6 Connecting generators to the distribution network Although distributed generation can have many advantages, it does not always easily fit into today’s centralised power systems. Even if overall benefits are positive, additional network costs can discourage distribution network service providers (DNSPs) from connecting a distributed generator. It is therefore not surprising that the most commonly raised immediate barrier to greater adoption of medium-scale distributed generation is the process for connecting these systems to the electricity network. Distributed generators require access to distribution networks for a range of reasons including selling electricity and balancing system loads (ClimateWorks et al. 2011, p.9). Connecting distributed generation is of particular interest to this inquiry because the connection processes and costs can have significant impacts on the efficiency and viability of medium-scale distributed generation projects. Connection barriers relate to connection costs (chapter 5) and the connection process (this chapter and chapter 7). Efficient connection would mean DNSPs have incentives to remove artificial barriers to entry, with efficient costs, timing and risk allocation. Material barriers to connection can be addressed at two levels: (1) The connection process: the Commission considers there are clear barriers in the connection process that could be ameliorated now. These changes are necessary, would improve competition between distributed generation and other options for achieving the National Electricity Objective (NEO), and increase the efficient use of distributed generation. These important barriers are the primary focus for this chapter and chapter 7. (2) DNSPs’ incentives to plan and manage the system to make efficient use of distributed generation: many participants argued that addressing the connection process alone will not be sufficient to guarantee efficient use of distributed generation. The Commission considers that some of these DNSP incentive issues are longer term in nature, but that they have a strong impact on the barriers to distributed generation. The Commission examines these barriers, recommends some more immediate actions and identifies areas where longer term action may be needed in chapter 5. Such connection barriers indicate a probable underinvestment in distributed generation in Victoria, primarily at the medium-scale where the connection barriers are more significant. The terms of reference of the inquiry ask the Commission to identify barriers to distributed renewable and low emissions generation in Victoria, including co-generation and tri-generation. This chapter and chapter 7 examine barriers in the connection process for medium-scale and ‘household-scale’1 distributed generation respectively. Each has different connection processes, the proponents have differing capacity to deal with DNSPs, and scale creates different kinds of network impacts. This chapter first sets out, in section 6.1, the regulatory context along with work currently underway to address connection barriers. Section 6.2 describes the benefits of medium-scale generation and section 6.3 summarises participants’ views on barriers to ‘Household-scale’ includes small-scale distributed generators owned by small business and community groups. 1 CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 87 connecting. The right to connect and export (section 6.4) and the connection process (section 6.5) are analysed in more detail, followed by section 6.6 which discusses the impact of implementing the Commission’s recommendations. 6.1 Context Connection of distributed generation is regulated by national and state arrangements. The national connection arrangements outlined in section 2.2.3 and appendix B include the connection elements of the COAG principles for feed-in-tariffs, chapter 5 and 5A of the National Electricity Rules (NER) and the National Customer Energy Framework (NECF). Chapter 5A of the NER provides basic, standard and negotiated connection services. The NECF and chapter 5A are not implemented in Victoria and the implementation date has not yet been announced. In 2009, the Australian Energy Market Commission (AEMC) conducted a Review of Energy Market Frameworks in Light of Climate Change Policies. The AEMC concluded that regulatory barriers prevent the efficient connection of distributed generators and that addressing these barriers is likely to further the National Electricity Objective (NEO) (AEMC 2009c, p.76). Many actions have been implemented or initiated to address these barriers (table 6.1). After the introduction of the NECF in Victoria, those seeking medium-scale connection will follow the process illustrated in figure 6.1. Prior to implementing the NECF in Victoria, connection is governed by chapter 5 of the NER, and supplemented by Victorian regulations including Electricity Industry Guideline No. 15: Connection of Embedded Generation (ESC 2004a), the Electricity Distribution Code (ESC 2012a) and distribution licences). Chapter 2 and section 6.4 describe the regulatory context in more detail. 88 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Table 6.1 Actions to address barriers to distributed generator connection Date Action Details July 2010 AEMO Small Generator Framework Design Sets out principles to minimise barriers to cost-effective participation by small generators in the NEM July 2011 AEMC responded to proposal by Minister for Energy and Resources (Victoria) on Total Factor Productivity (TFP) in network pricing regulation Aimed to improve incentives for DNSPs to invest more efficiently. AEMC concluded the TFP approach has merit but practical implementation issues exist December 2011 Distributed generators included in the Demand Management Incentive Scheme (DMIS) The AEMC completed a rule change process to include distributed generation in the DMIS June 2012 Proposal to the AEMC to amend the NER for connecting embedded generators ClimateWorks, Seed and the PCA proposal to streamline connection processes and improve DNSP incentives for engagement April 2012 AEMC published draft determination on rule change proposed by MCE on Distribution Network Planning and Expansion Framework Main components are an annual planning and reporting process, a Demand Side Engagement Strategy, and a Regulatory Investment Test for Distribution (RIT-D) June 2012 AER published guidelines on connection charges Provides guidance on connection charges under the new chapter 5A September 2012 Final AEMC Demand Side Participation (DSP) Report: The Power of Choice Aims to improve opportunities for DSP September 2012 Outcome of AEMO Small Generator Aggregator Framework rule change request to AEMC Aims to simplify registration of distributed generators April 2013 Final report of Productivity Commission inquiry into electricity network regulation Seeks, among other things, to address barriers to distributed generation To be determined Commencement of Chapter 5A of the NER in Victoria Expands the NER for connection of household and medium-scale distributed generation Notes: Australian Energy Market Operator (AEMO), Australian Energy Market Commission (AEMC), Clean Energy Council (CEC), Ministerial Council on Energy (MCE), National Electricity Market (NEM), Property Council of Australia (PCA). Source: Commission analysis. CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 89 Figure 6.1 Connection approval process for medium-scale distributed generator retail customers (with NECF) Preliminary inquiry from potential applicant wishing to connect DNSP has 5 days to provide information Applicant lodges application on form determined by DNSP Application incomplete Additional information required DNSP informs applicant of additional information needed DNSP informs applicant of deficiency Application complete Completed application submitted Site visit, if needed Not approved service. DNSP notifies applicant of the negotiation process & possible changes & expenses DNSP uses best endeavours to make offer within 65 days of receiving completed application* Offer open for 20 days Agree d Offer terms form connection contract * This applies to negotiation, not dispute resolution DNSP has 10 days to advise whether the service is covered by an approved connection process and, if so, make a connection offer offer open for 45 days expedited connection may be available Basic connection service or standard connection service Use agreement pre-approved by AER Negotiated connection offer Not agreed Option of dispute resolution through AER Legend AER – Australian Energy Regulator DNSP – Distributed Network Service Provider Source: Commission analysis. 