foundation has to be prepared

advertisement
Infrastucture and Schedule
•Detector power supply
•Detector cooling
•Polarity switches
•Kicker pulser
•Preparation of the experimental hall
•Modification of the IP region
•Installation of Olympus
•Time schedule
April 6th 2009
Olympus Meeting at DESY, F.Brinker
1
Detector power supply
• A 10kV to 480V transformer is available and will be
placed outside the experimental hall
• The foundation has to be prepared
• The 7000 A power supply from Petra has to be installed
in the hall
• The cabling to the transformer (10kV), to the power
supply (2500A, 480V DC) and to the detector (7000A,
225V DC) has to done ( ~ 9 km cable in total )
April 6th 2009
Olympus Meeting at DESY, F.Brinker
2
Water cooling
• A cooling water circuit for about 1.6 MW for the toroid
has to be installed
• The capacity of the cooling tower is sufficient
• the place for the heat exchanger and the water pump is
available near water supplies from the cooling tower
• A heat exchanger and a water pump can be reused from
Hera/Zeus
• The tubes, regulation and electronics will be new
• Cooling for the moved cavities is still available, the last
few meters are missing
• Cold water for air conditioning is available, tubes have to
be laid
April 6th 2009
Olympus Meeting at DESY, F.Brinker
3
Polarity switches
• There are 46 main magnet power supplies at DORIS and
the transport line
• 12 of those are already replaced by bipolar devices
• 10 devices with currents below 270A can be modified
with polarity switches from HERA
• The remaining 24 devices need new polarity switches,
14 devices for 400A and 10 devices for 800A
• Cabinets, controls and cabling have to be done
April 6th 2009
Olympus Meeting at DESY, F.Brinker
4
Powersupply
Transformer
Water
cooling
April 6th 2009
Olympus Meeting at DESY, F.Brinker
5
Kicker pulser
• The extraction/injection elements at DESY and DORIS
have to be bipolar
• The Septa can be modified accordingly
• The Kicker ( 2 DORIS + 1 DESY ) need new power
supplies, which can be build at DESY ( spare parts? )
April 6th 2009
Olympus Meeting at DESY, F.Brinker
6
Preparation of the experimental hall
• Parts of the hall are in use as store room, the parts here
have to be removed
• Another part is used for an DESY exhibition, these
objects will be removed and partly find a new home in
HERA hall west
• The ARGUS detector has to be disassembled and
removed
This work can start soon and should be finished by the end
of this year
April 6th 2009
Olympus Meeting at DESY, F.Brinker
7
Modification RF-lab
• An RF laboratory for testing of Tesla cavities is placed on
the outside of the DORIS ring
• A rectangular region of 2.5 x 9.5 m has to be cut out
–
–
–
–
–
Install dust cover
Remove walls
Cut ceiling and floor
Build new walls
Change installations ( crane, electricity, water etc.)
This work can start in summer 2010, when the ongoing
work in the laboratory is finished (earlier, if possible)
April 6th 2009
Olympus Meeting at DESY, F.Brinker
8
Modification of the IP region (1. shut down )
• Move signal cables from IP region ( can be done in
advance )
• Remove interlock installations
• Remove shielding blocks
• Remove accelerator components
– Cavities, vacuum chambers
– 4 quadrupoles
– Girders
• Install dust cover
• Demolition work on parts of concrete
April 6th 2009
Olympus Meeting at DESY, F.Brinker
9
Modification of the IP region
•
•
•
•
•
•
•
•
Build up new shielding
Install new girders/support for experiment vacuum
Put in 6 new quadrupoles
Install vacuum system, including target chamber and
new vacuum valves
Install cavities at the new position
Cabling, water connections
Install modified interlock system
Surveying
April 6th 2009
Olympus Meeting at DESY, F.Brinker
10
April 6th 2009
Olympus Meeting at DESY, F.Brinker
11
Installation of Olympus ( 2. shut down)
•
•
•
•
•
•
•
•
Remove part of shielding
Remove vacuum system between valves
Roll in the detector
Install vacuum chambers
Connect cooling water and electrical power
Rebuild shielding
Surveying
Interlock tests
April 6th 2009
Olympus Meeting at DESY, F.Brinker
12
April 6th 2009
Olympus Meeting at DESY, F.Brinker
13
April 6th 2009
Olympus Meeting at DESY, F.Brinker
14
Background
studies
Parasitic studies
+ some days (~5)
full operation
April 6th 2009
Olympus Meeting at DESY, F.Brinker
15
Download