Siemens AG COAL-GEN August 20-22, 2014 COAL-GEN, Nashville, Tennessee, USA, August 20 - 22, 2014 Adding CO2 Post-Capture Helps US CoalSteam Plants Meet Proposed EPA Limits Dennis Horazak, Michael Horn, Oliver Reimuth and Gernot Schneider Siemens AG (Germany) and Siemens Energy, Inc. (USA) 1/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 1 Executive Summary Coal will continue to generate significant amounts of power in the US, but coal plant operators will eventually need to control CO2 emissions. The current EPA proposal would require that about half of the flue gas produced by a coal fired power plant need to be treated in a carbon capture facility. Siemens has developed a post carbon capture technology (PostCap™) based on an Amino Acid Salt (AAS) solution as solvent. The AAS process offers a viable method for both new and existing plants to meet EPA requirements. This paper describes the addition of a Siemens PostCap™ system to a typical pulverized coal supercritical steam power plant, including the estimated impact on thermal performance, cost and space 2 Introduction 2.1 Coal fired power plants in US Based on actual publications for the year 2013 [1] the United States has 1,031 GWe of installed electric capacity, of which 302 GWe, or 29% is fueled by coal. The US Department of Energy expects 45 GWe of coal plant retirements between now and 2040 but only 1.2 GWe of new coal plants, resulting in an overall 14% decline in active coal power to 258 GWe in 2040 [1]. However, the US has large domestic reserves of coal, and coal is expected to continue as a significant source of power generation fuel, as shown in Figure 1. Figure 1 – Coal-fueled US Electric Generating Capacity from 2013 through 2040 [1] Figure 2 shows that over that same period oil and natural gas fueled capacity is expected to increase dramatically so that the 2040 energy mix would be led by 644 GWe or 52% by oil or gas-fueled plants and 258 GWe or 21% by coal-fueled plants. Even with only small predicted numbers for new build coal fired plants this gives a large potential for retrofit of the existing fleet. To receive or extend operation licenses the fulfillment of environmental restrictions is crucial. 2/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Figure 2 –US Electric Generating Capacity Changes from 2013 through 2040 [1] 2.2 EPA requirements Between 1971 and 2002 the US Environmental Protection Agency (EPA) established power plant emission limits for particulate matter, sulfur oxides, and nitrogen oxides. In September 2013 the EPA proposed to also limit carbon dioxide emissions. Under the proposed rule, new power plants would be limited to 454 g CO2/kWh-gross (1,000 lb CO2/MWh-gross) for natural gas-fired turbines burning more than 249 MWth (850 MBtu/h) of natural gas, and to 499 g CO2/kWh-gross (1,100 lb CO2/MWh-gross) for smaller natural gas turbines and coal-fired units. Table 1 shows the current EPA limits for particulates, SO2, and NOx for power plants built after May 3, 2011 [2] and proposed CO2 limits for new power plants. There is no current limit on SO3 emissions, which are typically much lower than SO2 emissions. Contaminant Emission Limit Particulate Matter – smaller of 11 ng/J (0.040 g/kWh = 0.090 lb/MWh) gross power output or 12 ng/J (0.043 g/kWh = 0.097 lb/MWh) net power output Sulfur Dioxide (SO2) – smaller of 130 ng/J (0.486 g/kWh = 1.0 lb/MWh) gross power output or 140 ng/J (0.504 g/kWh = 1.2 lb/MWh) net power output, or 3% of potential SO2 emissions (97% reduction) Nitrogen Oxides (NOx) – smaller of 88 ng/ J (0.317 g/kWh = 0.70 lb/MWh) gross power output or 95 ng/J (0.342 g/kWh = 0.76 lb/MWh) net power output Carbon Dioxide (CO2), proposed 499 kg/MWh (1,100 lb/MWh) gross power output Table 1 – US EPA Emission Limits for New Coal-fired Plants The proposed CO2 limits for new plants are expected to be finalized by June 2014 [3], after which the EPA can address CO2 limits in existing power plants. Section 111(d) of the Clean Air Act requires each of the 50 states to develop plans to implement new emission standards in their existing plants, subject to EPA review and approval [4]. To fulfill the upcoming limits for CO2 3/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 emissions it is important to have carbon capture technologies developed and mature for full scale applications. While for new build plants three major technology lines are currently apparent (Pre combustion/coal gasification, post combustion/absorption from flue gas and oxy-fuel), for retrofit of existing plants the choice is limited to post combustion technologies. This is based on the fact that the use of the two other technologies would require major changes within the existing power plant. Thus those technologies are not feasible for retrofit. 