More power reliably into the grid thanks to adapted electrical systems at Niederaussem Electrical Solutions Reference Instrumentation, Controls & Electrical SPPA-E3000 Power Upgrade Package optimally aids to adapt the electrical components and systems during the turbine upgrade at the Niederaussem power plant. The Plant The first unit of a new lignite-fired base-load power plant went into operation in 1963 at the RWE Power AG site in Niederaussem. The plant has undergone continual expansion ever since. It currently comprises nine units and with a total net capacity of 3680 MW it is one of the largest lignite-fired power plants in Europe. The Result ■ Reliable transmission of the increased power into the grid ■ High planning and scheduling reliability thanks to trouble-free project execution with Siemens as the central partner protection made the medium-voltage system to be able to cope with the extended lifetime. The entire MV protection system was replaced and integrated in the new I&C via IEC 61850. This direct integration of the electrical components into SPPA-T3000 produces a uniform and innovative operation and monitoring system with increased diagnostic and analysis capabilities. With Siemens as a central partner for all the issues relating to modernization of the electrical systems, it was possible to complete the on-site changeout, including dismantling, installation and commissioning, in only 10 weeks. The Task The "MOD 600" retrofit program for lifetime extension and for more profitable operation of the two 600-MW units G and H at the Niederaussem power plant also included the uprating of the turbine. To cope with this increased power output, the electrical systems in the plant had to be adapted. Our Solution An I&C modernization based on SPPA-T3000 and an uprating of the LP turbine were required in order to achieve the objectives of the retrofit program. As far as the necessary modernization of electrical systems was concerned, Siemens had the competitive edge over the competitors in all the sub-packages of the contract. Price, competence and a comprehensive and economically sound solution won us the tender. The turnkey SPPA-E3000 Power Upgrade Package, which is customized for use with each individual plant, included an upgrade of the generator bus ducting to enable the increased generator current to be reliably transferred to the grid. The LV switchgear was also replaced while using the existing power and control cables. Modernization of the unit auxiliary supply “We are totally satisfied both with the result and with the execution of the electrical project. The close cooperation between our personnel and the on-site Siemens project team made it possible to adhere to the tight time schedule and the equally tight budget.” Tilman Bechthold Power Plant Manager at Niederaussem RWE Power AG Answers for energy. Retrofit of generator bus ducting A core component of the overall project was the uprating of the turbine. The generator had the necessary reserves, but the bus ducting had come up against its performance limits. This was confirmed by thermographic testing of the generator bus ducting. For this reason RWE opted for complete servicing and modernization of the generator bus ducting. Silver-plated flexible connectors were installed in the generator connection to reduce losses. Because the existing current transformers were no longer able to accurately convert the increased current subsequent to the uprating, they were replaced with transformers with a higher primary current. The voltage transformers were also replaced, as these were close to the end of their service life. New insulators and seals were fitted throughout, in addition to a number of other internal components. Connection of generator bus ducting Replacement of low-voltage switchgear The low-voltage switchgear no longer satisfied current standards and was also replaced as part of the project. The new switchgear with a total of 150 panels and over 1000 load feeders had to be reinstalled in the same place. Extensive preparatory measures, both at the Siemens factory and on site, were necessary in order to reliably complete the work within the scheduled changeout time. The new switchgear was assembled at the factory in a full-scale simulation and tested prior to acceptance by the customer. This included wiring of the cross-panel inter-locks, connection of the automatic transfer gear and assembly of the I&C equipment. All the interlocks and automatic transfer gear and the interaction with the I&C were tested bit for bit in this configuration. The switchgear panels were then delivered directly to Niederaussem for installation and connection. This ensured that commissioning could be carried out in the shortest possible time. SIVACON encapsulated low-voltage switchgear Retrofit for medium-voltage switchgear and integration in the process I&C based on IEC 61850 The upcoming inspection and overhaul of the switchgear panels and circuit breakers in the medium-voltage switchgear was performed in the course of the project. However, the replacement of the protection system was the main focus of the medium-voltage retrofit. Protection devices from the Siemens SIPROTEC family were used. These devices are equipped with IEC 61850 interfaces and could therefore be integrated directly in SPPA-T3000 without the need for any further modification. Further information from the unit auxiliary supply systems, e. g. the low-voltage switchgear, the automatic transfer gear and many other components, was acquired using system components from the SICAM 1703 range and transferred to the I&C by means of an Ethernet link and IEC 61850. The direct integration of the electrical components in the process I&C permits extensive analysis in the event of a fault. When SIPROTEC devices are used, this is further enhanced by a time resolution of 1 ms and, more importantly, by a high time accuracy of < 1 ms between the individual field devices. Published by and copyright © 2012: Siemens AG, Energy Sector Freyeslebenstrasse 1 91058 Erlangen, Germany E304_FR_PUP_Niederaussem_e_V2-0 Order no. E50001-G230-A284-X-4A00 For more information contact sppa-e3000.energy@siemens.com www.siemens.com/energy/sppa-e3000 Siemens AG Fossil Power Generation Instrumentation, Controls & Electrical Siemensallee 84 76187 Karlsruhe, Germany Printed in Germany Dispo 05401, c4bs-Nr. 7465 Printed on elementary chlorine-free bleached paper. Extract from an overview diagram from SPPA-T3000 All rights reserved. Trademarks mentioned in this document are the property of Siemens AG, its affiliates, or their respective owners. Subject to change without prior notice. The information in this document contains general descriptions of the technical options available, which may not apply in all cases. The required technical options should therefore be specified in the contract.