Running a power grid with 100% renewables on King Island, Australia Simon Gamble Manager Hybrid Off-Grid Solutions Context and Key Messages • It is possible to operate a MW scale island power system at 100% RE penetration o Despite myths around RE you can improve safety, reliability and security o Key is integration at all levels – policy, planning, design, control, operation • However, to integrate renewable energy requires changes to system operation o utility must be involved : new paradigm = new capability requirements • Attractive returns on investment are possible o Primary aim should be to displace diesel fuel through higher RE penetration o Technology has matured, demonstrations have mitigated risk Invitation to visit King Island and see the system working 2-day international workshop 18/19 November Hydro Tasmania Hybrid off-grid power systems capability • Government Business Enterprise – owned by State • Australia’s largest clean energy producer • Utility responsible for generation, distribution and retail in the Bass Strait islands • Developer, owner and operator of leading hybrid offgrid systems • King Island was our test bed for solution development – menu of integration options • Leading consultant to aid agencies and utilities, including: Yap, Cook Islands, Rottnest Island, Coober Pedy, Thursday Island. King Island location Source: Google Earth King Island : largely agricultural land use with world class wind resource King Island power system 18 year development path for renewable energy Population approx. 1,600 • • • • 2.5MW load 6MW diesel generation 450km of 11kV Expensive system - diesel fuel is 80% of cost - incentive to use RE Adding RE is an integration challenge – RE displaces diesel generation High RE requires enabling systems – communication; control; services Requires holistic approach – policy, planning; phasing development Diesel fuel cost dominates 1998 – First Wind Farm Low renewable energy penetration “Low hanging fruit” Deliberately limited RE installed No impact to operations Simplified Solar PV example 15% reduction in diesel 2004 – Wind Farm Expansion Medium renewable energy penetration 2.45MW wind (1.2MW min load) RE controlled (limited) protect diesels Some RE is wasted (curtailed) Simplified Solar PV example 30% annual reduction in diesel Note minimum diesel operation 2008 – First enabling technology Enhanced medium renewable energy penetration Enabling technology – Dynamic Resistor (Load bank) elements 35% annual reduction in diesel • Resistive elements artificially increase the load: convert excess to heat • Load balance is maintained (dynamically by resistors) – not diesel generators • More RE is utilised – more diesel savings Counterintuitive : taking spilled energy & converting to a useful service 2014 - Energy Storage An enabling technology option for high RE penetration • Absorb excess RE (increase the load) • Recover excess RE (power injected) • Applications o Load balancing o reserves o power for security of supply o energy shifting Australia’s largest battery – 3MW / 1.5MWh King Island 2014 – Advanced hybrid system Ability to operate at 100% RE penetration • Need to always operate diesel generation has been a key barrier to renewables 100% RE systems require: • Surplus RE capacity • Full automation – high speed communication and control • Enabling systems – that replace all services provided by diesels King Island flywheel – supports system without diesel generation Consumes surplus renewable energy to operate Also an instant start diesel generator to provide firm capacity 2014 - Demand management Further optimise RE utilisation by altering demand to match available RE generation (another option) • Aggregates controllable customer load to help balance demand / supply during high RE contribution and variation. • Fast load shedding , smart EV charging, smart solar PV switching • Monitoring customer load and providing data to customers via smart phone app. 2015 - King Island System Proven, robust, reliable MW class hybrid system Result of planned, coordinated activity > $24m in diesel savings (>$2m per annum) > 900 hrs of diesel off operation 65% diesel savings now possible Good return on investment Cost of power reduced Winner 2013 innovation award 2015 – King Island System Operation Extended “diesel off” operation (100% RE) Combined performance of enabling systems King Island app & web site Real time data www.kingislandrenewableenergy.com.au 2016 – Reduce cost of deployment New approach : Scalable modular enablers & control Flinders Island Hybrid Energy Hub Project – under construction Aim is to further reduce time, cost, risk of deployments Thank you Further information: Hybrid Off-Grid Solutions Simon Gamble simon.gamble@hydro.com.au www.kireip.com.au “KIREIP” iPhone app