2.3 CO2 Removal from Typical Coal-Steam Plants Most US coal-steam plants would have to capture between 30% and 60% of flue gas CO2 in order to meet the EPA limit of 500 kg (1,100 lb) per MWh(e) of plant gross power, as shown in Figure 3. Most US bituminous coals produce between 295 and 325 kg CO2 per MWh(thermal) (650-720 lb/MWht), and most US low-rank coals produce between 310 and 350 kg/MWht (690770 lb/MWht). For reference, pure carbon produces 390 kg (860 lb) of CO2 per thermal megawatt hour. Typical subcritical and supercritical PC plants without CO2 capture have gross efficiencies around 39% and 41%, respectively. Adding CO2 removal to comply with EPA regulations reduces gross efficiency by 3 to 10 points, depending on the removal technology 1, resulting in gross efficiencies around 29-36% for subcritical plants and 31-38% for supercritical plants. As a result the curved lines represent 30%, 35% and 40% gross efficiencies of power plants that include CO2 removal to meet EPA emission limits. Figure 3 is a simplified graph for the estimation of how much CO2 must be removed to meet EPA regulations at a given power plant. The horizontal axis represents CO2 produced for each thermal MWh of heat released by burning the coal 2. The gross efficiency of the standard power plant should be reduced by 3 to 10 points to get the curved lines. The vertical axis shows the percent of CO2 that must be removed from the flue gas in order to meet EPA limits. An example: Illinois No. 6 coal with an HHV of 27.13 MJ/kg (11,666 Btu/lb) and 63.75% carbon produces 310 kg(683 lb)/MWht, plus another 2% of CO2 produced by the FGD, resulting in 316 kg (697 lb)/MWht of total CO2 on the horizontal axis. If it were used in a supercritical plant with 38% gross efficiency (41% minus 3% for CO2 removal), the required CO2 reduction to get to 500 kg (1,100 lb) per MWh(e) would be 40%. 3 (Please refer to the black arrows in figure 3.) 1 Included here: CO2 compression to 152 bara Includes CO2 from flue gas desulfurization (FGD), assumed to be 2% of coal CO2. 3 For comparison: The flue gas without CO2 removal would contain 1,834 lb (832 kg) of CO2, per MWh(gross electric) 2 4/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Figure 3 - Required CO2 Removal to meet 1,100 lb(CO2)/MWhe(g) 2.4 Typical configuration of a modern supercritical coal fired steam power plant Driven by the increased environmental awareness over the last decades and resulting legislations equipment for emission reduction with regards to NOx, SOx and particulate matters for power plants has been developed, introduced to the market and is now state of the art. The main elements of a typical state of the art pulverized coal supercritical steam power plant are shown in Figure 3. Coal is burned with primary air in a wall-fired boiler furnace while forceddraft fans provide additional air, including over-fire air to reduce NOx. The pressure in the boiler is slightly less than ambient, so that any air leakage is into the boiler, identified as infiltration air. A selective catalytic reduction (SCR) unit in the boiler controls NOx emissions, fabric filters in a baghouse remove particulate material, and activated carbon injection (not shown) controls mercury. An induced draft fan provides additional pressure to move the flue gas through the remaining emission control equipment and out the stack. A wet flue gas desulfurizer (FGD) converts flue 5/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 gas sulfur compounds into byproduct gypsum using makeup water, oxidation air and limestone slurry. The requirement to reduce the CO2 emission poses a new challenge to the industry, mainly based on the large quantities to be treated. By using a post capture technology this leads to a predominantly “chemical” plant, which has to be considered with regards to capital and operative expenses as well as space and utility consumption. The principal location of the CO2 Capture Plant and CO2 compression in the process is shown with dashed lines in Figure 4. Figure 4 – Main Elements of Typical Pulverized Coal Supercritical Steam Power Plant Thermal Performance Operating conditions and performance data for a typical supercritical steam cycle is taken from a comparison study of various types of reference coal-fired plants with and without carbon capture, performed for the Department of Energy and reported in 2010 [5]. From this report, Case 11 was chosen as a base for this paper. The main performance data of this case (without CO2 capture) are summarized in Table 2. Plants with CO2 capture would have reduced gross power due to LP steam being used for solvent regeneration. Besides that, the net power output is shortened due to the auxiliary loads for the CO2 removal equipment and CO2 compressor. 