90 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION 6.2 Benefits of medium-scale distributed generation Depending on location and operation, medium-scale generators offer several advantages in network support and electricity supply to the owner and other parties in the electricity system: Greater potential for network savings at lower cost than small-scale renewables because of economies of scale. CSIRO estimates co- and tri-generation could provide nearly five times more peak generation capacity than local renewables at one sixth of the cost (Dunstan et al. 2011, pp.12, 68). With strong demand for green building office space, co-generation can contribute to national emissions reduction targets and improved green building ratings which improve rental returns for building owners (ClimateWorks et al. 2011, p.15). Low transaction costs with less than 100 medium- to large-scale plants making up 295 MW of installed capacity compared with around 50 000 small-scale PV installations making up around 75 MW of installed capacity in Victoria in 2010.2 Co- and tri-generation plants can switch on at full capacity or switch off unlike solar PV which cannot guarantee maximum production when the network is constrained and the electricity spot prices peak (Dunstan et al. 2011, p.74). The net benefits of medium-scale generation vary by location and operation, and achieving many of these benefits requires connection to the network. Many participants were concerned about significant barriers to connecting medium-scale generators. 6.3 Barriers to medium-scale distributed generation The Commission consulted with different stakeholder groups during the inquiry. Medium- scale connection barriers: proponent view A survey conducted by Senergy of connected distributed generators found a range of connection issues although the survey did not include the DNSPs (box 6.1). A separate survey conducted by Entura for Sustainability Victoria (SV) in 2010 found that: The majority of survey respondents and interviewees found their working relationship with the DNSP to be average or below normal expectations and believed that this resulted in longer project implementation times and increased costs. There is a clear relationship between the quality of the perceived working relationship with the DNSPs, and the number of grid connection problems faced, the technical requirements needed and the cost of grid connection (SV 2010, p.i). Despite the challenges, ‘there is generally a good success rate in connection to the grid’ (SV 2010, p.i). 2 Natural gas 133 MW, waste gas 45 MW, black liquor 55 MW, landfill gas 40 MW, sewage gas 22 MW (ESAA 2011, pp.20–21; CEC 2011a). CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 91 Box 6.1 Senergy report on distributed generation connection experiences Senergy surveyed distributed generator proponents after the connection process was completed. Distribution network service providers (DNSP) were not involved in the survey. The main concerns highlighted by respondents in the interface between the DNSP and the customer included: access to the appropriate DNSP representatives for connection related issues (e.g. legal and technical staff) excessive response times from DNSPs for apparently straight forward queries lack of transparency in, and understanding of, connection processes fear that accessing dispute resolution services would have a negative impact on a distributed generation project or even the proponent’s distributed generation project portfolio. In addition, even though the regulatory instruments define some aspects of the connection process, respondents said that DNSPs often fail to meet their obligations, including: inadequate and/or delayed connection enquiry responses insufficient detail provided on the DNSP’s management of the process or scheduling of connection related activities lack of commitment to firm delivery dates for connection offers, or to meet such milestones if they are committed to, and a lack of understanding of the importance of such milestones inadequate data provision (both in detail and timing) required to fully assess the commercial significance of a connection offer, despite the National Electricity Rules requiring this data to be provided not paying avoided use of system charges as required by the current legislation issues respondents raised about the negotiation process included: – – – – DNSPs using their information to advantage during the connection process unwillingness to negotiate terms in the offer and significant delays in responding to requests to reconsider terms, often leading to non-preferred agreement terms being signed due to external commercial pressures. These terms included open ended liability on the distributed generator not providing access to DNSP legal representatives insufficient information on cost estimates and work scopes for applicants to assess their fairness or reasonableness. Source: Senergy 2011, pp.3–4. Medium-scale connection barriers: DNSP view Connecting medium-scale distributed generation can also involve significant cost for DNSPs in understanding network capacity, reinforcing the network and responding to inquiries. As mentioned in Unlocking the Barriers to Cogeneration, currently the impact of a proposed distributed generation project on the network is unknown until both the DNSP and project proponent commit significant time and resources (ClimateWorks et al. 2011, p.24). Overcoming the technical barriers to connection can involve many millions of dollars of investment in the network (Senergy 2011, p.12) but DNSPs suggested there are no simple solutions to some of these problems (UE, sub. 77, p. 5). 92 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION DNSP participants recognised the potential benefits of distributed generation but raised concerns about the impact on their networks. CitiPower/Powercor ‘support the connection of distributed generation to their distribution systems, including wind farms, provided that these connections promote the National Electricity Objective and the Businesses’ safety obligations’ (sub. 80, attachment 1, p. 5). While knowledge varies considerably, the distributed generator proponents do not always have a good understanding of the connection process and requirements (Senergy 2011, p.19). In the Commission’s roundtables, the DNSPs indicated that they have a large number of distributed generation inquiries, not all of which have the resources and knowledge to follow through with a connection. Proponents may also be operating under some uncertainty: It is therefore likely that while negotiating with the DNSP, the project owner is also in negotiations with tenants or other stakeholders on the design of the building itself. They may not, therefore, be in a position to provide the DNSP with the required information for the connection application to proceed as the NER and the DNSPs currently require. (ClimateWorks et al. 2011, p.23) DNSPs acknowledge better communication with distributed generation proponents may help to improve proponents’ appreciation of connection challenges: UE understand that customers perceive these legitimate technical issues as a barrier to connection and we will be seeking to improve in this area. (sub. 77, p.5) There is also a barrier in the economic regulation in that DNSPs face uncertainty about whether they can receive a return on the cost of studies and time spent responding to distributed generator inquiries (AEMC 2012f, p.169). The Commission’s view Table 6.1 detailed several processes that are in progress or will be implemented to reduce the barriers to distributed generation connection. The proposed AEMC rule change by ClimateWorks, Seed and PCA could make significant progress in clarifying connection processes and rights (box 6.2). The Commission considers that all of the actions in table 6.1 will reduce connection barriers but some barriers will remain. The key issues and material barriers to medium-scale distributed generation identified by the Commission’s analysis and through submissions (chapter 3) are: information and planning on network capacity (chapter 5) sharing network costs, benefits and risks (chapter 5) regulatory incentives for efficient connection (chapter 