Javier A. Sevilla
Engineering Group
Conventional Facilities
June 17, 2008
CF Commissioning Plan-FAC Review
1
Javier A. Sevilla sevilla@slac.stanford.edu
June 17, 2008
CF Commissioning Plan-FAC Review
2
Javier A. Sevilla sevilla@slac.stanford.edu
Beam Transport Hall
Commissioning Areas
Undulator Hall Near Experimental
Hall
Central Utility Plant/
12Kv Substation 522
Far Experimental
Hall
Electron Beam Dump
Front End Enclosure
X-Ray Transport &
Diagnostics Tunnel
June 17, 2008
CF Commissioning Plan-FAC Review
3
Javier A. Sevilla sevilla@slac.stanford.edu
Prepared by
Commissioning Plan
1. Defines Scope of CxA and requirements
2. Part of contract documents for each MEP subcontractor
3. Part of TCCo
Contract http://www-ssrl.slac.stanford.edu/lcls/cf/commissioningplan/
June 17, 2008
CF Commissioning Plan-FAC Review
4
Javier A. Sevilla sevilla@slac.stanford.edu
Scope Definition for CxA
1. List Requirements
2. List Deliverables
3. List team members
4. Provides all reference documentation https://www-lcls-internal.slac.stanford.edu/projectspace_L2/Project_Office/SOW/ConvFac/1.9-703-r0.pdf
June 17, 2008
CF Commissioning Plan-FAC Review
5
Javier A. Sevilla sevilla@slac.stanford.edu
Team
Commissioning Agent
(CxA)
Engineering Economics
Inc. (EEI)
CF Engineering Group
CF Construction Group
LCLS QA Manager
Turner
MEP Coordinator
Cx Coordinator
June 17, 2008
CF Commissioning Plan-FAC Review
6
SLAC Facilities Dept
HVAC, Electrical, Fire Alarm,
Ops Mechanics
Subcontractors
O. C. McDonald-HVAC &
Piping
Alpha Air Balancing Agency
Cupertino Electric (CEI)
Air Systems, Inc. BMS
Ceitronics-Fire Alarm
Mitsubishi-Elevator
Allied Cranes
RCM-Fire Protection
Javier A. Sevilla sevilla@slac.stanford.edu
Engineering Economics Inc (EEI)
Selected by using a competitive bidding process
Five bids received (AEC, EEI,AEI, and WBI)
EEI has offices nationwide and able to shift resources if necessary
Commissioned over 33 million sf
Data centers, office buildings
Medical research labs
Pharmaceutical labs
Federal facilities
LCLS Sector 20 Injector Facilities - successful
LCLS Magnetic Measurement Facilities - successful
June 17, 2008
CF Commissioning Plan-FAC Review
7
Javier A. Sevilla sevilla@slac.stanford.edu
Commissioning Meeting
Started in
Nov. 14,
2007-
Meetings every 3 weeks
May 2-08
Weekly
Meetings
June 17, 2008
CF Commissioning Plan-FAC Review
8
Javier A. Sevilla sevilla@slac.stanford.edu
CF LCLS
K. Ahmed
R. Baclit
D. Ciorbea
R. Maggi
J. Saldivar
J. A. Sevilla
L. Shewchuk
K. Yang
QA Manager
D. Marsh
ESH/BIO
R. Kerwin
E. Gomes
B. Smith
EEI
K. Quigley
A. Parker
M. Abrahamson
Commissioning Team
Subcontractors-TCCO SLAC Facilities
A. Pimentel
F. Sisca
C. Farnell
R. Gonzales
G. Strickland
J. Fitzgerald
H. Limosnero
K. Minchaca
D. Swartz
R. Spina
R. Furtado
T. Locatelli
M. Clayton
B. Choate
G. Kuraitis
R. Radau
K. Chan
R. Candelario
B. Harrison
P. Francisco
S. Poitier
S. Jensen
J. Kang and HV electricians
J. Pfefferkorn
F. Castillo and LV electricians
K. Joong
N. Yeung
R. Zingsheim
June 17, 2008
CF Commissioning Plan-FAC Review
9
Javier A. Sevilla sevilla@slac.stanford.edu
Commissioning Team at Work
June 17, 2008
CF Commissioning Plan-FAC Review
10
Javier A. Sevilla sevilla@slac.stanford.edu
Commissioning Process
PLAN
Requirements (FT, PFT, Acceptance, Inspections)
Resources (CxA, CF Engrs, TCCO, Subcontractors, Facilities
Configuration Control of test results, observations, inspections, minutes, schedule, acceptance, etc.
