TESA PROJECT ~ Facility Specifications

advertisement

Emergency Management Strategies:

Lessons Learned in Developing

Specifications, Procuring, Housing and Maintaining a 100-Bed Mobile

Hospital

Jenny Atas MD

Associate Professor

Wayne State University

Medical Director

Region 2 South Medical

Bio-Defense Network

Mark Sparks

Logistics/Planning Officer

Region 2 South Medical

Bio-Defense Network

1

Presentation Overview

Project Background

Acquisition Process and Specifications

Durable and Non-Durable Equipment

Acquisition Process

Storage & Deployment Considerations

2

PROJECT

BACKGROUND

~ Organization ~

3

Project Background ~ Organization

Pre 9-11: District Organization

8 Emergency Management

Districts covering 83

Counties

45 Public Health

Departments

65 Medical Control

Authorities (oversight of pre-hospital system) with no seat at the table

4

Project Background ~ Organization

Post 9-11: New Paradigm of Planning

Emergency

Management

Public

Health

Health

Care

5

Project Background ~ Organization

Post 9-11: HHS Grant Programs

HRSA

(now HHS

ASPR)

CDC

Medical Control Authorities

Hospital/Pre-hospital

Local Health Departments

Other Local/Regional

Partners

Coordinated State/Local/Regional Planning

6

Project Background - Organization

Post 9-11: Regional Organization

8 Medical Bio-Defense Regions

Mirror of 8 E.M. Districts

Incorporates 65 MCAs

Bioterrorism Coordinator

Medical Director

Emergency Preparedness Coordinator

(Local Health Department)

Epidemiologist

SNS Technical Advisor

Seat at the table

7

Project Background ~ Organization

Region 2 South (R2S) Overview

3 Counties; 97 local political jurisdictions; 2.6 million people

14 P.A. 390 Emergency Management/Homeland Security

Programs ( 4 with Public Health authority)

6 Public safety mutual aid organizations

4 Public Health Authorities

4 Medical Control Authorities

37 Hospitals

69 Fire/EMS agencies

11 Private/EMS agencies

8

Project Background ~ Organization

Lessons Learned

Regional Partnership with Emergency

Management is Critical

Development of surge plans, procedures and resources must involve all disciplines

Take full advantage in the ability to leverage other federal funding streams (restrictions / allowances)

Allows you to mitigate duplication of effort on all fronts

9

PROJECT

BACKGROUND

~ Foundation ~

DHHS NBHPP Program Guidance for Fiscal 2006 dictates that states have the ability to surge outside hospitals and healthcare systems

10

Project Background ~ Foundation

Situation

Hospitals in Michigan have incorporated the ability to surge 20% above the average daily census.

Even with these additional 7,000 beds there still exists insufficient surge response capability to address the needs that a medium level pandemic

MEMS remains the primary method of addressing

Medical Surge Capacity and Capability (MSCC)

Hurricane Katrina demonstrated the utility of surge facilities

11

Project Background ~ Foundation

Situation

Pandemic Flu

Outbreak of a moderately severe pandemic flu would exhaust surge capacity within the first two weeks

Natural and Man-Made Disasters

Trauma victims immediately exhaust surge capacity

Non-urgent health problems are exacerbated and further increase healthcare demands

Local Healthcare Emergencies

International air-traveler quarantine

2003 SARS: 3,017,496 international passengers thru DTW

“All hazards” response capability

12

Project Background ~ Foundation

Situation

In light of these factors a decision was made to utilize HRSA/ASPR funding to develop two self-contained all-weather mobile field hospitals or “surge facilities”

Initially develop and equip a 100-bed unit

Lay the groundwork

Based on available funding, develop a 50-bed unit

Extension of 100-bed unit

Rapid acquisition; rely on established specifications

13

Project Background ~ Foundation

Patient and Staff Planning Assumptions

The Mobile Field Hospital would be designed…

For patients suffering from COPD, asthma, congestive heart failure (no C-PAP or vent), chronic pain syndrome, and behavioral conditions, and needing IV hydration and IV antibiotic therapy

