Grid Access Huge offshore platforms are needed to transmit offshore wind power to the shore. Their construction is sensational in size, material, and logistics. A report from the yard. Text: Onno Groß Photos: Kay-Uwe Rosseburg The Art of Illustration: Bridgemanart Building a Colossus The topside of the HelWin 1 platform is as tall as the Colossus of Rhodes – together with its substructure, it’s almost as tall as London’s Big Ben. Living Energy · No. 7 | November 2012 47 Grid Access Denmark Germany Flensburg SylWin Husum BorWin HelWin Heide Substation Büttel DolWin Cuxhaven Substation Hagermarsch Stade Wilhelmshaven Germany Delfzijl Netherlands Rorichmoor Substation Diele Giants in the Ocean HVDC converter platforms are cuttingedge links between offshore wind parks and onshore power grids, converting the turbines’ AC power into direct current for low loss transmission to onshore HVDC converter stations. BorWin 1 (400 MW)** BorWin 2 (800 MW)* DolWin 1 (800 MW)** DolWin 2 (900 MW)** DolWin 3 (900 MW)X HelWin 1 (576 MW)* HelWin 2 (690 MW)* SylWin 1 (864 MW)* * Siemens (contract) ** Other provider (contract) X Tendering 48 Living Energy · No. 7 | November 2012 I nevitably, the Colossus of Rhodes comes to mind. As the Greeks once must have done before one of the Seven Wonders of the Ancient World, I am marveling at the enormous structure that is being created in the Nordic Yards hangar in Wismar: an eight-deck construction, almost the size of a soccer field and filled with technology. How can something this large ever be anchored in the sea? This massive construction, assembled in one of Europe’s biggest covered dockyards, is the HelWin 1, a so-called HVDC (high-voltage direct-current) converter platform for the transformation of alternating into direct current on sea. It will serve to link the many offshore wind turbines in the North Sea with the onshore grid. The name HelWin is derived from the Ger- man outpost in the North Sea, Heligoland. In its vicinity, 85 kilometers off the coast, the HVDC converter platform will be anchored more than 20 meters below sea level in 2013. Placing this steel monster – 35 meters high, 72 meters long, 51 meters wide – in the choppy North Sea, that’s the real technological challenge. To achieve this feat, the platform is being built in two parts: the topside, in which the technological apparatus is encased, and the base frame, the foundation on the bottom of the sea. They will be transported separately to their location and assembled at sea. Shipyard Craftsmanship In the dock on the Baltic Sea coast, a base frame for an HVDC converter platform has already been completed and placed on board a ship. The di- Graphics: independent Substation Dörpen / West mensions are again gigantic, considering that many thousand tonnes of steel went into the base frame’s construction. In shallow waters, for instance off the English coast, many wind turbines use a simple steel anchoring system called Monopile. But the German wind turbines are located much further out in the open sea, beyond the Wadden Sea and out of sight of the coastline. Here, the turbines have to be installed on a tripod or a jacket, also known as a lattice tower, to weather the tides. And they have to be extremely tall, since waves can – once or twice in a century – pile up to 20 meters high in a North Sea gale. From a distance, the basement on the wharf resembles a climbing frame with its towering cranes, spokes, and reinforcements. However, when standing in front of it, you simply face a bulky mess of pipes rising into the sky. On closer inspection, I can make out the five strong support pipes forged from the best offshore steel, each pipe wall 8 centimeters thick, ­almost the length of a ballpoint pen. The shipyard workers are standing in front of the huge grid, displaying apparent pride in their work. The steel construction was executed with the utmost care, since the base frame will have to provide a solid support for the HelWin HVDC converter station. Seven hundred shipyard workers at Nordic Yards are involved in building and setting up the offshore platform. It takes three times as many working hours to assemble the platform as to build a container vessel. But as yet they’re still sailing in uncharted waters with the construction of offshore platforms. Vitaly Yusofov, owner and chairman of Nordic Yards, assures me that, “the dockyard has a long tradition and is already experienced in building drilling platforms.” He aims to be an important partner for maritime special orders. The shipyard craftsmanship is also noticeable in the hangar where the HVDC converter platform is being built. My exploratory visit of the topside takes me over a couple of stories. In the lower parts lie two gigantic clean rooms full of transistors – they are the core of the offshore converter station. Then I head onwards through the climatic chambers which will later be used for cooling and air cleaning, through the workshops, passing the rooms for IT and the cabins for a crew of 20, and all the way up onto the top roof. Up here, cranes and a heliport have been installed, giving an idea of the working routine out on sea. The gulls are still missing, but the sea view from almost 50 meters altitude is sure to be overwhelming. Unmapped Territory A construction of this scale with complex HVDC transmission is globally still unmapped territory. During the assembly, the most cutting-edge mi- crotechnology is subjected to higher dust loading. “This calls for strong ­logistics, so that all components can be fitted quickly,” says Christian Schmitt, Project Manager at Siemens, and explains the challenge to me. The procedure has to be organized in a sensible way and at the same time set