6/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Plant Thermal input Steam Turbine Power (gross) Plant Auxiliary Power Plant Net Power Plant Net Efficiency (HHV) Steam main cycle pressure Steam main cycle temperature Reheat steam pressure Reheat steam temperature IP/LP steam crossover pressure IP/LP steam crossover temperature Condenser cooling duty Condensation pressure Condensation temperature MWth MWe MWe MWe 1,400 580 30 550 39.30% MPa (psia) °C (°F) MPa (psia) °C (°F) MPa (psia) °C (°F) MWth MPa (psia) °C (°F) 24 (3515) 593 (1100) 4.5 (656) 593 (1100) 1.2 (170) 392 (737) 638 0.01 (1) 38 Coal type Illinois No.6 Total Auxiliary Power Requirement MWe 30 Table 2 – Main performance data for Case 11 (typical supercritical steam power plant without carbon capture) Capital and Operating Cost Estimates Using the NETL report [6] as a reference, the equipment capital cost (Total Plant Cost) of this power plant, excluding owner’s costs, is estimated to be $ 1,981/kWe, in June 2011 dollars. When owner’s costs are added to this figure, including preproduction costs, inventory capital, initial catalysts and chemicals, land, and financing costs, the resulting Total Overnight Capital is $2,452/kWe. Operating and maintenance costs for this typical plant, including fuel costs are estimated to be $42.61/MWh. Emission Performance For a new supercritical plant, the emissions are assumed to meet EPA New Source Performance Standards for NOx, SO2 and particulates 3 Application of Siemens PostCapTM to a typical US coal-fired steam power plant under proposed EPA requirements 3.1 Siemens PostCapTM technology The Siemens Energy Sector has developed the PostCap (post combustion carbon capture) absorption process based on an amino acid salt solvent (aqueous solution), which is capable of separating at least 90% of the CO2 contained in the flue gas from coal, oil or gas fired power 7/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 plants as well as from industrial sources. Figure 5 shows the principal Siemens PostCap process configuration. Cleaned Flue Gas Solvent Reclaiming CO2 Compression CO2 Absorption CO2 Desorption Flue gas inlet Figure 5 – Siemens PostCapTM Process configuration The raw flue gas is cooled in a flue gas cooler and then conveyed by a blower through the absorber. The gas leaves the top of the absorber as cleaned flue gas. The solvent meets the flue gas in the countercurrent absorber, where CO2 is selectively absorbed by a chemical reaction. The “rich” solvent (loaded with CO2) is pumped from the absorber bottom and heated up in a “rich/lean solvent heat exchanger”, before it enters the top of the desorber column. At the desorber bottom, the chemical bonding of CO2 is reversed at a higher temperature (which is provided by steam in a reboiler). Thus a mixture of CO2 and water is stripped out. The water is condensed at the desorber top, whereas the remaining CO2 is compressed (and if applicable purified) for transport, such as by pipeline, and further use. The “lean” solvent (which has been relieved of most of its CO2) is pumped from the desorber bottom, cooled in two steps (“rich/lean solvent heat exchanger” and “lean solvent cooler”) and then fed to the absorber top. A small solvent slipstream is taken downstream of the lean solvent cooler for reclaiming. The purified solvent is fed back upstream of the lean solvent cooler. The particular advantages of using an Amino Acid Salt as solvent are: • Application of an environmentally friendly, non-toxic solvent • Minimal detectable solvent emissions due to a very low vapor pressure • Good solvent stability against various degradation mechanisms, particularly from oxygen and - as a result - low solvent refill need Ease of handling by power station operators and personnel. 