Maryland Government Building Penn State AE Senior Capstone Project Andrew R. Pino | Construction Management Option Advisor | Dr. John Messner Maryland Government Building I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery Methods I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Concrete Formwork I. Potential Replacements & Chosen Formwork System II. Structural Breadth III. Cost and Schedule Impact Analysis V. Analysis 3 | Terra Cotta Rain Screen Pre-fabrication I. Research and Feasibility II. Cost and Schedule Comparisons III. Mechanical Breadth and Conclusion VI. Conclusions and Recommendations VII. Acknowledgements Number of Stories | 10 Contract Value | $75 million Estimated Cost-to-Date | $100 million Dates of Construction | Jan 16, 2012 – Dec 2, 2013 Occupancy Type | Office (Type B) CM at Risk | The James G. Davis Construction Corp. Maryland Government Building Andrew Pino | AE Senior Thesis | Construction Management Option Project Size | 520,000 SF (200,000 SF Parking Garage) Owner/Developer | The JBG Companies Architect | HOK Government Building Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Maryland Existing Site Plan Andrew Pino | AE Senior Thesis | Construction Management Option Construction Site Plan Site Logistics Plan - Structure Government Building Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Maryland Project Features Concrete batch plant Post-tensioned concrete Terra cotta rain screen Pursuing LEED Silver Andrew Pino | AE Senior Thesis | Construction Management Option Concrete Batch Plant Post-Tension Cables Government Building Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Andrew Pino | AE Senior Thesis | Construction Management Option Maryland Analysis #1 | Integrated Delivery Methods Problem Statement: Traditional design-bid-build delivery methods have the potential to hinder the design change approval process. Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Overview Maryland The JBG Companies Owner/Developer GSA VIKA Civil Engineer HOK Architect DAVIS Construction CM at Risk Tadjer-Cohen-Edelson Structural Engineer Miller & Long Concrete W.E. Bowers Mechanical GHT Limited MEP Engineer FB Harding Electrical American Automatic Fire Protection/Sprinkler ARUP Fire Protection Consultant Miscellaneous Metals Metal Fabrication C.J. Coakley Terra Cotta MCLA Lighting Designer Deneau Utilities Tidewater Glass and Glazing Polysonics Corp. Acoustics Consultant GMP Contract Prime Contract Lump Sum Contract Communication Owner A/E CM Subs Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Government Building Case Studies Maryland Case Study #1 Case Study #2 Project comparison Survey of 200+ industry professionals Success Criteria Common Themes Teams Processes Risk Reward Communication Documentation Agreements Andrew Pino | AE Senior Thesis | Construction Management Option Meeting client’s criteria Budget and schedule met Reduction in disputes Overall quality Success Factors Unit cost fluctuations greater with D/B D/B - 185 percentage points D/B/B – 102 percentage points Lower D/B labor cost percentage Early contractor involvement is critical Clearly defined scope Good relationships Contractor experience End user’s early input Client participation Survey Results Time/schedule Cost Quality Functionality Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Application to Project Targeted Benefits Early contributions to design Reduced design conflicts and RFI’s Improved schedule management Reduced design documentation time Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Maryland Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Conclusion Maryland Recommended Structure Integrated Project Delivery Method True IPD offers highest level of integration Individual success tied directly to project success Single multi-party contract not appropriate Design/Build Delivery Method Benefits of integration without single contract Co-location of major entities Reduces layers of design change approval Early contractor involvement Full integration not present Design/build GSA Client The JBG Companies Owner/Developer Design/Build Team Architect, engineers, consultants and CM Subcontractors and Suppliers Government Building Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Andrew Pino | AE Senior Thesis | Construction Management Option Maryland Analysis #2 | Modular Concrete Formwork Problem Statement: Wood panel post-and-beam formwork is labor intensive and time consuming. Presentation Outline Formwork Systems Maryland Lightweight Adaptable Complex components Desired Benefits Rapid reuse cycle Mobility Andrew Pino | AE Senior Thesis | Construction Management Option Lightweight Drop heads Fewer props Simple components Plywood table panels DoKart required Dokamatic Table Lightweight materials Aluma Dek Simple components Peri Sky Deck I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Government Building Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Government Building Structural Breadth Maryland Purpose | Redesign to a Flat Slab System Largest Column Span Andrew Pino | AE Senior Thesis | Construction Management Option Relocated and Added Columns Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Government Building Structural Breadth Maryland ACI Deflection Check h > ln / 33 = (30 ft * 12) / 33 = 10.9 in Minimum slab thickness of 11 in 12 in slab thickness chosen Parameters Deflection & Punching Shear ACI Punching Shear Check ACI 318-11 for calculations Two-way slab w/o drop panels