Application of decision theory to the procurement of a geothermal power plant April 2nd 2008 Viktor Þórisson www.enex.is Presentation Overview 1. Company overview & background 2. What is geothermal energy? 3. Definition of the project 4. Application of @risk and precision tree in this project www.enex.is Company Overview Export of Icelandic Geothermal Know-how What we do Development of geothermal potential for electrical generation and direct use. Feasibility Studies & Business Plans Reliance on comprehensive know-how and operational experience. Engineering Founded in 1969 by the main geothermal consultancies in Iceland to export the Icelandic geothermal consulting. Project Management Construction & Commissioning Operation www.enex.is What is geothermal energy? www.enex.is What is geothermal? The thermal energy stored within the earth's crust is collectively called geothermal energy. Faults and fractures develop where the earth crust is unstable or is moving, most commonly in areas of active volcanism. www.enex.is What is geothermal? In areas of active volcanism, the upper crust is frequently intruded by hot magmatic intrusions. These intrusions move heat from the inner parts of the earth towards the outer crust. They are the prime force that usually drives geothermal systems. In some parts of the world hot rock formations within the crust contain water, which is the ideal medium for carrying this energy up to the earth's surface in a useful form. www.enex.is Simplified geothermal power plant cycle www.enex.is Waste water bathing www.enex.is Main factors affecting the profitability • • • • Temperature of reservoir (or enthalpy) Flow from well (or production index) Depth of well Chemical conditions of the brine www.enex.is Definition of the project Decision tree to answer the question: In a geothermal project. When to procure the critical components with the longest lead time for a power plant, after last drilling, before first drilling or somewhere in between? www.enex.is The project chart if components are ordered after drilling www.enex.is Main trade offs in the model are Benefit: •Shorter time until plant is operational. Trade-off: •More information available when components are ordered and thus optimizing the efficiency of the plant •The risk of higher investment cost than necessary due to over dimensioning of the turbine. •Potential higher costs if project results in no go after drilling and thus order cancellation fees of components are incurred. www.enex.is Overview of the Overview oftree the tree www.enex.is Probabilities, methodology (1-cummulative distribution) www.enex.is Fitted distributions Normal(1,21184; 0,66555) Normal(160,289; 18,687) 1,0 1,0 0,8 0,8 0,6 0,6 0,4 0,4 0,2 0,2 < 5,0% 129,55 90,0% 5,0% > 191,03 < -Infinity 100,0% 2,5 2,0 1,5 1,0 0,5 0,0 0,0 200 190 180 170 160 150 140 130 120 0,0 > +Infinity www.enex.is Definition of failure Insurance line 148 146 Temperature [°C] 144 142 140 Insurance line 138 136 134 132 0 0,2 0,4 0,6 0,8 1 1,2 Production Index [l/sek/m] www.enex.is Probability of failure first drilling • Probability of failure due to reasons other than geological is defined as 5%. • Probability of success first drilling is therefore: 89,26% * 95% = 84,9% www.enex.is Probability of success second drilling www.enex.is Given success first drilling BetaGeneral(3,6130; 1,2859; 109,492; 177,157) Uniform(0,13379; 2,4238) BetaGeneral(3,6130; 1,2859; 109,492; 177,157) 1,0 1,0 4,0 0,8 0,8 3,5 PI 5,0% 2,309 5,0% 90,0% 135,81 180 90,0% 135,81 < 170 180 170 160 150 140 Temperature 90,0% 0,248 130 120 110 2,5 2,0 1,5 1,0 0,5 0,0 0,0 160 0,0 0,5 150 0,0 1,0 140 0,2 1,5 130 0,2 2,0 120 0,4 0,4 2,5 110 0,6 100 0,6 Values x 10^-2 3,0 175,12 175,12 www.enex.is Results from simulation, probability of failure of the project, given success/given failure first drilling. www.enex.is Potential plant size Distribution for peak plant cut of belove insurance function X <=-2,5 .032% 0,12 X <=7,36 10.74% 0,1 0,08 0,06 0,04 0,02 0 -5 0 5 10 15 20 25 Mean plant size 13,8 MW given success first drilling. Example of Possible values: T PI 165 1,5 160 2,1 www.enex.is 30 The newsboy problem CO * PO = CU * PU www.enex.is Sensitivity of production to flow 20% 10% -40% -30% -20% power Sensitivity 0% -10% 0% -10% flow to turbine 10% 20% 30% 40% -20% -30% -40% -50% www.enex.is Other costs • Cost of over sizing (CO) 500.000 EUR/MW unnecessary investment cost. • Cost of under sizing (CU) Expected cancellation fee of turbine. Cost of lost production Cost per MW lost production thousends of Euros 4500 4000 3500 3000 2500 Cost of lost production 2000 1500 1000 500 0 8 8,5 9 9,5 10 10,5 MW 11 11,5 12 12,5 www.enex.is The optimal path www.enex.is Sensitivity of costs Spider graph of NPV 13500 13000 12500 1. Expected lost revenues due to efficiency reduction NPV 12000 11500 2. Expected value of lost production explained above 3. Expected value of extra investment cost if pre ordered 11000 10500 10000 9500 9000 0% 200% 400% 600% % change from base value 800% 1000% www.enex.is Sensitivity of costs Decisions, drilling vs. ordering turbine before first drilling 14000 1. Drill first well without ordering components 13000 12000 NPV 11000 10000 2. Order genset before first drilling 9000 8000 7000 6000 0% 200% 400% 600% 800% 1000% % Change from base value of expected extra investm ent cost if pre ordered www.enex.is 2 way decision analyze of costs % change from base value of expected extra investment cost 2 way decision analys 1000% 900% 800% 700% 600% 500% 400% 300% 200% 100% 0% 1. Drill first well without ordering components" 2. Order genset before first drilling" 0% 200% 400% 600% 800% 1000% % change from base value of lost efficiency www.enex.is Sensitivity of probabilities Sensitivity of probabillities NPV 20000 15000 P(success|success) 10000 P(success|failure) 5000 P(success) 0 -60% -50% -40% -30% -20% -10% 0% -5000 10% 20% P(nongeological success) -10000 % change of probabillities from base value www.enex.is 2 way decision analyze of probabilities % Change from base value of P(nongeological success) 2 way decision analys 70% 60% 50% 1. Drill first well without ordering components 40% 30% 2. Order genset before first drilling 20% 10% 0% 0% 10% 20% 30% 40% 50% 60% 70% % Decrease from base value P(success) www.enex.is Thank you www.enex.is