With a 4:1 ratio of adult to pediatric patients

With a planned admission/discharge rate of 23 hours

To be operated by a core team of medical professionals augmented by volunteers (Michigan Volunteer Registry)

14

Project Background ~ Foundation

Lessons Learned

Don’t recreate the wheel

Patient profile from the Katrina disaster experience

Patient demographics from Michigan Census

Staff profile from existing Michigan plans for

Alternate Care Facilities/MEMS Model

15

Transportable Emergency

Surge Assistance Medical

Unit

( TESA)

~ Facility Acquisition Process ~

16

TESA Project ~ Facility Acquisition Process

Grant Application

Region 2 South was selected to develop the 100-Bed

TESA Unit

The project was outlined in Region 2 South’s FY 06-07

HRSA Grant Application

Statewide resource ; housed in S.E. Michigan and operated by “strike teams” from across the state

Complete project within the grant year

Establish a Task Force to:

Research the different platforms and associated planning, operational, administrative and logistical considerations

Recommend how to best configure and develop the facility within budgetary constraints

17

TESA Project ~ Facility Acquisition Process

Grant Approval / Initial Steps

Project was approved; $1,000,000 budget

Task Force formed in October 2006.

Agencies represented:

Region 2 South Medical Bio-Defense Network

Michigan Department of Community Health, Office of

Public Health Preparedness

Michigan Department of State Police, Emergency

Management/Homeland Security Division

Michigan-1 Disaster Medical Assistance Team

18

TESA Project - Facility Acquisition Process

Task Force Determinations

The recommended basic platform for the facility would be a “soft-walled” shelter structure.

To account for cost uncertainties, the platform

(and invitation to submit proposals) would be designed around:

A core 50-bed facility (to include areas for triage, supply, admin, and staff support)

25-bed add-on patient wards .

19

TESA Project - Facility Acquisition Process

Task Force Requirements

Basic Requirements for the 50-Bed Core

Separate staff and patient entrances

Separate areas for facility administration, facility supplies, staff lounge and staff hygiene, and patient care wards a. Staff hygiene must have a changing area, sink, shower and toilet, cold and hot water, an on-board potable water supply with a water distribution system and a gray water containment system

Each patient ward must be equipped with a private field toilet (the Brief Relief TM system, or equivalent)

20

TESA Project – Facility Acquisition Process

Task Force Requirements

Basic Requirements for the Entire Shelter System

Completely self-contained

Trailer-mounted generators

Maximum component size (98”w, 50”d, 50”h)

Man-portable components (maximum 75lb per worker)

Rapidly erected without the use of tools or equipment

Must provide all-weather climate controlled environment

Materials must meet NFPA Standards

Must be interoperable with existing FEMA-NDMS assets

21

TESA Project - Facility Acquisition Process

Task Force Determinations

Proposal/Bid Quotation Requirements

Must provide a comprehensive description of:

Proposed system components

Warranties, manuals, parts availability guarantees

Where requirements are met or exceeded

Where requirements are not met and why a variance should be considered

How it will be packaged w/container dimensions

Must include diagrams (50-bed core, 75-bed and 100bed configurations)

Must identify single POC for notices and inquires

Must be submitted by e-mail (formatted in MS Word and Adobe PDF.

22

TESA Project - Facility Acquisition Process

Task Force Determinations

Parameters established to select potential shelter sources:

Identify potential sources known by the Task Force to manufacture shelters that

Generally met platform requirements

Were in common use as mobile medical facilities

To maximize practical competition, limit the minimum number of potential sources to 3

To minimize the procurement process, limit the maximum number of potential sources to 6

23

TESA Project - Facility Acquisition Process

Task Force Determinations

Six potential platform sources were identified

4 that generally met shelter requirements and had been used by members of the Task Force

1 that generally met shelter requirements but was unknown to members of the Task Force

1 that manufactured “hard-walled” shelters, was unknown to members of the Task Force but was a Michigan-based company

These 6 potential vendors were e-mailed the

Invitation to Submit a Combined Proposal/Bid

Quotation

24

TESA Project - Facility Acquisition Process

The RFP/RFQ Package

Task Force determinations were reduced to a

3-page invitation to submit a combined

Proposal/Bid

Quotation…

…that would be e-mailed to preselected vendors.