Configuration Control of tests results, inspections, training, documentation, acceptance, etc.
http://www-ssrl.slac.stanford.edu/lcls/cf/commissioningplan/
June 17, 2008
CF Commissioning Plan-FAC Review
11
Javier A. Sevilla sevilla@slac.stanford.edu
Configuration Management Cx Process ftp://ftp.slac.stanford.edu/groups/lcls/Turner/LCLS%20Commissioning%20Process/
June 17, 2008
CF Commissioning Plan-FAC Review
12
Javier A. Sevilla sevilla@slac.stanford.edu
Commissioning Process
Activities
Review of design documents by CxA
Site inspections (CxA, Facilities Dept, CF LCLS)
Prepare list of observations (by Category)
Review of Constructions checklists (CxA and
Facilities Dept)
Witness some PFT (CxA)
Perform ALL Functional Testing (FT)
June 17, 2008
CF Commissioning Plan-FAC Review
13
Javier A. Sevilla sevilla@slac.stanford.edu
Chillers
CUP Plan View
Boilers
Drawing M0203
Electrical Rm
June 17, 2008
CF Commissioning Plan-FAC Review
14
Mech Room-NEH
Javier A. Sevilla sevilla@slac.stanford.edu
CUP On-Going Cx Activities
Boiler
Substation 522
Chillers
Switchgear
June 17, 2008
CF Commissioning Plan-FAC Review
15
CUP transformers
Javier A. Sevilla sevilla@slac.stanford.edu
Commissioning Activities Completed
Substation S522
Energized and completed except pending punch list
Rating capacity 4,000 amps, 12.47 KV
Provides power to LCLS three 2.5MVA transformers and others
New medium pressure underground natural gas piping to CUP: 1,400 LF
30 Million BTUHs nominal capacity
BTH West Construction
BTH Switchboard ( 480 v, 3 ph, 800 Amps)
June 17, 2008
CF Commissioning Plan-FAC Review
16
Javier A. Sevilla sevilla@slac.stanford.edu
LCLS Substation S522
Substation 522 behind the CUP
12.47 kv Switchgear inside
June 17, 2008
CF Commissioning Plan-FAC Review
17
Javier A. Sevilla sevilla@slac.stanford.edu
CENTRAL UTILITY PLANT (CUP)
Major Equipment to Commission
Two Chillers (425 tons/ea), Primary and Secondary CHW loops and
Pumps BTH,UH,EBD,FEE, NEH and FEH
One Boiler (150 BHP/ea) Primary and Secondary HW loops and pumps
DDC Temperature Control System to be connected to SLAC network via ALC Web Control
Interface with EPICS (Technical systems)
One Air Compressor (268 SCFM@150psi), Air Dryer and Receiver.
Will provide service to: BTH, UH, EBD, FEE, NEH,X-RAY, FEH
Wet Sprinkler System-Ordinary Hazard Group 1
One AHU for electrical room
Mechanical rooms for NEH HVAC system (MAU) and AHU’s
June 17, 2008
CF Commissioning Plan-FAC Review
18
Javier A. Sevilla sevilla@slac.stanford.edu
Chillers Room in CUP
June 17, 2008
CF Commissioning Plan-FAC Review
19
Javier A. Sevilla sevilla@slac.stanford.edu
Deliverables
Final Commissioning Report
Pre-Functional and Functional Test Reports
(FT), PFT, Checklists, observations. Etc.
O&M MEP
Training Records
All documentation available for future operations and maintenance
June 17, 2008
CF Commissioning Plan-FAC Review
20
Javier A. Sevilla sevilla@slac.stanford.edu
Summary
Roles and responsibilities are clearly defined in the
Commissioning Plan
Expectations are documented and well understood!
CxA reports to CF LCLS and collaborate with
TCCO, MEP subs, SLAC Facilities maintenance and operations staff
Goal is to deliver a complete and functional project with all MEP systems fully operational, inspected, tested, checked, verified and documented!
June 17, 2008
CF Commissioning Plan-FAC Review
21
Javier A. Sevilla sevilla@slac.stanford.edu
June 17, 2008
CF Commissioning Plan-FAC Review
22
Javier A. Sevilla sevilla@slac.stanford.edu
Partial List of MEP Equipment
June 17, 2008
CF Commissioning Plan-FAC Review
23
Javier A. Sevilla sevilla@slac.stanford.edu
Minutes of Meetings
June 17, 2008
CF Commissioning Plan-FAC Review
24
Javier A. Sevilla sevilla@slac.stanford.edu
Review Documentation and PFT
June 17, 2008
CF Commissioning Plan-FAC Review
25
Javier A. Sevilla sevilla@slac.stanford.edu
Chillers
CUP Plan View
Boilers
Drawing M0203
Electrical Rm
June 17, 2008
CF Commissioning Plan-FAC Review
26
Mech Room-NEH
Javier A. Sevilla sevilla@slac.stanford.edu