Project Management Process
Managing the Information
Systems Project
Focus of project management
To ensure that information system projects
meet customer expectations
Delivered in a timely manner
Meet constraints and requirements
Managing the Information
Systems Project
Project Manager
Requires diverse set of skills
Leadership
Customer relations
Technical Problem Solving
Conflict management
Team Management
Risk & Change Management
Project Management Process
Initiation
Assess the size, scope and complexity of the
project
Establish procedures to support later project
activities
Planning
Define clear, discrete activities and the work
needed to complete each activity
Execution
Plans created in prior phases are put into action
Closing down
Initiating the Project
1.
2.
3.
4.
5.
Establish project initiation team
Establish relationship with customer
Establish project initiation plan
Establish management procedures
Establish project management
environment and workbook
Planning the Project
1. Describe project scope, alternatives
and feasibility
Scope and Feasibility
Understand the project
What problem is addressed
What results are to be achieved
Measures of success
Completion criteria
Planning the Project
2. Divide the project into manageable
tasks
•
•
Work breakdown structure
Gantt chart
3. Estimate resources and create a
resource plan.
4. Develop a preliminary schedule
•
Utilize Gantt and PERT charts
Gantt Chart
PERT Chart
Comparison of Gantt and
PERT Charts
Gantt
Visually shows
duration of tasks
Visually shows time
overlap between
tasks
Visually shows slack
time
PERT
Visually shows
dependencies
between tasks
Visually shows which
tasks can be done in
parallel
Shows slack time by
data in rectangles
Gantt and PERT Charts
Steps
1. Identify each activity
2. Determine time estimates and expected
completion times for each activity.
3. Determine sequence of activities
4. Determine critical path
Estimated Time Calculations
Sequence of Activities
Critical Path Activities
Early Finish Te
Sum ET from left to right
Use max if the activity has more than 1
predecessor
Late Finish Tl
Subtract ET from right to left
Use min if the activity has more than 1 successor
Slack time = Tl-Te
On Critical Path if Slack Time = 0
Critical Paths
Time Estimation
Planning – 15%
Analysis – 20%
Design – 35%
Implementation – 30%
Trade-offs
Size
Effort
Time
Planning the Project
5. Develop a communication plan
Outline communication processes among
customers, team members and management
Types of reports
Frequency of reports
6. Determine project standards and procedures
Specify how deliverables are tested and
produced
Communication Methods
(Uses)
Project Workbook (Permanent record)
Meetings (Resolve issues)
Seminars and Workshops (Inform)
Project Newsletters (Inform)
Status Reports (Inform)
Specification Documents (Permanent record)
Minutes of Meetings (Permanent record)
Bulletin Boards (Inform)
Memos (Inform)
Brown–Bag Lunches (Inform)
Hallway Discussions (Resolve Issues)
Planning the Project
7. Identify and assess risk
Identify sources of risk
Estimate consequences of risk
8. Create a preliminary budget
9. Develop a statement of work
Describe what the project will deliver
10.Set a baseline project plan
Estimate of project’s tasks and resources
Executing the Project
1. Execute baseline project plan
Acquire and assign resources
Train new team members
Keep project on schedule
2. Monitor project progress
Adjust resources, budget and/or activities
Executing the Project
3. Manage changes to baseline project
plan
Slipped completion dates
Changes in personnel
New activities
4. Maintain project workbook
5. Communicate project status
Closing Down the Project
1. Termination
Types of termination
Natural
Unnatural
Requirements have been met
Project stopped
Documentation
Personnel Appraisal
Closing Down the Project
2. Conduct post-project reviews
Determine strengths and weaknesses of
Project deliverables
Project management process
Development process
3. Close customer contract
Commercial Project
Management Software
Many systems are available
Three activities required to use:
Establish project start or end date
Enter tasks and assign task relationships
Select scheduling method to review project
reports