25

TESA Project - Facility Acquisition Process

The RFP/RFQ Package

Task Force determinations were reduced to a

3-page invitation to submit a combined

Proposal/Bid

Quotation…

…that would be e-mailed to preselected vendors.

26

TESA Project - Facility Acquisition Process

Evaluating Proposals/Quotes

All invitees responded

Hundreds of pages

Each with unique format

Some highly detailed and well organized

Some lacked detail and organization

All were printed, bound and distributed to each member of the Task

Force

Vendor 1

Vendor 2

Vendor 3

Vendor 4

Vendor 5

TESA Project - Facility Acquisition Process

Evaluating Proposals/Quotes

COMPARABLES

Quote Duration

Cost

Max Size Container

Assembly

# Basic Units

Access Doors

Area (sq. ft.)

Furniture

Power

Lighting

Outlets

HVAC

NDMS Interop?

Trailer Boot

Warranty

Framing

Fabric

Insulation

Hygiene Center

Flooring

Training

Vendor 1 Vendor 2 Vendor 3 Vendor 4 Vendor 5 Vendor 6

THE EVALUATION MATRIX

28

TESA Project - Facility Acquisition Process

Awarding the Contract

2 vendor’s RFP/RFQ met specs, the other 4 were eliminated from competition

Task Force members to NDMS conference to inspect both shelter systems

Gained experience - revised specifications

Requested final quote on revised specifications

Reviewed final quotes

Unanimous agreement to award contract

29

TESA Project - Facility Acquisition Process

Lessons Learned

Need experienced and knowledgeable team to avoid pitfalls when expediting a complex project

Need comparison matrix to efficiently deal with variable specifications

No substitute for getting your hands dirty

(in-person inspection and assembly)

No substitute for face-to-face discussion with vendor representatives

30

TESA

PROJECT

~

Facility Specifications ~

31

TESA Project – Facility Specifications

Quick Specs

10,000 Sq. Ft. Enclosed

Area

20,000 Sq. Ft. Footprint

(125’ x 158’)

5 Generators (4 @ 36kW and 1 @ 56 kW)

16 HVAC

15 @ 42K BTU heat/3.5 ton cool/29K heat strip

1 @ 60K BTU heat/cool/HEPA positive or negative pressure)

4 Hygiene Centers

Each with sink, shower, toilet, hot H

2

O, 500-gallon fresh and gray water holding tanks

16 Interconnected Shelters

1 each for Administration,

Staff, Supply (w/boot) and

Intake/Triage/Treat

1 ten-bed Patient Ward

(isolation)

7 ten-bed Patient Wards

4 five-bed Patient Wards

Design

4:1 ratio of adult to pediatric patients

Admit/Discharge Rate: 23 hours (= 100 patients per day)

Over

Pieces

1,000

Separate

32

TESA Project – Facility Specifications

The Design

33

TESA Project – Facility Specifications

Tactical Labeling

The components of each individual shelter are:

Color-coded & labeled

Packaged together

34

TESA Project - Facility Specifications

Tactical Storage

35

TESA Project – Facility Specifications

As Built (40-Bed Unit)

36

TESA Project – Facility Specifications

Lessons Learned

Color-code and label individual shelter components

Facilitates handling

Has limitations

Only so many distinct colors

Correlates only to complete 100-bed layout

Because it is a white vinyl tent labor intensive for cleaning before repackaging

Setup and tear down takes expertise

Requires the development of specialized teams

37

TESA

PROJECT

~ Equipment & Supply Acquisition~

38

TESA Project ~ Equipment/Supply Acquisition Process

Patient & Staff Profile

The Mobile Field Hospital would be designed…

For patients suffering from COPD, asthma, congestive heart failure (no C-PAP or vent), chronic pain syndrome, and behavioral conditions, and needing IV hydration and IV antibiotic therapy

With a 4:1 ratio of adult to pediatric patients

With a planned admission/discharge rate of 23 hours

To be operated by a core team of medical professionals augmented by volunteers (Michigan Volunteer Registry)

39

TESA Project ~ Equipment/Supply Acquisition Process

Task Force Determinations

The stakeholder Task Force determined to utilize solesource provider of medical supplies and equipment to outfit the facility

Previously qualified source

Current source of ACC and NEHC facilities for MEMS components.