Max span of 30 ft Andrew Pino | AE Senior Thesis | Construction Management Option Column of Highest Concern Actual shear = Vu = qu*AT = (640 SF) * (352 psf) = 225,280 lb Allowable shear = 4*1*√(f’c)*bo1*d1 = 4*1*√(5000)*144in*(12in-0.75in) = 458,205 lb Vu < 0.75*Vc1 225,280 < 0.75 * 458,205 225,280 lb < 343,654 lb, punching shear is acceptable Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Government Building Cost Analysis Maryland Existing System Costs Redesigned System Costs Assumptions RSMeans labor costs 65% labor reduction Equipment cost +20% Cost savings calculated for single floor Andrew Pino | AE Senior Thesis | Construction Management Option Material (62%) Material (80%) Labor (35%) Equipment (3%) Labor (15%) Equipment (5%) Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Government Building Schedule Analysis and Conclusion Subsequent Cost Savings Schedule Savings 25% increase in productivity 2-3 day reduction per floor 20-30 day total reduction Critical path time savings Andrew Pino | AE Senior Thesis | Construction Management Option Roughly four week schedule reduction $48,058 per-week general conditions costs Significant cost savings Maryland Conclusion Concrete redesign enables ideal use of modular formwork Peri Sky Deck offers significant cost and time savings Labor savings outweigh added material costs Schedule reduction applies to the critical path Government Building Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Andrew Pino | AE Senior Thesis | Construction Management Option Maryland Analysis #3 | Terra Cotta Rain Screen Pre-Fabrication Problem Statement: The construction of the terra cotta rain screen is complex, involving four layers to be installed consecutively. Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Government Building Overview of Systems Maryland Current Rain Screen Design Components Risk Factors Metal CM Sheathing with z-girts Complex process Insulation Rain Screen Trades Architect Labor intensive Glazing Support profile Time consuming Andrew Pino | AE Senior Thesis | Construction Management Option Terra cotta panels Terra Cotta Air / Vapor Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Overview of Systems Current Installation Process Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Maryland Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Overview of Systems Proposed Panel Layout Panel Sizing Width: 10’-0”– 17’-6” Height: 10’-0”– 26’-9” Total number of panels: 208 Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Maryland Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Cost Analysis Government Building Schedule Analysis Maryland Façade Breakdown Precast Concrete: 49,000 SF Unitized Terra Cotta Panel Installation Schedule Terra Cotta: 22,000 SF Glazing: 73,500 SF Cost Estimate Data Total Building: 144,500 SF Andrew Pino | AE Senior Thesis | Construction Management Option Glazing and terra cotta scopes combined under unitized system Precast concrete excluded as it does not change Square-foot cost data provided by DAVIS and others Original Sept Unitized Oct Nov Dec Jan Feb Mar Apr Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Mechanical Breadth Conclusion Breadth Results Relative humidity between layers never exceeds 100% Condensation will not occur in this assembly A unitized panel system would: Breadth Assumptions Interior: RH = 40% T = 28 C (82 K Exterior: RH = 80% T = -15 C (5 K Andrew Pino | AE Senior Thesis | Construction Management Option F) = 297 F) = 258 Create a streamlined process Reduce terra cotta installation duration by roughly three weeks Mitigate risk of labor and weather variables Produce a higher quality end product Cost an additional $1,458,996 Government Building Maryland Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Final Recommendations Maryland Analysis #1 | Integrated Delivery Methods Design/build better facilitates the design change approval process Co-location of major entities offers ease of communication Early contractor involvement is critical Analysis #2 | Modular Concrete Formwork Concrete redesign enables ideal use of the Peri Sky Deck Schedule reduction of one month Applies to the critical path Total cost savings of $437,974 Analysis #3 | Terra Cotta Rain Screen Pre-Fabrication Three week schedule reduction Additional cost of $1,458,996 More streamlined installation process Factory assembly means improved quality control Original Sept Unitized Oct Nov Dec Jan Feb Mar Apr Presentation Outline I. Introduction II. Project Background I. Site Overview II. Project Features III. Analysis 1 | Integrated Delivery I. Overview & Case Studies II. Application to Project III. Conclusion IV. Analysis 2 | Modular Formwork I. Formwork Systems II. Structural Breadth III. Cost and Schedule V. Analysis 3 | Terra Cotta I. Overview of Systems II. Cost and Schedule III. Mechanical Breadth VI. Conclusions and Recommendations VII. Acknowledgements Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Acknowledgements Maryland Academic Acknowledgements Penn State Architectural Engineering Faculty Dr. John Messner – CM Advisor Ray Sowers – CM Advisor Dr. Linda Hanagan – Structural Advisor Industry Acknowledgements Special Thanks The DAVIS Construction Project Team Tyler Moyer – DAVIS Project Manager David Gibbons III – DAVIS Senior Project Manager Leaha Martynuska – DAVIS Project Manager PACE Industry Members Family and Friends Questions Andrew Pino | AE Senior Thesis | Construction Management Option Government Building Maryland