5) right to connect and export (this chapter) process, timelines and uncertainty (this chapter). CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 93 Box 6.2 Proposal to amend the National Electricity Rules for connecting embedded generators On 18 April 2012, the AEMC received a rule change request from ClimateWorks Australia, Seed Advisory and the Property Council of Australia. The applicants argued that the National Electricity Rules (NER) deter distributed generators from connecting to the electricity grid, as the connection process is uncertain, complex, burdensome, time consuming, inefficient and costly. The application proposed that the NER be amended to: (1) Provide an automatic right of connection to the grid and standard access terms. This would apply to generators that meet ‘Automatic Access Standards’. (2) Enable embedded generators a right to export electricity to the grid. (3) Provide an improved connection process for embedded generators that are ineligible for automatic access and a right to export electricity to the grid. (4) Allow DNSPs to charge an optional fee-for-service. This is to promote collaboration with proponents during the connection process. (5) Oblige DNSPs to publish annual network reports identifying where capacity is limited. Source: ClimateWorks et al. 2012. 6.4 Right to connect and export Some proponents of distributed generation argued that there are network access barriers for medium-scale distributed generators caused by ambiguity around standards and no obligation on DNSPs to provide an automatic right to connect and export electricity. This contrasts with household-scale distributed generation, where systems that meet AS4777 can automatically connect through Guideline 15 and the Electricity Distribution Code (ESC 2012a) and there is an automatic right to export through the FiT regulations (provided FiT eligibility criteria are satisfied). Similarly, for large generators 30 MW or greater, network connection cannot be refused when they meet the automatic standards in Schedule 5.2 of the NER. An automatic connection and a right to negotiate export, subject to transmission network constraints, are granted under chapter 5 of the NER. The arrangements for medium-scale generators are not as clear. There is no automatic right to connect and in the draft report the Commission concluded DNSPs have discretion to set minimum technical standards. DNSPs have strong incentives to manage impacts on their network and weak incentives to reduce the cost of connection to distributed generators who must pay for costly network studies and network reinforcement. The AEMC concluded this arrangement is a key barrier to connecting distributed generation (AEMC 2009b, p.28). Many inquiry participants supported this view: As a priority, enabling automatic access for cogeneration systems up to 5MW should be immediately implemented because, relative to the size of their installation, the costs of connection and the current connection process are very high. (ClimateWorks et al. 2011, p. 36) 94 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Once connected to the network, medium-scale generators can face conditions on their connection agreement that prevent the export of electricity. A right to export would allow generators to separately negotiate a price with a retailer or other party, potentially subject to network constraints, as is the case on the transmission network. While improving these connection arrangements for medium-scale generators could present some challenges for DNSPs, the Commission considers that opportunities to improve the connection process while maintaining appropriate safeguards on the network should be explored. Opportunities for improvement An automatic right of connection and export based on a specific process and technical standards, as advocated by some participants, is one way to establish an equivalent connection process across all sizes of generation. In response to the draft report, however, the CEC stated that the technical standards have been defined in Electricity Distribution Code (EDC) and that this is not the source of barriers that other participants have claimed (CEC, sub. DR197, p. 18). The Commission assessed the clarity of technical standards for medium-scale distributed generators by looking at relevant State and national regulations. National minimum technical standards At the national level, there are no minimum technical standards for non-registered generators3 in the NERs. In theory the standard connection service that will be available to distributed generators when chapter 5A is introduced in Victoria would allow DNSPs to offer a standardised process and automatic connection with specific terms and conditions that could include minimum technical standards. United Energy (UE), however, stated it will not establish standard connection offers given the vast differences between connections: … there may be a perception that automatic access may be provided via the NECF standard connection offer contracts. UE has considered this approach and has not progressed contracts in this area due to the need to standardise the technical and cost arrangements in these contracts, nor do we believe that there is a high volume requirement in the UE distribution area. (sub. 77, p. 5) If standard connection services are not established through chapter 5A, at the national level, medium-scale distributed generators would be left to negotiate technical standards with the DNSPs through chapter 5 or chapter 5A of negotiated connection service. The general standards in chapter 5 does not apply to these smaller generators: Chapter 5 of the NER sets out the technical conditions for the connection of generators. However, these provisions do not apply to generating systems that are subject to, or eligible for, an exemption from registration. In the case where the Chapter 5 technical conditions do not apply, the technical requirements for a connection to the distribution network would be determined by the relevant distributor in accordance with jurisdictional and local network requirements. (AEMC 2012a, p.18) There is a standing exemption from registration for generators under 5 MW, which covers the majority of medium-scale distributed generators. 3 CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 95 Victorian minimum technical standards At the State level, clause 7 of the Electricity Distribution Code (EDC) details the technical standards for medium-scale embedded generators. These include obligations, mainly on the embedded generator, in relation to: supply frequency co-ordination and compliance of embedded generating units minimum requirements for embedded generating units negative sequence voltage harmonics inductive interference fault levels (ESC 2012a clauses 7.2 to 7.8). The Victorian Government intends to retain some Victorian-specific regulation relating to embedded generator connections after the NECF is applied in Victoria (DPI 2011n). While the CEC considered that the technical standards in the EDC are sufficient, other participants raised concerns. The EDC standards depend on information the DNSPs hold on network condition, DNSPs can set more stringent requirements, the EDC is not the only set of requirements, and there is minimal guidance on how the State requirements should apply. Limited information can make it difficult to determine whether a project meets the clause 7 requirements of the EDC. The Commission understands that fault levels are a key issue, given they are a strong driver of network reinforcement costs, medium-scale generators can contribute significantly to fault levels, and fault level ‘headroom’ is constrained in the Melbourne CBD where many developers wish to install medium-scale generators. The EDC states that fault levels should not exceed set standards. Some distributed generator proponents claimed that, with limited information available by location on network condition and planning for other customers, it is difficult to determine whether a distributed generator would exceed the fault levels in the EDC. In 2009, the fault levels at some locations were reportedly slightly higher than those expressed in clause 7.8 and action was being taken to address the issue (SKM 2009, p.4). Where fault levels are exceeded distributed generators will cause a breach of clause 7.8. Participants also mentioned the minimum technical requirements of the EDC have not been changed since 2006 and are out of date. Clause 7 of the EDC is not the only set of requirements which apply to medium-scale distributed generators. Entura, in its survey of distributed generators for SV, concluded it was the complexity and lack of clarity around which standards apply which confuses proponents: The problem is not that there aren’t specific requirements existing, it stems that there are many documents from different sources and the proponents struggle to identify if a requirement has precedence or which requirement is for their installation. (SV 2010, p.14) The AEMC noted that jurisdictional arrangements contain minimal guidance for DNSPs and embedded generators, giving DNSPs considerable discretion to set the minimum technical standards (AEMC 2009b, p.45). Distributed generator participants claimed DNSPs ‘gold plate’ network protection by mandating high levels of protection equipment for unlikely safety and reliability events. These participants also claimed the DNSPs show little flexibility to negotiate lower cost solutions to network protection. 