8/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 In addition to these features Siemens has proven the operability and effectiveness of the process and its low energy consumption in more than 9,000 hours of operation in the PostCap™ pilot plant at E.ON’s hard coal fired Power Plant Staudinger in Germany since September 2009. The onsite pilot facility is able to process flue gas from the coal fired plant as well as from a separate gas fired plant. One selection criterion for the solvent was a low thermal energy demand for stripping CO2 from the rich solvent. The PostCap™ demand of 2.7 GJ per tonne (1161 Btu/lb) of CO2 captured has been validated in the pilot plant. It was achieved with improved process configurations and is considerably lower than the energy demand for MEA baseline solution. In addition there is still potential to further decrease this figure. Absorber operating temperature would be in the range of 40°C to 50°C (104°F to 122°F), and the stripper operating temperature between 100°C and 110°C (212°F to 230°F). The PostCap™ reclaimer needs much less thermal energy than does the MEA baseline process because it uses crystallization instead of thermal distillation to separate waste material from the solvent. Based on the results of these pilot plant tests, a scale-up of this technology to large-scale demonstration and full-scale projects is possible. Siemens PostCap technology had been chosen by several large-scale projects globally for the design of CO2 capture plants to be optimally integrated into either new-build power plants or to be retrofitted to existing ones. Recently, Siemens successfully finalized the Technology Qualification Program for the large-scale Carbon Capture Mongstad (CCM) project in Norway. The 18-month program included a pilot plant operation and comprehensive engineering for the large-scale CO2 capture plant. During process operation amino acid salt solvents (as well as amines) form degradation products by thermal stress or reactions with SOx, NOx, and oxygen contained in the flue gas. To offset this degradation, the Siemens PostCap process applies a proprietary two-step reclaiming process to minimize solvent losses, hence operation costs. SOx contaminated solvent is fully recovered, the blocking of the solvent is fully reversed, and a sellable sulfur product is generated. In principle any SOx content in the flue gas is feasible for PostCap, however in practice a reasonable level has to be determined based on economic considerations (cost of flue gas desulfurization vs. cost of reclaiming). Furthermore a highly selective separation of the amino acid salt solvent from other by-products is applied and thus a high recyclability assured. Each step of the reclaimer can be operated independently (either continuously or batch-wise), which allows tailor-made solutions for client’s needs. For full scale applications the dimensions of the reclaimer are relatively small compared to the rest of the capture plant. Siemens has developed a reclaimer design with a high degree of prefabrication where complete units are pre-mounted in transportable skids with steel frames. This allows system testing (such as water tightness) in the factory and thus shortens erection and commissioning periods on site. 3.2 PostCapTM CO2 Capture Plant Design Based on the reference coal fired plant (NETL Case 11) as described under 2.4 a post combustion capture plant design was developed to a) fulfil the EPA requirements given for new build coal fired power plants as outlined in section 2.2 for a reference power plant and b) use a state-of-the-art design to reduce necessary investment and operating costs. 9/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 The same technology would apply for the retrofit of an existing coal fired plant. In this case it would be necessary to investigate the best possible ways to supply mainly of steam and power (but also for other necessary utilities) from the existing systems. Furthermore, additional space restrictions in the existing plant layout have to be considered. 3.2.1 Plant Design Resulting from EPA Requirements and NETL Configuration To reach the EPA requirement for CO2 emissions of 499 g/kWh (gross) only a slip stream of the flue gas needs to be treated by CO2 capture. To calculate this slip stream, the normal CO2 emissions of a supercritical coal fired power plant of 760 g/kWh (gross) needs to be taken into account, as well as the loss of gross power caused by the heat consumption of the capture plant. For this paper it was decided to keep the power plant at its given design, to simulate an existing plant. This means that the net power output will be reduced by the power demand for CO2 capture and compression. This decision was made to keep the comparability for new build plants as well as for retrofits. With approximately 13 vol% of CO2 in the flue gas and a state-of-the-art capture rate of 90 % this results in a slipstream of approx. 