Construction Phase
PROJECT LIMITS
Cypress Point Parkway to Florida Park Drive ~ 1.23 miles
Community Development
Department
PROJECT BENEFITS
• Reduce congestion (increase level of service and reduced travel
times).
• Improve safety for vehicles and pedestrians as well as potential
for accidents.
• Improve mobility for emergency vehicles.
• Improve westward hurricane evacuation operations.
• Provide an 8-foot sidewalk along the roadway and bridge in both
directions to accommodate pedestrians and bicyclists.
• Provide dedicated turn lanes.
• Provide concurrent left turns at Cypress Point Intersection and
Old Kings Road.
• Extension of street lighting.
• Enhanced Landscaping and conversion of irrigation to re-use.
Community Development
Department
TREE RELOCATION
Indian Trails Sports Complex
Waterfront Park
Community Development
Department
PROJECT DEVELOPMENT PROCESS
• Construction Phase: 2014 - 2015
 FDOT has allocated funding for the construction phase in
the current fiscal year budget.
 Agreements for this Phase have been executed.
 Interlocal between City & County.
 FDOT LAP Agreement between County & FDOT
 Supplemental FDOT LAP Agreement pending
approval & execution. (scheduled for County
Commission Meeting on 12/16/2013.
 Construction to begin early 2014 and to be completed
by the end of 2015.
City of Palm Coast
2014 Capital Projects Timeline
10/8/2013
Streets Improvement Fund
1st Quarter
Project Name
2nd Quarter
December 2013
3rd Quarter
March 2014
4th Quarter
June 2014
September 2014
Palm Coast Parkway Six-Lane
Construction
Community Development
Department
CITY COUNCIL ACTION
a) Construction Contract
 P&S Paving, Inc.
 Contingency
$10,556,445.42
$ 1,055,644.54
b) Construction Inspection (CEI) Contract
 Hill International, Inc.
 Contingency
$ 1,180,197.00
$
118,019.00
c) Post-Design Services Change Order
 DRMP Engineers
$
160,691.00
d) FPL Street Light Agreements
 Relocation Agreement
 Street Light Agreement
$
$
114,139.00
385,864.00
Community Development
Department
CONSTRUCTION PHASE FUNDING
FDOT
Budget:$10,328,232
Actual: $10,328,232
TOTAL:
CITY - UTILITY FUND
Budget: $1,000,000
Actual: $1,000,000
Budget:
$13,788,058
Actual
$13,570,997
CITY - STREET IMP. FUND
Budget: $2,459,738
Actual: $2,242,679
Community Development
Department