96 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION These ambiguities present barriers to medium-scale distributed generators: [Proponents face] a need to renegotiate all technical requirements for an identical embedded generator by the same proponent, but in a different location. While some technical requirements will likely be location specific, there may be scope for some requirements to be standardised. (NERA 2008, p.37)4 Developing technical standards In the Demand Side Participation Stage 2 Review, the AEMC recommended reducing the barriers to connecting distributed generators. NERA Economic Consulting’s advice to the AEMC in that review was that ‘the barriers reflected mainly inexperience and a lack of operating procedures and standards to facilitate the connection of distributed generators’ and that there was potential to rebalance the discretion DNSPs have in setting minimum technical standards (NERA 2008, p.37). Accordingly the Demand Management Incentive Scheme was expanded to include embedded generators. The AEMC also recommended the reliability panel examine minimum technical standards for embedded generators. ClimateWorks, Seed and the PCA recently submitted a rule change request to the AEMC that proposed developing minimum technical standards for medium-scale distributed generation (ClimateWorks et al. 2012). The Commission understands they are also developing a technical brief which outlines the issues that should be examined in developing a technical standard. The rule change request could be the mechanism the AEMC uses to address minimum technical standards but the process for development is not clear: To provide for greater certainty and timeliness in processing connection applications for embedded generators, the proponents suggest that automatic access standards for embedded generators be developed. The rule change request does not include an actual proposed standard or suggestions of how it may be developed or by whom. (AEMC 2012b, p.18) The Commission understands a scoping study on developing a technical standards is also underway under the auspices of the COAG Select Committee on Climate Change (SCCC). All jurisdictions (including Victoria) support this work, which will examine international examples of technical standards to identify options to develop standards for connecting distributed generation in Australia. ClimateWorks, Seed and PCA acknowledge that medium-scale systems have more significant impacts on networks than household-scale inverter connected systems and that developing standards will be challenging (ClimateWorks et al. 2011, p.41). During consultation the PCA suggested that not all applications would proceed through an automatic right of connection with an Australian Standard but that such a standard would assist some applicants. The CEC does not consider ambiguity around technical standards is a barrier to connection, but even if it is, they are sceptical about whether technical standards would be effective: 4 The CEC (sub. DR197, p. 18) suggested the NERA report is referring to other states but there is evidence of similar problems in Victoria (NECA, sub. DR174, p. 4) (ClimateWorks et al. 2011, p.11). CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 97 … while the CEC agrees that there may be merit in exploring the avenue of developing automatic access standards for distributed generation, the magnitude of the barriers present to the development [of] such an approach creates extreme uncertainty and complexity. In conjunction, the CEC is not certain that such an approach will efficiently remove the barriers to distributed generation which the Commission has identified. (sub. DR197, p. 5) The CEC instead emphasises the importance of an improved connection process, with upfront recognition of the core issues and a program to resolve them, as discussed in section 6.5. The SCCC’s scoping study should help to resolve the question of whether it is practical to develop standards, as should the AEMC’s consideration of the rule change request by ClimateWorks, Seed and the PCA. ClimateWorks suggested the Victorian Government could support development of an Australian Standard for connecting medium-scale distributed generators. In particular the Victorian Government could assist the SCCC’s scoping study by: Reviewing the extent to which current Victorian technical requirements differ from those of other (NEM) states and the magnitude of the task of harmonising standards. This could include the requirements of the relevant Act(s) and the Distribution Code, any requirements that Energy Safe Victoria (ESV) imposes on connections and any requirements imposed by the DNSPs, for example, the Service Installation Rules (SIRs), which are DNSP defined but have the effect of a regulatory instrument. Reviewing the obligations, enforcement and penalties on all parties for safely connecting distributed generators to the network. DNSPs have taken the stance that the obligation for ensuring safety rests predominantly with them, but this is inconsistent with ClimateWorks’ understanding of the regulatory framework more generally. (ClimateWorks 2012) If minimum technical standards are established a right to connect would require legislative obligations on DNSPs to make a connection offer when the standards and reinforcement costs are met. Right to export There is some ambiguity about whether distributed generators have a right to export electricity to the network through an established connection. The EDC places obligations on the DNSPs and distributed generators in relation to connection agreements and export of electricity. Clause 7.1.1 of the EDC appears to provide a right to export for distributed generators: ‘a distributor must ensure that its distribution system is able to receive a supply of electricity from an embedded generating unit... in accordance with an agreement… on the terms and conditions of dispatch, connection and disconnection’. However: DG [distributed generator] proponents argued that DNSPs are placing onerous restrictions on DG proponents in their connection agreements which can limit their export capability. For example DNSPs may restrict the operation of DG installations by requiring it to run in 'island mode' (that is, not synchronised with the network) and this consequently prevents any energy from being exported. However, DNSPs consider that placing these terms in the connection agreement is their only opportunity to collectively 98 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION identify and mitigate any technical and performance issues associated with DG that could arise in the network. (AEMC 2012f, p.176) Clause 7.8 of the EDC requires embedded generators to design or operate so as not to cause fault levels in the distribution system to exceed specified levels, which may negate the apparent right to export in clause 7.1.1. The AER states ‘embedded generators have no firm right of access to the shared network and are subject to network constraints for exporting electricity’ (AER 2012d, p.65). Seed submitted to the AER that ‘to argue that clause 7.8 trumps clause 7.1 in governing the connection of embedded generators is based on a construction of the intent of the Distribution Code for which we believe there is no evidence’ (Seed 2012, p.2). It is unclear whether the barrier to export is in the EDC or the way AER interprets