Conventional Facilities Overview

advertisement

CF LCLS Commissioning Plan

Javier A. Sevilla

Engineering Group

Conventional Facilities

June 17, 2008

CF Commissioning Plan-FAC Review

1

Javier A. Sevilla sevilla@slac.stanford.edu

June 17, 2008

CF Commissioning Plan-FAC Review

Outline

Plan

Team

Commissioning Process

Activities

Deliverables

Summary

2

Javier A. Sevilla sevilla@slac.stanford.edu

Beam Transport Hall

Commissioning Areas

Undulator Hall Near Experimental

Hall

Central Utility Plant/

12Kv Substation 522

Far Experimental

Hall

Electron Beam Dump

Front End Enclosure

X-Ray Transport &

Diagnostics Tunnel

June 17, 2008

CF Commissioning Plan-FAC Review

3

Javier A. Sevilla sevilla@slac.stanford.edu

Prepared by

Commissioning Plan

1. Defines Scope of CxA and requirements

2. Part of contract documents for each MEP subcontractor

3. Part of TCCo

Contract http://www-ssrl.slac.stanford.edu/lcls/cf/commissioningplan/

June 17, 2008

CF Commissioning Plan-FAC Review

4

Javier A. Sevilla sevilla@slac.stanford.edu

Scope Definition for CxA

1. List Requirements

2. List Deliverables

3. List team members

4. Provides all reference documentation https://www-lcls-internal.slac.stanford.edu/projectspace_L2/Project_Office/SOW/ConvFac/1.9-703-r0.pdf

June 17, 2008

CF Commissioning Plan-FAC Review

5

Javier A. Sevilla sevilla@slac.stanford.edu

Team

Commissioning Agent

(CxA)

Engineering Economics

Inc. (EEI)

CF Engineering Group

CF Construction Group

LCLS QA Manager

Turner

MEP Coordinator

Cx Coordinator

June 17, 2008

CF Commissioning Plan-FAC Review

6

SLAC Facilities Dept

HVAC, Electrical, Fire Alarm,

Ops Mechanics

Subcontractors

O. C. McDonald-HVAC &

Piping

Alpha Air Balancing Agency

Cupertino Electric (CEI)

Air Systems, Inc. BMS

Ceitronics-Fire Alarm

Mitsubishi-Elevator

Allied Cranes

RCM-Fire Protection

Javier A. Sevilla sevilla@slac.stanford.edu

Commissioning Agent (CxA)

Engineering Economics Inc (EEI)

Selected by using a competitive bidding process

Five bids received (AEC, EEI,AEI, and WBI)

EEI has offices nationwide and able to shift resources if necessary

Commissioned over 33 million sf

Data centers, office buildings

Medical research labs

Pharmaceutical labs

Federal facilities

LCLS Sector 20 Injector Facilities - successful

LCLS Magnetic Measurement Facilities - successful

June 17, 2008

CF Commissioning Plan-FAC Review

7

Javier A. Sevilla sevilla@slac.stanford.edu

Commissioning Meeting

Started in

Nov. 14,

2007-

Meetings every 3 weeks

May 2-08

Weekly

Meetings

June 17, 2008

CF Commissioning Plan-FAC Review

8

Javier A. Sevilla sevilla@slac.stanford.edu

CF LCLS

K. Ahmed

R. Baclit

D. Ciorbea

R. Maggi

J. Saldivar

J. A. Sevilla

L. Shewchuk

K. Yang

QA Manager

D. Marsh

ESH/BIO

R. Kerwin

E. Gomes

B. Smith

EEI

K. Quigley

A. Parker

M. Abrahamson

Commissioning Team

Subcontractors-TCCO SLAC Facilities

A. Pimentel

F. Sisca

C. Farnell

R. Gonzales

G. Strickland

J. Fitzgerald

H. Limosnero

K. Minchaca

D. Swartz

R. Spina

R. Furtado

T. Locatelli

M. Clayton

B. Choate

G. Kuraitis

R. Radau

K. Chan

R. Candelario

B. Harrison

P. Francisco

S. Poitier

S. Jensen

J. Kang and HV electricians

J. Pfefferkorn

F. Castillo and LV electricians

K. Joong

N. Yeung

R. Zingsheim

June 17, 2008

CF Commissioning Plan-FAC Review

9

Javier A. Sevilla sevilla@slac.stanford.edu

Commissioning Team at Work

June 17, 2008

CF Commissioning Plan-FAC Review

10

Javier A. Sevilla sevilla@slac.stanford.edu

Commissioning Process

PLAN

Requirements (FT, PFT, Acceptance, Inspections)

Resources (CxA, CF Engrs, TCCO, Subcontractors, Facilities

Configuration Control of test results, observations, inspections, minutes, schedule, acceptance, etc.

