Construction Start

advertisement
Status Report Presentation
to the
LISD Board of Trustees
by the
Facility Construction Department
March 27, 2002
1
Projects Under Construction
(as of March 18, 2002)
1.
2.
3.
4.
5.
6.
Campus
Sta. Maria Elementary School
Farias Elementary School
Dovalina Elementary School
Sanchez/Ochoa Elem. School
J. W. Nixon High School
Milton Elementary School
Start Date
Oct. 2001
Oct. 2001
Oct. 2001
Oct. 2001
Oct. 2001
Jan. 2002
2
Santa Maria Elementary School







Architect:
Contractor:
Contract amount:
Construction Start:
Start of School:
Completion Date:
Change Order(s):
Cavazos & Associates Architects
Leyendecker Construction, Inc.
$4,862,700.00
Oct. 31, 2001
Aug. 15, 2002
Aug. 31, 2002
Addition of Single Sex
Restrooms at PK & K.
3
Financial Overview – Sta. Maria
Leyendecker’s Contract
Balance to Finish
Including Retainage= $
3,533,963.47
73%
Amount Paid = $
1,328,736.53
27%
4
Construction Time - Sta. Maria
Leyendecker’s Contract
Total Days
Remaining in
Contract = 166
55%
Days Lapsed in
Contract = 138
45%
5
Santa Maria Elementary School
LISD:
Sta. Maria:
Foundation construction on going.
Approximately 45,000 sq. Ft. Will
be poured by 1-18-02. Additional
20,000 sf to be poured by 1-22-02.
All excavations is complete, all
reinforcing is on jobsite. Masonry
construction projected to commence
1-23-02. Metal building delivery
scheduled to commence 3-01-02.
THIS IS A VIEW LOOKING NORTH FROM THE SOUTH WEST CORNER
OF THE NEW CAMPUS
6
Santa Maria Elementary School
THIS IS A VIEW OF THE AIR CONDITIONING DUCT BEING
ASSEMBLED FOR INSTALLATION
7
Santa Maria Elementary School
LISD:
Sta. Maria:
Foundation construction on going.
Approximately 45,000 sq. Ft. Will
be poured by 1-18-02. Additional
20,000 sf to be poured by 1-22-02.
All excavations is complete, all
reinforcing is on jobsite. Masonry
construction projected to commence
1-23-02. Metal building delivery
scheduled to commence 3-01-02.
ZONE “A” AND “B”
8
Santa Maria Elementary School
LISD:
Sta. Maria:
Foundation construction on going.
Approximately 45,000 sq. Ft. Will
be poured by 1-18-02. Additional
20,000 sf to be poured by 1-22-02.
All excavations is complete, all
reinforcing is on jobsite. Masonry
construction projected to commence
1-23-02. Metal building delivery
scheduled to commence 3-01-02.
KINDER AND FIRST GRADE
9
Santa Maria Elementary School
LISD:
Sta. Maria:
Foundation construction on going.
Approximately 45,000 sq. Ft. Will
be poured by 1-18-02. Additional
20,000 sf to be poured by 1-22-02.
All excavations is complete, all
reinforcing is on jobsite. Masonry
construction projected to commence
1-23-02. Metal building delivery
scheduled to commence 3-01-02.
EAST SIDE ENTRANCE
10
Farias Elementary School

Architect:

Contractor:
Contract amount:
Construction Start:
Days in Contract:
Completion Date:
Change Order(s):





Ashley Humphries, & Sanchez
Architects
Leyendecker Construction, Inc.
$4,926,997.
Oct. 31, 2001
320 Calendar Days
Aug. 31, 2002
Addition of Single Sex
Restrooms at PK & K.
11
Financial Overview – Farias
Leyendecker’s Contract
Balance to Finish
Including Retainage =
$ 3,673,681.95
75%
Amount Paid =
$ 1,253,315.05
25%
12
Construction Time - Farias
Leyendecker’s Contract
Total Days
Remaining in
Contract = 182
57%
Days Lapsed in
Contract = 138
43%
13
Farias Elementary School
FRONT VIEW OF BUILDING SECTION “E”
14
Farias Elementary School
FRONT VIEW OF BUILDING SECTION “F”
15
Farias Elementary School
INSIDE VIEW OF BUILDING SECTION “E”
16
Farias Elementary School
VIEW LOOKING SOUTH AT HE FRONTS OF SECTIONS “B”
AND “C” FFROM THE FLOOR PLAN
17
Farias Elementary School
VIEW OF SECTION “A” LOOKING EAST FROM THE NORTH
WEST CORNER OF THE SITE
18
Farias Elementary School
VIEW OF THE REAR AREA OF SECTION B
19
Dovalina Elementary School