the EDC. The rule change request by ClimateWorks, Seed and the PCA provides an avenue to resolve this uncertainty. The Commission’s view The Commission considers that ideally medium-scale distributed generators and DNSPs would have clarity about: minimum technical standards network condition cost sharing arrangements for network reinforcement (chapter 5) the process that gives a right to connect and export electricity if minimum standards are met and network reinforcement costs are paid. In progressing to this ideal, key questions for the Victorian Government include the role of government in supporting development of a standard, the efficiency of establishing such an arrangement, and the maintenance of appropriate safeguards for the network. As highlighted by CitiPower, the impact on all network customers and the cost sharing arrangements for automatic connection require careful and explicit consideration (sub. DR184, p. 6). The Commission considered these issues in chapter 5. Role of Government The Commission considers that there is only a role for government if there are broad net benefits to the community or market failures. The beneficiaries of the development of automatic access standards for medium-scale generators are national energy consumers, through increased competition, and mainly the distributed generators. Medium-scale distributed generators should therefore provide the majority of the funding for the development of the standard. One arguable source of market failure is a lack of coordination in competing medium-scale generators working together to develop a standard. If there is a coordination problem any intervention should target coordination rather than funding. Where there are benefits to national electricity users, the Victorian Government could support development of the standards along with other jurisdictions (including the Commonwealth) and the distributed generators. Efficiency of developing a standard The Commission considers that if automatic connection based on minimum technical standards is possible for large- and small-scale generators, then such a process could be possible for medium-scale. The question is whether the benefits of developing standards exceed the costs. CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 99 If practical, consistent minimum standards would eliminate the confusion and delay caused by the DNSPs having discretion to negotiate standards on a case-by-case basis. Minimum technical standards also provide the developers of distributed generation unites with the information on DNSP requirements they need to improve system integration (Bauknecht & Brunekreeft 2008, p.485). Distributed generator proponents may then make commercial decisions to connect or not connect based on predetermined standards and the cost of meeting those standards. Those who do not meet the standards could choose not to connect or negotiate a tailored connection service. The SCCC scoping study and the PCA’s technical brief should identify the costs and benefits and timeframes for developing such a technical standard. The AEMC’s consideration of the rule change request by ClimateWorks, Seed and the PCA will also provide useful information. The Commission considers there is merit in exploring the development of technical standards that apply to Victorian DNSPs for standard types of distributed generation projects below 5 MW, and using such standards as the basis of an automatic right to connect. Safeguards The highest net benefits would result from an appropriate balance between the discretion afforded to DNSPs in setting minimum technical standards and maintaining their flexibility to address technical issues on constrained local networks. To ensure the safety and reliability of the network, large-scale power stations must do significant preparatory work to meet the minimum standards that guarantee a right to connect. It is appropriate that similar but proportional safeguards are established for connecting medium-scale generators. Net benefits can be maximised by recognising that prudent risk management does not always require ‘gold plated’ network protection, and would rather give flexibility to adopt alternative lower cost network protection solutions. Distributed generators should have a right to export electricity to the network once they have met the standards for network connection and resolved any reasonable fault level issues. This would give the distributed generator the opportunity to negotiate with an aggregator or retailer, or to register and sell through the NEM. Consultation with participants suggested there was some scope to define minimum technical standards for distributed generators that would improve information to proponents on network requirements and network condition, and reduce duplication in considering equivalent plant in different locations. Conclusion If the ClimateWorks, Seed and PCA rule change request to the AEMC is successful it could result in common standards and an automatic right to connect. In recommendation 6.1 the Commission proposes that the Victorian Government support this proposed rule change. Victoria could support this work by making a submission on the AEMC rule change and compiling and making available information on its own standards. If the ClimateWorks, Seed and PCA rule change request is unsuccessful, the Victorian Government could support private sector initiatives to develop agreed standards, being mindful of the role of state government and the likely beneficiaries of this work. 100 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION 6.5 Process: cost, timelines and uncertainty The connection process was raised by many participants as a source of uncertainty and delay and therefore a barrier to distributed generation (details of the medium-scale connection process are set out in chapter 2 and figure 6.1). Participants identified key causes of delay and uncertainty at several stages in the connection process: Information on the connection process: distributed generator proponents claim there is a lack of accessible consolidated information on the connection process including information requirements, national and state regulatory instruments and the rights and responsibilities of the various parties: Some jurisdictions have developed guidelines on cogeneration connection, but there is still no NEM-wide regulated process for cogeneration connection. A number of processes are underway that could partially address these issues, like the AEMC’s ‘Comprehensive Technical Standards Review’, but even if these deliver on their potential there will still be major gaps. (EEC, sub. DR200, p. 11) When the NECF is in place in Victoria, some generators would be eligible for connection through either a standard (if offered by the DNSP) or negotiated connection service through chapter 5A, or connection through chapter 5. No standard process: each DNSP has its own process and medium-scale projects are assessed on a case-by-case basis: NERA commented that distributors appear to take an ad hoc approach to each embedded generator connection. (AEMC 2009b, p.45) This exacerbates the problems caused by uncertainty about minimum technical standards and a lack of information on network condition. Engagement between proponent and DNSP: in the Commission’s distributed generators roundtable, participants identified poor information exchange as a driver of uncertainty. DNSPs can ask for more information partway through the process, so distributed generator proponents do not know where they stand. In one extreme case ‘the owner received approval of its connection application, only to have it subsequently withdrawn, without explanation for the change of approach’ (ClimateWorks et al. 2011, p.24). DNSPs also have limited capacity to recover the costs of responding to inquiries and the regulatory incentives to engage with distributed generator proponents are not strong (ACIL Tasman 2011b, p.6). Distributed generator participants claimed that these arrangements have discouraged DNSPs from building or retaining skills in this area: Furthermore, the historical focus of [DNSPs] on network augmentation has left them critically under-skilled in understanding both the potential for DSP to reliably reduce peak demand, and the options for using DSP effectively. (EEC, sub. DR200, p. 9) Connection times: distributed generator participants noted that long delays can reduce the viability of proposals