49 % of flue gas mass flow, or 291 kg/s (642 lb/s) to the Siemens PostCap™ process. Temperature Pressure 57 °C 135°F 1.0077 bara 3.11 in w.c. Composition Amount kg/h CO2 216.179 476,596 20.6% 13.5% N2 692.391 1,526,469 66.1% 68.1% O2 27.881 61,467 2.7% 2.4% Ar 0 0 0.0% 0.0% H2O 99.218 218,739 9.5% 15.2% Other 11.893 26,220 1.1% 0.8% 1.047.562 2,309,491 100.0% 100.0% Total amount By-products Amount kg/h Amount lb/h Mass fraction Vol fraction Amount lb/h ppmv NOx 45 NO2 2 SO2 88 194 SO3 3 7 38 Table 3: Mass Flow and Composition of Flue Gas at Carbon Capture Plant Inlet From the IP/LP crossover, steam of 364 °C (688 °F) at 0.93 MPa (135 psia) is available for the PCC process in the NETL configuration [5]. This steam is throttled, and condensate is injected in order to reach the conditions desired at battery limits of the capture plant, which are 153 °C (307 °F) and 0.52 MPa (75 psia). Optimizing the effect of steam extraction on the power plant along with the requirements of the PostCap plant gives room for further improvement but is not covered in this paper because an integral approach to both plant designs would be necessary. 10/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Detailed simulation of PostCap performance by Siemens showed that the chosen parameters lead to a decrease of gross output by approx. 45 MWe. Based on the resulting value of 535 MWe the specific CO2 emission is 460 g/kWh (gross) (1,014 lb/MWh) and thus well below the required limit set in the EPA requirements. 3.2.2 Plant Design Resulting from Siemens PostCap™ Process Requirements When investigating the design parameters for this paper we kept in mind that for future investment decisions the capital expenditure (CAPEX) is of major importance while in parallel operating expenditures (OPEX) need to be kept at a reasonable level. Taking into account that CO2 compression is not directly influenced by PostCap design, and would lead to similar values for different capture processes, and that that the balance of plant is highly dependent on local conditions (such as available space, air, and water conditions), the major lever for a general CAPEX reduction is the design of the columns and internals and the choice of materials. Based on this the decision was to use a single train design (1 flue gas cooler, 1 flue gas blower, 1 absorber, 1 desorber). This leads to column diameters smaller than 12 m (39 ft), which is well within the limits for production, transport and handling during erection. Whether the large columns will be delivered as single prefabricated units or in pieces to be siteerected has to be decided for each specific project based on local labor cost and available infrastructure. Flue Gas Cooler The flue gas cooler is designed to cool the flue gas from 57 °C (135 °F) to approx. 30 °C (86 °F). In addition the flue gas cooler washes out some particulate matter and other contaminants in the flue gas. To further reduce the SOx content of the flue gas a dosing of an alkaline solution shall be integrated. A high amount of SOx in the flue gas would lead to higher (temporary) blocking of the solvent and thus a larger Siemens SOx reclaimer. The diameter of the flue gas cooler is 12 m (39 ft). Absorber Column A high efficiency packing design optimized for the configuration with amino acid salt (AAS) is used in the absorber. This leads to higher gas volume flow and thus a reduced column diameter, resulting in a lower CAPEX. As an alternative the pressure drop and thus the power requirement of the flue gas blower could be reduced, if the column diameter is kept constant. This would lead to lower OPEX and may be considered at regions with high prices for electrical energy. Based on the given cooling water conditions (NETL report)[5] the solvent temperature at the inlet of the absorber was set to 30 °C (86 °F). At this temperature an effective and flow optimized absorption can be achieved. For the cost evaluations in this paper the lower column diameter was taken into account. Under the given design conditions the column diameter was calculated to be 11.5 m (38 ft). In amine-based PCC processes there is normally an additional washing step installed on top of the absorber column to clean the emitted flue gas from solvent aerosols and vapor. This step is not considered necessary for the AAS solution used by Siemens based on the fact that salts have very low vapor pressures. For possible droplet emissions a demister is foreseen. This configuration was tested successfully in the pilot plant at E.ON’s Staudinger coal fired power plant in Germany. 