the standards for future constructions. At Siemens in Hamburg, 300 employees from the offshore department are busy optimizing the logistics to speed up the assembly of such offshore platforms. The HVDC converter platform HelWin 1 is not the only order in the Baltic Sea shipyard’s book. Actually, with a capacity of 576 megawatts, it is the smallest of four Siemens constructions currently under way. Three additional HVDC converter platforms desperately needed to connect the wind farm to the grid are SylWin 1 (­ 864 MW), BorWin 2 (800 MW), and HelWin 2 (690 MW). Colossal Proportions 70 m 35 m 22 m Big Ben 23 m Human Soccer Field Living Energy · No. 7 | November 2012 49 Grid Access cent of the power requirement. Great Britain plans to raise the proportion of wind energy to 25 percent of the ­total, covered by up to 48.6 gigawatts from offshore wind farms. In the latest planning phase – the so-called Round 3 – the wind turbines will be increasingly built at greater distances from the coastline and thus need an HVDC connection. An estimated 160 wind farm clusters will spring up all over Europe in the near future. Connecting these wind farms is a ­logistical challenge, also for the network provider TenneT who commissioned the platforms. The Dutch company will connect the North Sea wind turbines to the grid. “It’s exciting at the moment,” confirms Wilfried Breuer, Senior Manager for offshore projects at TenneT. Comparable to the work of an urban planner, he has to distribute wind farm clusters, transformer platforms, direct current and three-phase current connections, and converter stations onshore in the tight exclusive economic zone of Germany. “In ten years’ time, we will have implemented nearly all future plans in network development, I’m sure about that.” Tim Dawidowsky of Siemens is equally optimistic: “Although we’ve been facing some difficulties with our first projects, I am convinced we will hardly remember these initial teething problems in ten years’ time. Offshore wind energy will become a success story.” BorWin is the second-largest of four HVDC converter platforms that Siemens will install in the North Sea to link the wind farm to the German power grid. Pioneer Projects in the North Sea 20 – 25 > 100 (in kilometers) 350 Average capacity 750 (in megawatts) 20 – 35 Water depth (in meters) Platform 20 – 40 2,000 – 2,500 (in tonnes) 10,000 – 15,000 AC solutions in Great Britain 50 Living Energy · No. 7 | November 2012 DC solutions in Germany A Profitable Future Market Compared to a three-phase current cable, HVDC technology transmits power almost without loss. If you take sea cables more than 80 kilometers long, this technology is the mandatory solution. Add Europe’s ambitious goals for the move to sustainable energy sources and the need to find an alternative to nuclear power to the equation and what you get is a profitable future market. Germany aims to generate 10 gigawatts from offshore wind farms by 2020 – this will require about 3,000 wind turbines – and to raise the output by 2030 to a total of 25 gigawatts. This will match 15 per- Photos: Ulrich Wirrwa, Kay-Uwe Rosseburg Graphic: independent From the coast “All offshore projects a long distance from the coast need high-voltage ­direct-current transmission,” says Tim Dawidowsky, CEO Business Unit Transmission Solutions of Siemens Energy. “Without these new power highways, Germany will not be able to meet its goals set for the expansion of renewable energy sources.” Siemens has installed more than 860 turbines in the sea, totaling approximately 2,500 megawatts of installed offshore capacity. Worshipping the Wind Network provider TenneT has announced investment obligations of currently €6 billion in the offshore segment. In the northern Baltic Sea, an HVDC route will power energy via the HelWin 1 HVDC converter platform to the converter station in Schleswig-Holstein. Significant lengths of cables, both underwater and onshore, will be needed to transmit power from the wind farms. In the southern part of the route, off the island of ­Borkum, two further direct current connections have been projected. In addition, the move towards renewable energy sources in Germany is ­being backed by roughly 3,800 kilometers of new transmission lines and optimization of 4,400 kilometers of existing routes onshore. Ultimately, there will be a new HVDC offshore grid that will transmit power from the sea via the coastlines to all over Europe. Gigantic colossi like the HelWin 1 platform are an indispensible part of it. The lighthouse on the Greek island of Rhodes was once built to honor the sun god Helios. In the north, present-day architects rather seem to worship the wind. p Onno Groß, a science journalist from Hamburg, writes regularly about maritime issues for news­ papers and magazines such as National Geographic, Financial Times Deutschland or Handelsblatt. 860 Siemens Wind Turbines to Date The platform’s base frame is made of thousands of tonnes of steel. The boom in wind energy started about ten years ago. Helped along by the Renewable Energy Act of 2000, the number of wind turbines increased rapidly. More than two dozen building applications for the windy North and Baltic Sea have been submitted to the Federal Maritime and Hydrographic Agency (BSH); so far 8 gigawatts of installed capacity have been granted. 2010 saw the commissioning of the first test area, alpha ventus just off Borkum. In May 2012, Baltic 1, the first wind farm in the Baltic Sea, followed suit: Here, 21 Siemens wind turbines produce enough energy to power a medium-sized town. Worldwide, Tim Dawidowsky (center), CEO Business Unit Transmission Solutions, at the Nordic Yards in Wismar. Living Energy · No. 7 | November 2012 51