Proposal Implementation Team SMOV Ops Working Group, 441 SMOV Planning Team SMOV Ops Team, SMOV TTRB (& SMOV CLOSURE) Carl Biagetti/STScI 3 SMOV4 PLANNING TEAMS & INTERFACES NASA H/Q HST PROJECT SMOV Policies, Oversight, ERO STScI SMOV Policies, Oversight, ERO SMOV Policies, Oversight, ERO SMOV TTRB PROJECT PROJECT CONTAMINATION CONTAMINATION WORKING GROUP WORKING GROUP (CWG) (CWG) COOLING SYSTEMS WORKING GROUP PROJECT (defunct?) CONTAMINATION 441, 442, STScI, ACS, WORKING GROUP COS, STIS, NICMOS (CWG) Information/reporting flow up. SERVICING MISSION OPS WG (SMOWG) 441,442, STScI, ACS, COS, STIS, NICMOS SMOV MGMT TEAM 441 Walyus/Mazzuca STScI - Biagetti STScI SM4 OPS W/G GSFC SMOV PLANNING TEAM 441 – Walyus/Mazzuca STScI SMOV TEAM CHAMP/MOSES IPT, IDT, BASD HST, SI Teams, ESS, ODM, OPO,441, 442, SMOV PIs STScI SMOV PLANNING TEAM Lead – Biagetti ACS –Sahu COS – Aloisi OTA/FGS – Lallo NICMOS/NCS – Wiklind/Wheeler STIS – Proffitt WFC3 – MacKenty Eng. Spt. – Wheeler ERO – tbd, OPO Planning & Scheduling - Reinhart, Chapman, Roman,et al. OPD – Ellis, et al. Archive – TBD IT - TBD PROPOSAL IMPLEMENTATION TEAM Management/direction flow down DO, HST, INS, ESS, ODM, OPO, 441 HST,P&S,SI Teams, ESS, ODM, OPO,441, SMOV PIs SMOV OPS TEAM DO, HST,P&S,SI Teams, ESS, ODM, OPO,441, 442, COS, WFC3 Carl Biagetti/STScI 4 SMOV4 Planning Schedule (Tentative) for May 2008 Launch Start* ===== Oct06 End* ===== Dec06 Dec06 Dec06 Activity ========== ============================ Concept/Requirements Update SMOV Requirements Review TBD ~ June ~June07 SMOV Planning SMOV Project Review ~June07 Apr08 Implementation Phase - Proposal generation/iteration - Special Commanding Development (ASAP) - ERO program Jan08 Apr08 Test Calendar/SMS generation Mar08 Readiness Review for STScI support to SM4/SMOV May08 SM4 May08 ~Aug08 ~Aug08 SMOV4 SMOV4 Closure Review * Exact dates are TBD Carl Biagetti/STScI 5 SM4 Ground Tests and Simulations Support Ground Tests (Dates not yet revised to reflect May08 launch.) Start ======= End ========== Oct06 Apr07 Servicing Mission Ground Tests (SMGTs) - WFC3, COS Nov06 Aug07 Simulations (Sims) Aug07 Aug07 Flight Operations Readiness Review (FOR) Dec07 Joint Integrated Simulations (JISs) Aug07 Integrated Hardware Testing Sep07 End-to-End Tests Carl Biagetti/STScI 6 SM4 Plans • • • • • • • • • • Current launch date = May 2008 Launch Readiness (FRR) = TBD Apr 2007 WFC3 is installed (in place of WFPC2) COS is installed (in place of COSTAR FGS3R replaces FGS3 STIS is repaired All six gyros are replaced All six batteries are replaced NOBL is installed on Bays 5, 7, 8 Soft Capture Mechanism (SCM) is installed – In parallel with EVAs • Note: ASCS, to be attached to STIS & COS, is no longer manifested. Carl Biagetti/STScI 7 SM4 EVA Timeline as of 10 Oct. 2006 Carl Biagetti/STScI 8 SMOV4 CONCEPT ASSUMPTIONS AND INITIAL CONDITIONS AT RELEASE (To be verified with Project) • SPACECRAFT SUBSYSTEMS – PCS • 6 new gyros (uncalibrated) • • 4-gyro complement at least through gyro calibration activity CVZ pointing (North or South TBD) for Bright Earth Avoidance (BEA) – – EPS • – New batteries on line TCS • – Noble installed in Bays 5,7,8 OTA • Normal operating mode – – – Heaters Off One new (uncalibrated) FGS DMS • • • – May entail some slewing restrictions DMU Side A HST486 in VSS mode SSR configured for normal science ops I&C • • Normal TDRS configuration Unrestricted SSAT use Carl Biagetti/STScI 9 SMOV4 CONCEPT (Cont’d) ASSUMPTIONS AND INITIAL CONDITIONS AT RELEASE (To be verified with Project) • Science Instruments – – – – COS in Safe WFC3 in Safe ACS in Safe NICMOS in Protect Safe • NCC off • ESM in Operate – STIS in Safe – FGSs in Operate Carl Biagetti/STScI 10 SMOV4 CONCEPT OPERATIONS DRIVERS/RESTRICTIONS (To be verified with Project) • Bright Earth Avoidance (BEA) – TBD days starting from Release – ACS/STIS MAMA for End-BEA Check? • NCS/NICMOS Cooldown – No high-voltage restrictions per HSTP – No ACS/STIS/FGS pre-requisites Carl Biagetti/STScI 11 SMOV4 Planning Guidelines The Generic SMOV Program • A SMOV program is associated with each servicing mission (viz. www.stsci.edu/smov) • Generic SMOV goals – Timely recommissioning of the Observatory for science operations • Commission newly installed science instruments • Recommission existing science instruments – Recommission Observatory systems for normal operations – Validation of other on-orbit replacements & installations – Early Release Observations • Demonstrate upgraded science capabilities to astronomical community and general public Carl Biagetti/STScI 12 SMOV4 Planning Guidelines Requirements • SMOV4 Requirements – – – – • ASCS no longer in the picture – • Developed in 2003 before mission cancellation Posted at http://www.stsci.edu/smov/smov4.html Requirements for each SI and S/C subsystem (2003 view) Need to update all on basis of current SM4 view Allows elimination of several SI requirements SMOVlite for existing SIs? – Recommended by 2003 Calibration Strategy Working Group (Whitmore) • • • • – Only “Core” SMOV for existing Sis, i.e., ACS/STIS/NICMOS No specific ERO program Use Cycle n cal program asap in place of SMOV commissioning No change to “normal” SMOV for new Sis Need clarification/direction from HST MO • Early indication of SMOVlite for ACS & NICMOS, only. Carl Biagetti/STScI 13 SMOV4 Planning Guidelines REQUIREMENTS PROCESS • Determine SMOV tests/measurements needed to recommission Observatory & SIs (channel-by-channel) – Goal to validate or augment ground-based calibration data bases – Ready Observatory for EROs and normal GO/GTO science operations • Circulate for SMOV team internal review • Present to Project/STScI management – Dec 2006 Carl Biagetti/STScI 14 SMOV4 Planning Guidelines REQUIREMENTS • Determine engineering parameters that need adjustment or measurement for commissioning an SI/channel for normal GO science • Requirements statements should specify quantitative results only where necessary for commissioning – Otherwise, define goals or simply state that a measurement is to be performed and analyzed • Identify any CEI specs to be verified in SMOV • Determine special commanding needs ASAP • Avoid implementation plans at requirements level – Unless unavoidable Carl Biagetti/STScI 15 SMOV4 PLANNING CURRENT APPROACH • Proceed with planning driven by May 2008 launch – Requirements by end of this year • Review and update 2003 requirements • Project Requirements Review = 12 Dec 2006 (tentative) • Await confirmation or change of launch date – New Launch date = May 2008 announced by NASA HQ on 31Oct06. • These charts (and schedule) have been updated to reflect it. Carl Biagetti/STScI 16 SMOV4 Planning Upcoming Stuff • Next SMOV4 Planning Meetings – Nov. 21 • Back-up Dec. 5 • SMOV4 Requirements Review – 12 Dec. 2006 – HSTP/STScI Management Review of our requirements analysis and determination Carl Biagetti/STScI 17