11/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 The decision to use either high alloy steel or concrete with liner for the absorber column structure depends on local labor cost, local availability and local cost of material (for concrete) and requirements such as earthquake or explosion pressure. Explosion pressure may apply in cases where oil and gas producing facilities are close by (e.g. refineries). In general the use of concrete becomes more cost effective if stability requirements would lead to thicker steel columns. Desorber Column For the desorber, a packing capable of handling higher liquid loads is used. The desorber is operated at a pressure of 3 bara (43.5 psia), which leads to a lower pumping power and cost reduction for some auxiliary equipment. At the same time, the column diameter can be reduced, which outweighs the higher cost for the design of the desorber as pressure vessel. Under the given design conditions this results in a column diameter of 10 m (33 ft) for the desorber. Reclaimer As described in chapter 2.3, Siemens has developed a proprietary design for reclaiming the solvent. The reclaimer consists of two units each modularized on pre-fabricated transportable skids with steel frames approximately 3.5 m long, 4 m wide, and 13 m high (11 ft x 13 ft x 43 ft). For the described reference plant configuration and based on the given concentrations of SOx and NOx in the flue gas the SOx reclaimer consists of 3 modules (3 vertical) and the NOx reclaimer of 4 modules (1 vertical, 3 horizontal). Plant Layout Taking into account the dimensions of the main components and auxiliary buildings as well as necessary areas for construction, operation and maintenance lead to a space requirement of approximately 170 m x 125 m (558 ft x 410 ft or 5.25 acres). One possible arrangement is shown in Figure 6. Structures for cooling water supply are heavily dependent on local conditions and are project specific, so direct cooling, cooling tower or air/water cooling units and are not shown here. Therefore at a cooling water circulation rate of approximately 35,600 m3/h (156,760 gpm), a significant space requirement for cooling water supply or cooling tower also has to be taken into account. 12/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Figure 6 - Possible Layout for a Carbon Capture Facility 3.3 Cost Impact and economic viability Impact on Electricity Price The capital expenses for a 49 % slip stream post carbon capture facility based on Siemens PostCap™ technology were estimated for a supercritical pulverized coal power plant with a defined gross output of approximately 535 MWe and at the environmental conditions described in NETL Report, Case 11 [5]. The cost is distributed among several portions as shown in Figure 7. Columns incl. internals 28.3% 16.2% 5.4% 14.7% 7.2% 13.2% CO2 Compression Other equipment Bulk material Construction 15.0% Civil Others/owners cost Figure 7 – CAPEX Distribution for CCS Plant 13/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 The addition of PostCap to the power plant is estimated to increase the CAPEX per kWe by 6070% and increase the OPEX per MWh by 30-35%. OPEX strongly relates to local utility prices (e.g. steam, electricity, water). In this paper it is assumed that steam and electricity are supplied internally by the power station without any additional cost, except for the power penalty related to a decreased net output of the plant. Using a simplified calculation taking into account CAPEX depreciation over 20 years and OPEX including power penalty, solvent refill, and operation and maintenance, a CO2 cost of approximately $80-58/tonne CO2 captured seems feasible. Not considered in this paper are cost for transport and storage of the captured CO2. Those costs project-specific have to be evaluated and added depending on local infrastructure, distance to and characteristics of the storage location. Table 4 shows the resulting data for the reference configuration used in this study. EPA limits were met by capturing 90% of the CO2 from approximately 49% of the flue gas stream. Power plant only Plant Thermal input MWth Steam Turbine Power (gross) Power plant incl. Delta