Engineering Economic Analysis
Canadian Edition
Chapter 7:
Rate of Return Analysis
Chapter 7 …
Introduces the internal rate of return (IRR)
method of evaluating project cash flows.
Relates IRR to net present value (NPV) by
plotting NPV versus the discount rate.
Uses an incremental technique and IRR to
evaluate mutually exclusive alternatives.
EECE 450 — Engineering Economics
7-2
Internal Rate of Return (IRR)
Definition (borrower’s perspective): the
interest rate on the balance of a loan such
that the unpaid loan balance equals zero
when the final payment has been made.
Plan
Year
0
1
2
3
4
5
IRR
A
-$5,000.00
$1,400.00
$1,320.00
$1,240.00
$1,160.00
$1,080.00
8.00%
EECE 450 — Engineering Economics
B
-$5,000.00
$400.00
$400.00
$400.00
$400.00
$5,400.00
8.00%
C
-$5,000.00
$1,252.28
$1,252.28
$1,252.28
$1,252.28
$1,252.28
8.00%
D
-$5,000.00
$0.00
$0.00
$0.00
$0.00
$7,346.64
8.00%
7-3
Internal Rate of Return (IRR) …
Definition (investor’s perspective): the interest
rate earned on the unrecovered investment
such that the unrecovered investment equals
zero at the end of the life of the investment.
Year Cash Flow
0 -$500,000
1
$100,000
2
$200,000
3
$250,000
4
$150,000
5
$75,000
IRR= 17.1686%
Unrecovered
Investment
(start of year)
$500,000.00
$485,843.05
$369,255.54
$182,651.58
$64,010.32
EECE 450 — Engineering Economics
Return on
Unrecovered
Investment
$85,843.05
$83,412.49
$63,396.04
$31,358.74
$10,989.68
Investment
Repayment
$14,156.95
$116,587.51
$186,603.96
$118,641.26
$64,010.32
Unrecovered
Investment
(end of year)
$500,000.00
$485,843.05
$369,255.54
$182,651.58
$64,010.32
$0.00
7-4
Calculating Internal Rate of Return
Alternate definition: the IRR is the discount
rate that forces the NPV to zero.
The best approach to calculating the IRR is to
use a “solver” like a preprogrammed financial
calculator or the IRR() function of Excel®.
If NPV is plotted versus the discount rate, we
see that the IRR is at the zero-crossing (next
page).
EECE 450 — Engineering Economics
7-5
Calculating Internal Rate of Return …
Net Present Value
Year
0
1
2
3
4
5
IRR=
i
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
11%
12%
13%
14%
Unrecovered
Return on
Unrecovered
Investment
Unrecovered Investment
Investment
Cash Flow (start of year)
Investment
Repayment
(end of year)
-$500,000
$500,000.00
$100,000
$500,000.00
$85,843.05
$14,156.95
$485,843.05
$200,000
$485,843.05
$83,412.49 $116,587.51
$369,255.54
$250,000
$369,255.54
$63,396.04 $186,603.96
$182,651.58
$150,000
$182,651.58
$31,358.74 $118,641.26
$64,010.32
$75,000
$64,010.32
$10,989.68
$64,010.32
$0.00
17.1686%
NPV
NPV versus Discount Rate
$275,000
$253,224
$300,000
$232,360
$212,361
$250,000
$193,179
$200,000
$174,773
$150,000
$157,102
$100,000
$140,128
$123,817
$50,000
$108,134
$0
$93,048
5%
10%
15%
20%
25%
-$50,0000%
$78,531
-$100,000
$64,554
Discount Rate
$51,092
$38,120
EECE 450 — Engineering Economics
7-6
Rate of Return Analysis
The rate of return is the most frequently used
measure of merit in industry.
Compare the rate of return (usually called the
Internal Rate of Return or IRR) to the
minimum acceptable rate of return (MARR).
If IRR > MARR, accept the investment.
If IRR < MARR, do not accept the investment.
If IRR = MARR, the investment is marginally
acceptable.
EECE 450 — Engineering Economics
7-7
Rate of Return Analysis …
Where two or more mutually exclusive
alternatives with the same lifetime will provide
the same utility, the IRR is calculated on the
difference between/among the alternatives.
Analyze the incremental project: subtract the
cash flows of a project with a lower initial cost
from the one that has the highest initial cost.
If IRR > MARR, accept the alternative with
the higher initial cost; otherwise accept the
lower cost initial cost alternative.