and increase investment costs with: Uncertain and often completely unjustifiable timeframes for negotiating an agreement. In Victoria, the connection approval process is typically more than 6 months with many taking 12 months or longer. (EEC, sub. DR200, p. 11) CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 101 But a 65 working day timeframe, as proposed by ClimateWorks, Seed and PCA may not be realistic. DNSPs claim it can take up to 12 months for a simple connection and up to two years for a more complex one (ClimateWorks et al. 2011, p.23). While legislation requires DNSPs to make a connection offer within 65 working days, 40 per cent of distributed generation systems have had a connection period greater than 12 months (SV 2010, p.i). It is therefore difficult to determine what timeframe would be realistic. Distributed generator roundtable participants mentioned that while it can take longer than four years to get a connection, there are examples of DNSPs providing an answer within two weeks. The ability to assess appropriate timeframes and DNSPs’ performance against those timeframes is exacerbated by a lack of reporting. There is no consolidated public reporting by DNSPs of their performance on timeframes for medium-scale connection offers. Some participants claimed, however, that connection is more difficult in Victoria than in other states: The Council has received informal comments from some members that connecting cogeneration and trigeneration units in Victoria is more challenging than in other states. There could be a number of factors that have driven these Council members’ experiences, including the available capacity to accommodate cogeneration in central Melbourne. (EEC, sub. DR200, p. 2) A key source of delay in the initial inquiry stage is the ability to restart the clock on decision-making timeframes. If the DNSP requests more information on the 19 th day of a 20 day decision making period this can restart the timeframes. Negotiation/arbitration costs and processes: any costs and delays through dispute resolution add to a process in which cost and delay is already posing barriers to connection (Senergy 2011, p. 33). Many participants identified that distributed generator proponents are concerned about the potential adverse ramifications of using dispute resolution systems through the AER (MEFL, sub. 75, pp. 9–10). The DNSP may not like the outcome which could in turn have a negative impact on the project due to adverse ‘retaliation’ from the DNSP. This could impact the project or even the developer’s project portfolio. While difficult to prove there is suspicion amongst the industry that this is a real threat. (CEC, sub. 76, attachment 3, p. 9) However, one respondent to Entura’s survey for SV escalated issues to the AER and was satisfied with the outcome: … we ended up taking them to the regulator [the AER] and although we never had a hearing, once we got it to that level we had a letter in the post saying we would be connected for free. (SV 2010, p.13) Opportunities for improvement The adverse impact of the inefficient connection process on distributed generation is generally acknowledged among participants. Some stakeholders responded to the Commission’s conclusion in the draft report that many of the actions outlined in table 6.1 would help improve connection barriers: United Energy concurs with the Commission’s conclusion that recently implemented and proposed changes to the national electricity regulatory framework will address the perceived barriers to connection of distributed generation. (UE, sub. DR199, p. 2) ClimateWorks, the CEC and some other participants, however, claim that even after the introduction of chapter 5A in Victoria and other changes, barriers to connecting 102 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION medium-scale distributed energy will persist (ClimateWorks et al. 2011, p. 11). The CEC stated: … the CEC is of the firm position that this [5A] amendment to the Rules will not simplify the process at all. Rather, it is expected to only gazette the barriers which the Commission has identified and introduce further complexity. (sub. DR197, p. 9) The ClimateWorks, Seed Advisory and the PCA submitted a rule change request to the AEMC which aims to streamline the process for distributed generators connecting through chapter 5 (box 6.3). Box 6.3 Streamlining connection of embedded generators The chart below summarises the proposed new two track connection process incorporating ClimateWorks, Seed and the Property Council of Australia proposed rule changes. Connection Enquiry Connection Application Automatic Access Submit Connection Enquiry May invite DNSP to advise on connection issues in design phase on a fee-forservice basis Site satisfies automatic access standards in amended Ch 5 Negotiated Access Submit Connection Enquiry May invite DNSP to advise on connection issues in design phase on a fee-forservice basis Connection Application proceeds under specified timeframe in amended Ch 5 Connection Agreement Offer Received within 20 day maximum time, as entitled to automatic connection for standard fee, amended in Ch 5 Standard connection agreement Offer required to be made no more than 65 days after full application Opt-in boilerplate contract terms common across DNSPs The proposed changes aim to replace case-by-case negotiations with a standardised process that is clearer, more certain and efficient. The declared intention of the proposal is to encourage distributed generation without compromising the integrity of the national electricity grid. Source: ClimateWorks et al. 2012. The CEC argued that many distributed generators will still need to connect through the chapter 5A negotiated connection service even if the changes to chapter 5 proposed by ClimateWorks, Seed and the PCA succeed (CEC, sub. DR197, p. 4). The CEC therefore, is considering submitting a rule change proposal to the AEMC to reduce information asymmetry problem. The proposal would: … tie all negotiable connection costs to the information provided by the DNSP at the start of the connection negotiation process. This approach limits the cost which the DNSP can charge to that which can be revealed through the information provided. The DNSP then carries the responsibility of ensuring that the information is complete and accurate and that applicants are well informed. (CEC, sub. 197, p. 20) The two requests for rule changes reflect the views of the proponents of rule changes and other participants that there are opportunities to improve the connection process, even after the introduction of chapter 5A in Victoria. These opportunities would: CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 103 improve information on connection processes standardise connection processes improve engagement and information exchange reduce connection times improve dispute resolution. Improve information on connection processes The report, Unlocking the Barriers to Cogeneration (UBC) stated that in states other than Victoria ‘it is almost standard for DNSPs to provide online information, an information line and a form outlining the connection process’ (ClimateWorks et al. 2011, p.22). Several bodies have developed connection guidelines to support distributed generator proponents and DNSPs to navigate the complex connection process, including: CitiPower/Powercor: Customer Guidelines for Sub-transmission Embedded Generation (CitiPower & Powercor Australia 2010) Connected Electricity Networks Association: ENA Guideline for the Preparation of Documentation for Connection of Embedded Generation within Distribution Networks (Energy Networks Australia 2011). The CEC submission said ‘Sustainability Victoria has developed a Victoria specific connection guideline intended to assist connection applicants in understanding the process and the obligations of all relevant parties and to identify risks associated with the process’ (sub. DR197, p. 5). The CEC believed that this guideline is awaiting ministerial approval before its release and suggested expediting the release process. Standardise connection processes In some other countries there are standardised connection processes and participants suggested this approach could work in Victoria: International jurisdictions, such as New Zealand and the United Kingdom, have implemented and benefited from a requirement by networks to publish standard connection contracts, standard connection processes and published connection charges and tariffs. (Exigency, sub. 4, p. 3) As mentioned, the CEC argued that the majority of distributed generators will connect through the negotiated connection process which limits the potential for standardising processes (sub. DR197, p.4). A survey by Entura for SV, however, found that while some requirements of the application process vary some could be consistent across different sites: … the costs for filling out the documentation for the DNSP and conducting the load flow studies could be standard, however equipment costs and augmentation required is site specific and as such the costs associated with these will remain variable. (SV 2010, p.9) The rule change request by ClimateWorks, Seed and the PCA and many submissions to this inquiry proposed a national, standardised connection process and practical district level licensing frameworks. In addition to the calls in this inquiry, the AEMC in its Power of Choice review received a number of submissions calling for a standardised connection process (AEMC 2012f, p.166). 