carbon capture 1,400 1,400 0 MWe 580 535 -45 Plant Auxiliary Power MWe -30 -65 -35 Plant Net Power MWe 550 470 -80 Plant Net Efficiency (HHV) % CO2 emission to atmosphere kg(lb) /MWhe(g) 39.3 760 (1675) 33.6 460 (1014) 5.7 -300 (-661) Table 4: plant performance data without and with carbon capture The net output of the power plant decreases 15% from 550 MW to 470 MW, leading to a 5.7 %point reduction in efficiency. At 7,500 hours of operation per year this results in an electrical production of 3,525,000 MWh/a (net). The specific CO2 emission is reduced by 300 kg/MWh (gross) (662 lb/MWh(gross)) leading to an amount of 1,459,000 tonnes of CO2 captured per year. These performance estimates are for the CO2 capture system retrofitted into an existing coalsteam plant without modifying the steam turbine. In the retrofit case, relatively high-quality steam is extracted from the steam cycle to regenerate the sorbent, then throttled and cooled without any further utilization. The performance penalty would be smaller if the steam turbine could be modified for optimal steam extraction, or if a back-pressure turbine could be added to utilize more energy from the higher-pressure steam. It might also be possible to replace the intermediate pressure section with a new design that allows steam extraction at the desired conditions. Newly built power stations offer still more options, although the available turbine designs might still not be optimal, and consideration of turbine part-load behavior can increase the complexity of the analysis. In any 14/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 case, attention to detail when integrating the CO2 capture system with the power block can help reduce the overall plant performance loss associated with the retrofit. Taking into account the above mentioned costs of $80-85/tonne CO2 captured the application of a CCS Plant at a coal fired power plant to reach the new EPA requirements would lead to a penalty of $30-35/MWh for the electricity price. It has to be stated that this value is based on a lot of assumptions where local environmental and industrial conditions and market situation are involved. Enhanced Oil Recovery (EOR) Primary oil recovery methods can produce only about 10-15 % of the oil in an oil field, and secondary methods such as water injection can re-pressurize the well and increase oil recovery to 20 - 40 %. A tertiary (enhanced) recovery method such as CO2 injection can increase recovery up to 30 – 60% by mixing CO2 with the oil to decrease its viscosity while increasing its pressure.[7] The quality of the CO2 generated in the PostCap™ process can meet the requirements for EOR applications, when CO2 purification steps are applied in combination with CO2 compression. Published reports indicate market prices of $40 – 80 per tonne of CO2.[8] There is already an existing CO2 pipeline infrastructure in the US serving regions around Texas and Louisiana, as shown in Figure 8. US oil wells produced about 103 million barrels of oil using 62 million tons of CO2 for EOR in 2012 [9], and the US market for CO2 is expected to grow. There are an estimated 80,000 million barrels of oil under the US that could be economically recovered using EOR, and approximately 25,000 million metric tons of CO2 would be required for this recovery.[10] For comparison, the Summit Texas Clean Energy IPCC Project produces 2.5 million metric tons of CO2 per year, so it would take 500 Summit-sized plants operating for 20 years to meet the potential CO2 market for EOR in the US. 15/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Figure 8 - Active US CO2 Pipeline and Injection Site Infrastructure [11] Future Improvements and Cost Reductions It has to be stated that a CCS plant will require a huge investment. At the current state of CCS development, the technology still has a high potential for optimization and further cost reductions as the process matures. With increasing confidence in the technology based on operational experience, processes can be optimized in regard to temperature, pressure and volume flow. Use of cheaper materials will be investigated and could lead to further cost reduction. For a real project, and especially with increasing market for plants with CO2 capture, equipment cost will decrease based on common purchasing levers. 