Demonstrated ability

Medical expertise to identify and meet needs (based on expected patients and healthcare staff)

Professional packaging

Competitive pricing

40

TESA Project ~ Equipment/Supply Acquisition Process

Patient Profile Questionnaire

Comprehensive questionnaire was used to refine the patient profile and then determine what level of service would be provided over a given period of time

41

TESA Project ~ Equipment/Supply Acquisition Process

Capability Worksheet

Function (sample)

Airway

Wound Treatment

IV Therapy

Ortho Care

EENT

Genitourinary

Gastrointestinal

Medication Admin

Emergency Care

X

X

X

X

X

Adult PEDS Infant

X X X

X X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

42

TESA Project ~ Equipment/Supply Acquisition Process

Master Template

Master Template was used to generate the type of treatment which could be offered and the type and quantity of equipment and supplies needed.

43

TESA Project – Equipment/Supply Acquisition Process

The Design

44

TESA Project – Equipment/Supply Acquisition Process

The Design

45

TESA Project – Equipment/Supply Acquisition Process

The Design

46

TESA Project – Equipment/Supply Acquisition Process

The Design

47

TESA Project – Equipment/Supply Acquisition Process

The Design

48

TESA Project – Equipment/Supply Acquisition Process

The Design

49

TESA Project – Equipment/Supply Acquisition Process

The Design

50

TESA Project – Equipment/Supply Acquisition Process

The Design

51

TESA Project ~ Equipment/Supply Acquisition Process

Lessons Learned

Patient Profiles will define the treatment modalities necessary

Establish a cache which is broadly used so that replenishment is easier and can be integrated into a local healthcare system

Establish Augmentation Sets to supplement specialty areas

OB-GYN

PEDS

Isolation

O2 Therapy

Nursery

Establish and procure basic equipment lists which do not require long training sessions

52

TESA

PROJECT

~ Storage & Deployment

Considerations ~

MAXIMIZE

DEPLOYMENT AND RECOVERY

SPEED

53

TESA Project ~ Storage/Deployment Considerations

Tactical Containerization & Labeling

Color-coded labels

Color-coded packages

Color-coded containers and augmentation sets

Modules which are color-coded and containerized

54

TESA Project ~ Storage/Deployment Considerations

Containers

Storage

Pallet size

Weight

Deployment

On or off pallets?

Storage of shipping materials

Re-packing

Sustainment

COT RACKS

HEPA HVAC

HVAC UNIT

55

TESA Project ~ Storage/Deployment Considerations

Transporting & Handling

Transport Vehicle

Semi-trailers

Flat bed

Dry box

Box truck

FLAT BED SEMI-TRAILER

Material Handling

Equipment

Fork Lifts

CONSTRUCTION

HI-LO

Pallet Jacks

BOX TRUCK

56

TESA Project ~ Storage/Deployment Considerations

Trailer-Mounted Generators

Shipping

Flat Bed - loading & unloading

Need loading dock

Need material handling equipment

Individual

Multi tow-vehicles and drivers

SHIPPING GEN-SETS

GEN-SETS IN STORAGE

57

TESA Project ~ Storage/Deployment Considerations

Storage Space

58

TESA Project ~ Storage/Deployment Considerations

Storage Scheme

59

TESA Project ~ Storage/Deployment Considerations

Lessons Learned

Color-coding simplifies storage, “picking”, shipping and sustainment planning and execution

Consider the storage of shipping materials

(pallets, containers, etc.) in deployment plans

Know your material handling equipment needs

Field (e.g. parking lot) vs. fixed facility (e.g. conference/exhibition center)

60

Emergency Management Strategies:

Lessons Learned in Developing Specifications, Procuring,

Housing and Maintaining a 100-Bed Mobile Hospital

Jenny Atas MD

R2S Medical Director e-mail: jatas@2south.org

Mark Sparks

R2S Planning & Logistics Officer e-mail: msparks@2south.org

61

Download