EECE 450 — Engineering Economics
7-8
Rate of Return Analysis …
Net Present Value
Year Machine X Machine Y
X-Y
0
-$500,000
-$400,000 -$100,000
1
$75,000
$60,000 $15,000
2
$125,000
$105,000 $20,000
3
$140,000
$120,000 $20,000
4
$150,000
$125,000 $25,000
5
$150,000
$125,000 $25,000
6
$130,000
$110,000 $20,000
7
$100,000
$85,000 $15,000
8
$50,000
$40,000 $10,000
IRR=
16.3387% 17.7188% 10.4043%
i
NPV X
NPV Y
0%
$420,000
$370,000
Comparing Machines X and Y
1%
$381,456
$337,709
2%
$345,204
$307,336
$500,000
3%
$311,077
$278,741
4%
$278,921
$251,797
$400,000
5%
$248,597
$226,385
$300,000
6%
$219,975
$202,399
7%
$192,937
$179,738
$200,000
8%
$167,375
$158,314
9%
$143,188
$138,041
$100,000
10%
$120,285
$118,843
11%
$98,580
$100,649
$0
12%
$77,996
$83,393
0%
5%
10%
15%
20%
25%
-$100,000
13%
$58,459
$67,015
14%
$39,904
$51,459
-$200,000
15%
$22,268
$36,674
16%
$5,495
$22,611
Discount Rate
17%
-$10,470
$9,226
EECE 450 — Engineering Economics
Machine X
Machine Y
7-9
Analysis Period
The analysis period must be considered and
can be used as a way of ensuring the
lifetimes are equal for incremental analysis.
Recall that there are three possible cases:
• Useful life of the alternative equals the analysis
period
• Alternatives have useful lives different from the
analysis period
• The analysis period is infinite, n = .
EECE 450 — Engineering Economics
7-10
Engineering Economic Analysis
Canadian Edition
Chapter Appendix 7A:
Difficulties in Solving for
an Interest Rate
Problems with the IRR
The IRR has some drawbacks that force us to
be cautious when we use it:
• The IRR technique can not distinguish between
investing and borrowing; and the criterion for
acceptance depends on which it is.
• Multiple IRR values can occur when there are two
or more reversals in the signs of the cash flows.
• The IRR technique assumes that all cash flows
are borrowed and reinvested at the IRR rate of
return during the project (may not be realistic).
The NPV technique always works properly.
The Modified IRR fixes some of the problems.
EECE 450 — Engineering Economics
7-12
Problems with the IRR …
Example of multiple IRRs:
0
1
2
3
IRR=
i
0%
5%
10%
15%
20%
25%
30%
35%
40%
50%
60%
70%
80%
90%
100%
120%
Cash Flow
-$1,000
$6,200
-$12,000
$7,200
20.00%
100.00%
200.00%
NPV
$400.00
$240.04
$128.47
$51.70
$0.00
-$33.60
-$54.16
-$65.39
-$69.97
-$66.67
-$54.69
-$39.69
-$24.69
-$11.23
$0.00
$15.03
NPV versus Discount Rate
$500.00
$400.00
Net Present Value
Year
$300.00
$200.00
$100.00
$0.00
0%
-$100.00
50%
100%
150%
200%
250%
300%
-$200.00
EECE 450 — Engineering Economics
Discount Rate
7-13
Modified Internal Rate of Return
Two of the problems with the IRR can be
solved by calculating the Modified Internal
Rate of Return (MIRR):
• Multiple IRR values
• Financing and reinvesting at the IRR rate of return
The MIRR technique requires two external
rates of return:
• einv for investing
• efin for financing
EECE 450 — Engineering Economics
7-14
Modified Internal Rate of Return …
Find the present value at the start of the
project of all negative cash flows using efin as
the discount rate.
Find the future value at the end of the project
of all positive cash flows using einv as the
discount rate.
Find the rate of return MIRR that balances
these two values at both ends of the project.
Note: this is an approximate technique; it
produces a reliable result that can be used
appropriately in the analysis/decision.
EECE 450 — Engineering Economics
7-15
Modified Internal Rate of Return …
Example of MIRR technique applied to the
previous multiple IRR example:
Year
0
1
2
3
IRR=
Cash Flow
-$1,000
$6,200
-$12,000
$7,200
20.00%
100.00%
200.00%
EECE 450 — Engineering Economics
External reinvestment rate:
16%
External financing rate:
10%
MIRR (formulas)= 12.4959%
MIRR (Excel function)= 12.4959%
7-16
Suggested Problems
7-31, 36, 38, 39, 46, 52, 54.
7A-9, 23, 26. Note the instructions at the
start of the problems for this section in the
text.
EECE 450 — Engineering Economics
7-17