104 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Improve engagement and information exchange ClimateWorks, Seed and the PCA suggested ‘DNSPs do not have a strong incentive to collaborate in the development and improvement of a connection enquiry or application’ (ClimateWorks et al. 2012, p.17). Entura, in its survey for SV, highlighted the importance of early engagement: … early engagement/communication with the DNSP at the detailed design stage, rather than later in the design process, may better facilitate a successful connection of the DG system to the grid. (SV 2010, p.16) A lack of resources for DNSPs to engage with distributed generators during the preliminary inquiry stage ‘could be easily resolved, as UBC project owners have indicated they would be prepared to pay on a fee for service basis to ensure this engagement process occurred’ (ClimateWorks et al. 2011, p.23). The rule change request by ClimateWorks, Seed and PCA includes such a proposal (ClimateWorks et al. 2012). In addition, the interplay between minimum technical standards (section 6.4), information on network condition and early communication between DNSPs and distributed generators can have important impacts on project outcomes: By having set standards for those wishing to install DG projects, project managers will be able to factor in all possible barriers at the pre-feasibility stage. This can assist in ensuring they do not reach a point in the project where they are unable to change things or in a position where they suddenly find themselves being informed of a new set of standards from the DNSP that weren’t originally accounted for, thus putting the project on hold. (SV 2010, p.14) The CEC similarly argued that earlier and more complete communication about technical standards, information requirements and network condition would allow distributed generators to assess the viability of their proposal earlier, reducing costs of redesign, additional network studies and progressing unviable projects (CEC, sub. DR197, p. 14). The CEC argued, however, that it would be difficult to achieve these savings by setting predetermined standards. Instead the CEC suggested DNSPs should be obliged to provide the necessary technical information requirements to applicants in the early stages of a connection application. Reduce connection times Distributed generator proponents participating in the inquiry suggested the connection timeframes should be substantially shortened. The case study proponents consider that a timeframe of between one and three months for completing the connection application process would be consistent with the wider commercial building development process, with an outer limit of six months in extreme cases. (ClimateWorks et al. 2011, p.23) The CEC also claims that earlier provision of technical and information requirements and network condition would save time as well as cost (sub. DR197, p. 14). The PCA rule change request outlines a 20 day connection decision for standard connections and a 65 day connection decisions for non-standard connection (ClimateWorks et al. 2012, p.11). CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 105 Improve dispute resolution Several participants argued for improved dispute resolution processes. During consultation the AER indicated its processes encourage alternative dispute resolution prior to arbitration which offers an avenue to minimise the costs of disputes. The AER’s processes allow for preliminary consideration prior to formal consideration of disputes, although legislation allows for formal considerations to take six months or more (AER 2011b, p.6). The Moreland Energy Foundation Ltd (MEFL) recommended that the government should ‘establish a connection ombudsman or other dispute resolution process to resolve disputes arising out of connection processes’ (MEFL, sub. 75 attachment 1, p. 2). The Energy Efficiency Council recommended establishing a distributed generation ombudsman in the AER (EEC, sub. DR200). The ClimateWorks, Seed and PCA rule change request submitted to the AEMC aims to address many of the connection process barriers raised in this inquiry. The rule change request does not, however, address dispute resolution processes (box 6.2). The Commission’s view Efficient and clear processes can reduce time and uncertainty and thereby support the efficient entry of distributed generation, resulting in effective competition in related markets. The outcomes of efficient connection processes include early withdrawal of unsound proposals and improvements to sound proposals (such as redesign to reduce, mitigate or avoid costly network reinforcement). An efficient process would also enable a progressively sharper focus on the key issues and data collection. As illustrated in figure 6.2, an efficient process would identify critical issues at the start of the process and progressively reduce their uncertainty. Distributed generator proponents normally prefer to delay outlays on the project until such uncertainty is reduced, to avoid the risk of wasting money if, for example, the assessment indicates the project needs redesigning or cannot proceed. DNSPs would also benefit as relevant information would be provided more quickly on higher quality more viable proposals. Accurate, timely information on network condition, as outlined in chapter 5, is critical to support investment decisions by distributed generator proponents, and the connection process. 106 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION Figure 6.2 Framing the connection process from a business perspective Current process under Chapter 5A Unlimited x 5 days Preliminary inquiry Unlimited x 10 days Clock stop/reset with information request/network study Information Application request/site visit DNSP advises standard or negotd process, expected costs Agree Negotiation Offer Dispute resolution Possible improvement to the process One timeframe with no resets, clock stop permitted Preliminary inquiry w/better engagement Notes: Information Application request/ site visit DNSP advises standard or negotd process, expected costs Agree Negotiation Offer Dispute resolution Negotiated (negotd); preliminary inquiry (Prelim. Inq); expected cost (exp. Cost). Source: Commission analysis. CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 107 The Commission considers the following actions would improve the connection process for medium-scale distributed generators and reduce uncertainty, timeframes and costs to business: Improve information on the connection process: information on minimum technical standards (section 6.4), network condition, cost sharing (chapter 5) and the process and information required from distributed generator proponents would help to streamline connection and reduce uncertainty. In addition to supporting improved information made available through the ClimateWorks, Seed and PCA rule change request to the AEMC, the Victorian Government should release Sustainability Victoria’s connection guidelines for distributed generators. Standardise connection processes: as medium-scale distributed generators are treated on a case-by-case basis, the costs of connection could be reduced significantly by standardising connection processes. Improve engagement with customers: DNSPs have limited incentive to engage with distributed generator proponents to help improve their applications and identify