Architect:
Contractor:
Contract amount:
Construction Start:
Number Contract Days:
Completion Date:
Change Order(s):
Design Group International, Inc.
Leyendecker Construction, Inc.
$ 2,801,900.
Oct. 31, 2001
304
Aug. 31, 2002
None
20
Financial Overview – Dovalina
Leyendecker’s Contract
Balance to Finish
Including Retainage
= $ 1,858,459.75
66%
Amount Paid =
$ 943,440.25
34%
21
Construction Time - Dovalina
Leyendecker’s Contract
Total Days
Remaining in
Contract = 166
55%
Days Lapsed in
Contract = 138
45%
22
Dovalina Elementary School
LISD:
Foundation has been poured for addition.
CMU in progress and is approximately 50%
complete. Metal building schedule for
delivery on 1-18-02, with metal panels and
insulation delivery scheduled for 1-25-02.
THIS IS A VIEW LOOKING WEST AT THE HALF WALL THAT WILL
DIVIDE THE GYMNASIUM AND THA CAFETERIA
23
Dovalina Elementary School
LISD:
Foundation has been poured for addition.
CMU in progress and is approximately 50%
complete. Metal building schedule for
delivery on 1-18-02, with metal panels and
insulation delivery scheduled for 1-25-02.
THIS IS A VIEW OF THE MASON’S FINISHING THE BLOCK WORK
AROUND A STEEL COLUMN ON THE GYM SIDE WHERE THE
FOLDING PARTITION WILL END
24
Dovalina Elementary School
LISD:
Foundation has been poured for addition.
CMU in progress and is approximately 50%
complete. Metal building schedule for
delivery on 1-18-02, with metal panels and
insulation delivery scheduled for 1-25-02.
THE A/C DUCT IS BEING PREPARED FOR INSTALLATION
25
Dovalina Elementary School
LISD:
Foundation has been poured for addition.
CMU in progress and is approximately 50%
complete. Metal building schedule for
delivery on 1-18-02, with metal panels and
insulation delivery scheduled for 1-25-02.
HALL NUMBER “7” LOOKING EAST
26
Dovalina Elementary School
LISD:
Foundation has been poured for addition.
CMU in progress and is approximately 50%
complete. Metal building schedule for
delivery on 1-18-02, with metal panels and
insulation delivery scheduled for 1-25-02.
ACCENTED CEILING INSIDE OF CLASSROOM #3,
THE ART CLASSROOM
27
Dovalina Elementary School
LISD:
Foundation has been poured for addition.
CMU in progress and is approximately 50%
complete. Metal building schedule for
delivery on 1-18-02, with metal panels and
insulation delivery scheduled for 1-25-02.
ACCENTED CEILING INSIDE OF CLASSROOM #4,
THE MUSIC AND FINE ARTS CLASSROOM
28
Dovalina Elementary School
LISD:
Foundation has been poured for addition.
CMU in progress and is approximately 50%
complete. Metal building schedule for
delivery on 1-18-02, with metal panels and
insulation delivery scheduled for 1-25-02.
VIEW LOOKING WEST AT THE EAST WALL OF THE NEW
GYMNASIUM
29
Sanchez/Ochoa Elementary School







Architect:
Contractor:
Contract amount:
Construction Start:
Number Contract Days:
Completion Date:
Change Order(s):
Sepulveda & Assoc. Architects
Leyendecker Construction, Inc.
$ 5,132,719.
Oct. 31, 2001
320
Sept. 16, 2002
None
30
Financial Overview – Sanchez/Ochoa
Leyendecker’s Contract
Balance to Finish
Including Retainage=
$ 3,813,900.50
74%
Amount Paid =
$ 1,318,818.50
26%
31
Construction Time – Sanchez/Ochoa
Leyendecker’s Contract
Total Days
Remaining in
Contract = 182
57%
Days Lapsed in
Contract = 138
43%
32
Sanchez/Ochoa Elementary School
FRONT VIEW OF SECTIONS “C” AND “D” FROM THE
33
FLOOR PLAN
Sanchez/Ochoa Elementary School
VIEW LOOKING INTO SECTION “C” OF THE FLOOR PLAN
34
Sanchez/Ochoa Elementary School
VIEW LOOKING
35
Sanchez/Ochoa Elementary School
36
Sanchez/Ochoa Elementary School
37
Sanchez/Ochoa Elementary School
38
J. W. Nixon High School







Architect:
Contractor:
Contract amount:
Construction Start:
Number Contract Days:
Completion Date:
Change Order(s):
Cavazos & Associates Architects
Leyendecker Construction, Inc.
$ 9,298,985.
Jan. 30, 2002
551
August. 15, 2003
None
39
Financial Overview – Nixon High
Leyendecker’s Contract
Balance to Finish
Including Retainage
= $ 9,023,466
97%
Amount Paid =
$ 275,519
3%
40
Construction Time – Nixon High
Leyendecker’s Contract
Total Days
Remaining in
Contract =
504
91%
Days Lapsed
in Contract =
47
9%
41
J. W. Nixon High School
42
J. W. Nixon High School
43
J. W. Nixon High School
44
J. W. Nixon High School
45
46
47
PAD PREPARATION FOR NEW TWO STORY BUILDING
48
FOUNDATION TRENCHING FOR TWO STORY BUILDING
49
Milton Elementary School








Architect:
General Contractor:
Asbestos/Demolition:
Contract amount:
Construction Start:
Number Contract Days:
Completion Date:
Change Order(s):
Turner Hickey & Assoc. Arch.
To be determined
M & M Contracting, Inc.
$ 183,978.
Jan. 27, 2002
47 Days
March 15, 2002
None
50
Financial Overview – Milton
M & M Contracting Contract
Asbestos/Demolition
Balance to
Finish = $
183,978.
100%
Amount Paid = $
0.
0%
51
Construction Time – Milton
M & M Contracting Contract
Asbestos/Demolition
Days Lapsed in
Contract = 50
100%
Total Days
Remaining in
Contract = 0
0%
52
Milton Elementary School
53
Milton Elementary School
54
55
56
57
End of Presentation
Question & Answer Session
58
Download