Configuration Control of tests results, inspections, training, documentation, acceptance, etc.

http://www-ssrl.slac.stanford.edu/lcls/cf/commissioningplan/

June 17, 2008

CF Commissioning Plan-FAC Review

11

Javier A. Sevilla sevilla@slac.stanford.edu

Configuration Management Cx Process ftp://ftp.slac.stanford.edu/groups/lcls/Turner/LCLS%20Commissioning%20Process/

June 17, 2008

CF Commissioning Plan-FAC Review

12

Javier A. Sevilla sevilla@slac.stanford.edu

Commissioning Process

Activities

Review of design documents by CxA

Site inspections (CxA, Facilities Dept, CF LCLS)

Prepare list of observations (by Category)

Review of Constructions checklists (CxA and

Facilities Dept)

Witness some PFT (CxA)

Perform ALL Functional Testing (FT)

June 17, 2008

CF Commissioning Plan-FAC Review

13

Javier A. Sevilla sevilla@slac.stanford.edu

Chillers

CUP Plan View

Boilers

Drawing M0203

Electrical Rm

June 17, 2008

CF Commissioning Plan-FAC Review

14

Mech Room-NEH

Javier A. Sevilla sevilla@slac.stanford.edu

CUP On-Going Cx Activities

Boiler

Substation 522

Chillers

Switchgear

June 17, 2008

CF Commissioning Plan-FAC Review

15

CUP transformers

Javier A. Sevilla sevilla@slac.stanford.edu

Commissioning Activities Completed

Substation S522

Energized and completed except pending punch list

Rating capacity 4,000 amps, 12.47 KV

Provides power to LCLS three 2.5MVA transformers and others

New medium pressure underground natural gas piping to CUP: 1,400 LF

30 Million BTUHs nominal capacity

BTH West Construction

BTH Switchboard ( 480 v, 3 ph, 800 Amps)

June 17, 2008

CF Commissioning Plan-FAC Review

16

Javier A. Sevilla sevilla@slac.stanford.edu

LCLS Substation S522

Substation 522 behind the CUP

12.47 kv Switchgear inside

June 17, 2008

CF Commissioning Plan-FAC Review

17

Javier A. Sevilla sevilla@slac.stanford.edu

CENTRAL UTILITY PLANT (CUP)

Major Equipment to Commission

Two Chillers (425 tons/ea), Primary and Secondary CHW loops and

Pumps  BTH,UH,EBD,FEE, NEH and FEH

One Boiler (150 BHP/ea) Primary and Secondary HW loops and pumps

DDC Temperature Control System to be connected to SLAC network via ALC Web Control

Interface with EPICS (Technical systems)

One Air Compressor (268 SCFM@150psi), Air Dryer and Receiver.

Will provide service to: BTH, UH, EBD, FEE, NEH,X-RAY, FEH

Wet Sprinkler System-Ordinary Hazard Group 1

One AHU for electrical room

Mechanical rooms for NEH HVAC system (MAU) and AHU’s

June 17, 2008

CF Commissioning Plan-FAC Review

18

Javier A. Sevilla sevilla@slac.stanford.edu

Chillers Room in CUP

June 17, 2008

CF Commissioning Plan-FAC Review

19

Javier A. Sevilla sevilla@slac.stanford.edu

Deliverables

Final Commissioning Report

Pre-Functional and Functional Test Reports

(FT), PFT, Checklists, observations. Etc.

O&M MEP

Training Records

All documentation available for future operations and maintenance

June 17, 2008

CF Commissioning Plan-FAC Review

20

Javier A. Sevilla sevilla@slac.stanford.edu

Summary

Roles and responsibilities are clearly defined in the

Commissioning Plan

Expectations are documented and well understood!

CxA reports to CF LCLS and collaborate with

TCCO, MEP subs, SLAC Facilities maintenance and operations staff

Goal is to deliver a complete and functional project with all MEP systems fully operational, inspected, tested, checked, verified and documented!

June 17, 2008

CF Commissioning Plan-FAC Review

21

Javier A. Sevilla sevilla@slac.stanford.edu

End of Presentation

Supporting Documentation to Follow

June 17, 2008

CF Commissioning Plan-FAC Review

22

Javier A. Sevilla sevilla@slac.stanford.edu

Partial List of MEP Equipment

June 17, 2008

CF Commissioning Plan-FAC Review

23

Javier A. Sevilla sevilla@slac.stanford.edu

Minutes of Meetings

June 17, 2008

CF Commissioning Plan-FAC Review

24

Javier A. Sevilla sevilla@slac.stanford.edu

Review Documentation and PFT

June 17, 2008

CF Commissioning Plan-FAC Review

25

Javier A. Sevilla sevilla@slac.stanford.edu

Chillers

CUP Plan View

Boilers

Drawing M0203

Electrical Rm

June 17, 2008

CF Commissioning Plan-FAC Review

26

Mech Room-NEH

Javier A. Sevilla sevilla@slac.stanford.edu