information needs during the preliminary inquiry stage and negotiation. Earlier and more thorough communication about technical standards, information requirements and network condition would allow proponents to make earlier decisions about their projects. This could reduce connection costs by hundreds of thousands of dollars through reduced network studies, project redesign and progress of unviable projects. There is a case for examining the incentives and accountability for DNSPs to provide this information in a timely manner. As noted in the draft report, 100 per cent pass through of costs creates disincentives for DNSPs and there are alternative incentive options (DR pp. 74-75). Clarify timeframes: establishing negotiated, project-specific time limits for each stage of the connection process, and reporting performance against these time limits. There is already a requirement for DNSPs to make a connection offer within 65 working days but with 40 per cent of projects taking greater than 12 months (SV 2010, p.i) this suggests the current arrangements could be significantly improved. The Commission considers there is a role for increased monitoring and reporting of DNSPs performance on connecting medium-scale embedded generators. Also establishing processes that allow the ‘clock to stop’ while the distributed generator proponent responds to information requests, but not to be reset, would encourage DNSPs to identify and communicate information requirements early so DNSPs retain sufficient time to subsequently reach a decision. Shortening the timeframes would improve integration at an operational level, by allowing the distributed generator connection to progress at the same rate as a broader commercial building approval process. Timeframes, however, need to allow DNSPs to perform the tasks required of them and if longer than 65 working days is required, this should be recognised in the process so developers have clarity for their decision making. The Commission considers that the evidence of a problem in conflict resolution arrangements is not convincing. Responsibility for these arrangements is moving from the ESC to the AER whose arbitration processes for distributed generation are largely untested. Resorting to regulated arbitration should be a last resort as using commercial mediation in advance of arbitration would reduce the costs of dispute resolution and would help remove barriers to distributed generation. The CEC supported this position (sub. DR197, p. 24). With the movement to national regulation of the energy market, national mechanisms are the preferred avenue for addressing medium-scale connection barriers. The Commission considers that the Proposal to amend the NERs for connecting embedded generators by ClimateWorks, Seed and the PCA has the potential to address many of the opportunities for improvement, including information on processes, standardised 108 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION processes and specific timeframes (ClimateWorks et al. 2012, pp.7, 15 & 26). As noted this proposed amendment also has the potential to establish an automatic right to connect and export for distributed generation projects that conform to specified standards (section 6.4). The Commission considers the best course is that the Victorian Government supports those aspects of the rule change request that address the problems identified in this report. If the rule change is not implemented by June 2013, the Commission suggests the Victorian Government expedites options to reduce barriers to distributed generation using Victorian regulatory instruments that sunset once equivalent national regulatory instruments are introduced. Options that align with chapter 5A would be consistent with Victoria’s commitment to work with other jurisdiction to harmonise arrangements prior to the introduction of chapter 5A and should relieve participant concerns about national consistency (UE, sub. DR199, p.4). The Victorian Government might consider: If the NECF has been introduced, using Victorian regulatory instruments (for example, distribution licences) to require DNSPs in Victoria to establish efficient connection arrangements by incorporating them into standard connection offers that are submitted to and approved by the AER. If the NECF has not been introduced, adding the wording from the relevant clauses of chapter 5A to the EDC, to establish standard and negotiated connection services. The Victorian Government could pass legislative amendments to the Electricity Industry Act 2000 (Vic) to require these to be assessed and approved by the AER. The rule change proposal by ClimateWorks, Seed and the PCA came forward during the course of this inquiry. The CEC’s submission signalled it intends to submit a rule change and others may come forward in the future. The Victorian Government should support these initiatives on their merits where they provide net benefits to the Victorian community. Recommendation 6.1 That, to facilitate efficient connection of medium-scale distributed generators up to 5 MW, the Victorian Government support initiatives that: clarify minimum technical standards and cost sharing arrangements that would support a right to connect and export improve information on the connection process, including publishing Sustainability Victoria’s guide to distributed generation connection in Victoria improve exchange of information and engagement between the distribution network service provider and distributed generator early in the connection process standardise and simplify connection processes and incorporate more reliable timeframes. In the first instance, the Victorian Government, through the Department of Primary Industries (DPI), indicate to the AEMC its support for those aspects of the ClimateWorks, Seed and PCA Proposal to amend the National Electricity Rules for connecting embedded generators that progress the above objectives. DPI should make the AEMC aware of this view during the AEMC’s consultation process on the rule change proposal. Should these issues not be resolved through the national rule change process by June 2013, the Government, subject to a positive cost benefit assessment, use Victorian regulatory instruments such as adding a licence condition requiring distribution network service providers in Victoria to establish such standards and rights. CONNECTING GENERATORS TO THE DISTRIBUTION NETWORK 109 6.6 Cost savings from improved medium-scale connection process The connection process for medium-scale generators is lengthy, complex and uncertain and can have a major (but unverified) impact on the financial viability of projects. A Property Council of Australia survey of its Victorian members in 2010 indicated that there were 23 co/trigeneration proposals being considered for implementation in the CBD, Docklands and city fringe areas. Nineteen of the projects identified were expected to proceed in the relatively short term. A saving of one week for each of these projects is a reduction of over $1 million in holding costs alone5. (ClimateWorks et al. 2012, p.19) There would also be savings in rework and design: One of the UBC Project members quoted a cost of $200,000 in engineering design work to rework the design package in response to changes required by the DNSP. (ClimateWorks et al. 2012, p.19) There is significant potential for cost-effective distributed energy in Victoria. The Institute for Sustainable Futures (ISF) claimed that strategically planned and implemented decentralised energy projects could reduce electricity sector emissions by 6.2 per cent and save consumers around $437 million per annum by 2020 (ISF 2012). The current share between household-scale and medium-scale distributed generation suggests much of this growth would be in medium-scale plant. In the Commission’s view, while it is difficult to be precise the adverse impact of connection barriers to medium-scale distributed generation are likely to be material. While improvement to the connection process would be helpful, it is the efficiency of incentives for DNSPs to invest in their networks and the cost sharing arrangements (chapter 5) that are likely to make the most significant difference to removing barriers to distributed generation. The PCA assumes holding costs of $50,000 to $70,000 per week for commercial property projects. Nineteen projects x $50,000 = $1,140,000. 5 110 POWER FROM THE PEOPLE: INQUIRY INTO DISTRIBUTED GENERATION