4 Conclusion The paper shows that a carbon capture plant using Siemens PostCap™ technology can meet EPA requirements for a medium-to-large size coal fired power plant in the US. Depending on the growth of electricity production in the USA, “clean coal” solutions may become viable options in future energy scenarios. The use of CO2 for EOR will assist in quicker market introduction of CO2 capture technology. 16/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Large scale employment of CO2 capture technology is possible today. However, further development of CO2 capture technologies is necessary to reach higher maturity and confidence while decreasing costs for full scale applications. 5 References [1] EIA, Annual Energy Outlook 2014 Early Release, December 2013. Table 9, Electric Generating Capacity [2] EPA, 40 CFR Part 60, Subpart Da – Standards if Performance for Electric Utility Steam Generating Units, sections 60.42Da, 60.43Da, and 60.44Da. [3] McCarthy, James E., EPA Standards for Greenhouse Gas Emissions from Power Plants: Many Questions, Some Answers, November 15, 2013. [4] Tarr, Jeremy M., Jonas Monast & Tim Profeta, Nicholas Inst. for Envtl. Policy Solutions, Duke Univ., Regulating Carbon Dioxide under Section 111(d) of the Clean Air Act: Options, Limits, and Impacts (2013), http://nicholasinstitute.duke.edu/climate/policydesign/regulating-carbon-dioxideunder-section-111d [5] NETLa, Cost and Performance Baseline for Fossil Energy Plants, Volume 1, Bituminous Coal and Natural Gas to Electricity, Revision 2, DOE/NETL-2010/1397, November 2010. [6] NETLb, Updated Costs (June 2011 Basis) for Selected Bituminous Baseline Cases, DOE/NETL-341/082312, August 2012. [7] US Department of Energy, http://energy.gov/fe/science-innovation/oil-gas/enhancedoil-recovery [8] Bloomberg New Energy Finance, company filings [9] Godec, M. L., “Opportunities for Utilizing Anthropogenic CO2 for Enhanced Oil Recovery and CO2 Storage,” presentation to Workshop: Introduction to Carbon Dioxide Enhanced Oil Recovery (CO2-EOR), Houston Texas, June 11, 2013. [10] Van Leeuwen, T., “An Updated Review of US and Worldwide CO2-EOR Resources,” prepared by Advanced Resources International for the 17th Annual Midland CO2 Flooding Conference, Midland Texas, December 8, 2011.] [11] Melzer, L. Stephen, Carbon Dioxide Enhanced Oil Recovery (CO2 EOR): Factors Involved in Adding Carbon Capture, Utilization and Storage (CCUS) to Enhanced Oil Recovery, prepared for the National Enhanced Oil Recovery Initiative, Center for Climate and Energy Solutions, February 2012. 17/18 Copyright © Siemens AG 2014. All rights reserved. Siemens AG COAL-GEN August 20-22, 2014 Permission for use The content of this paper is copyrighted by Siemens and is licensed to COAL-GEN for publication and distribution only. Any inquiries regarding permission to use the content of this paper, in whole or in part, for any purpose must be addressed to Siemens directly. Disclaimer These documents contain forward-looking statements and information – that is, statements related to future, not past, events. These statements may be identified either orally or in writing by words as “expects”, “anticipates”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “will” or words of similar meaning. Such statements are based on our current expectations and certain assumptions, and are, therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond Siemens’ control, affect its operations, performance, business strategy and results and could cause the actual results, performance or achievements of Siemens worldwide to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise, among others, from changes in general economic and business conditions, changes in currency exchange rates and interest rates, introduction of competing products or technologies by other companies, lack of acceptance of new products or services by customers targeted by Siemens worldwide, changes in business strategy and various other factors. More detailed information about certain of these factors is contained in Siemens’ filings with the SEC, which are available on the Siemens website, www.siemens.com and on the SEC’s website, www.sec.gov. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in the relevant forward-looking statement as anticipated, believed, estimated, expected, intended, planned or projected. Siemens does not intend or assume any obligation to update or revise these forward-looking statements in light of developments which differ from those anticipated. Trademarks mentioned in these documents are the property of Siemens AG, its affiliates or their respective owners. 18/18 Copyright © Siemens AG 2014. All rights reserved.