The Great Wind Reality Check: Getting Funded Steve Krebs Hilton University of Houston

advertisement
The Great Wind Reality Check:
Getting Funded
Steve Krebs
Hilton University of Houston
Houston, Texas
November 15, 2005
Funding Follows the Cash Flow
ƒ
Equity investors and lenders seek quality cash flows.
ƒ
Quality cash flows produce stable margins, robust
debt service coverages and leverage.
ƒ
Stable cash flows produced by appropriate structuring,
risk identification and allocation.
ƒ
Due diligence and contractual structuring facilitate
appropriate risk allocation.
Project Risk Identification/Allocation
Sound project structuring and financing requires
evaluation & allocation of risks and rewards, including:
ƒ
ƒ
ƒ
ƒ
Completion
Operating
Transmission
Revenue
These are not nearly exclusive.
Completion Risk
Risk project is not completed on time, on budget and
capable of operating as expected
ƒ Site control
ƒ Turbine suppliers strike back
ƒ
ƒ
ƒ
ƒ
Availability
Down payments
Delivery flexibility
Cost increases
ƒ Balance of plant agreement - no wrap of turbines
ƒ Permits
ƒ Possible delay - NIMBY
ƒ Environmental and regulatory
ƒ Interconnection upgrades
Completion Risk (cont’d)
Completion Risk Mitigants
ƒ Tightly crafted TSA/BOP
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
Proven contractor
Fixed cost/scope/schedule
Liquidated damages
Performance bonds/retainage/LOCs/guarantees
Proven design
Permits
Insurance/contingency amounts
Sponsor guarantees/completion tests
Operating Risk
The risk that the project, once complete, will not perform
as expected. Mitigated by:
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
experienced creditworthy operator
safety, security and environmental safeguards
permits
perform PPA and interconnection agreements
incentives for good performance
O&M reserves
insurance
Transmission Risk
The risk that the power will not flow to the customer
ƒ Who pays interconnection costs?
ƒ Constraints on transmission
ƒ Locational Marginal Pricing disproportionably affects wind
generators
ƒ Remote wind sites create access problems
ƒ Imbalance penalties
ƒ Wind intermittent
ƒ Reactive and Voltage requirements
Revenue Risk
The risk that the project will not have adequate cash for
debt service, costs and return to sponsors.
ƒ PPA
ƒ contracted volumes
ƒ pricing
ƒ creditworthiness
ƒ Merchant
ƒ uncontracted volumes
ƒ Change in market model
ƒ PTC
ƒ in service by 12/31/07
ƒ RECs
ƒ Change in law
Power Purchase Agreement Issues
ƒ
Coordinate with other project/financing arrangements
ƒ
Completion requirements
ƒ Commercial Operation Date - right to terminate/LDs
ƒ Added turbine/tower/cost overruns
ƒ Matches BOP/TSA/TWA
ƒ
Scheduling/Curtailment
ƒ
Default, damages for breach and termination
ƒ
Force majeure
ƒ
Financing
ƒ Strong PPA yields financing includes less equity, more
leverage, lower reserves, longer tenor, lower costs, easier
distribution conditions.
Financing Sources
Use Complex Financing Structures
ƒ Traditional Project Finance
ƒ Tax Equity
ƒ
ƒ
ƒ
ƒ
Some developers without PTC/tax attribute appetite
Financial investors monetarize benefits
Complicated tax/cash flow allocations
Maintain business alignment
ƒ Portfolio financings/Project bonds
ƒ IPO
ƒ Private Equity
Investors not over merchant power bust. May require:
ƒ Market studies for volumes and prices of power
ƒ Cost/engineering/transmission/insurance studies
Conclusion
ƒ
Getting wind projects funded can be challenging.
Applying lessons learned will make sounder
structures.
ƒ
Limited recourse financing will be available for wellstructured projects using PPAs.
ƒ
Successful projects align their business model with
the capabilities and objectives of their participants.
ƒ
Even with experience, creative thinking and careful
planning are required for successful financing and
development.
Questions
Steve Krebs
Partner and Head of Project Development and
Finance Practice
Baker Botts LLP
One Shell Plaza
910 Louisiana
Houston, Texas 77002
Telephone
Fax
E-mail
1-713-229.1467
1-713-229-7767
stephen.krebs@bakerbotts.com
www.bakerbotts.com
Download