Procurement Systems – an initial overview
Proper choice of delivery system can help to reduce conflicts on construction projects
05. 06. 2007
Building Procurement – Contract strategy
Right Building
Right Time
Right Place
Successful Investment
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Participants of a construction project have different interests
Claims and litigations
How to reduce conflicts/risk of construction projects
One area, generate conflicts: Procurement system (project delivery system)
Possibilities
Consequences
Of choice the procurement system
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Idea
Investment Process
Area
Money
Initiation Hand-over and use
Civil Engineer/Architect is involved the process
in different phases
in different „roles”
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Common goal of participants to perform a building
Meeting the client’s requirements, ensuring completion
On time
Within cost
To required quality standards
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Cost
Cheapest
Economical
Quality
Best
Adequate
Reasonable
Fastest
Time
In addition: participant’s individual interest
(The incompatibility of cost, quality and time)
(Kharbanda et al. 1980.)
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Directly involved
External client, designer, contractor
Indirectly involved advisor, project manager, supervisor bank, authority
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
But
Conflicts, claims and litigation seems to be inevitable part of construction projects
Areas generate conflicts
One-sided contract (Client drafted contract)
Procurement system (project delivery system)
Site conditions
Site services, etc.
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Not clear understanding peculiarities of that specific procurement and contracting system
Responsible parties
Does not recognise or
Does not want to accept responsibility
Lack of identification of own interest leads to one-sided contract
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Shares: activities responsibilities risks with the partners
Will choose procurement system and contract form
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Idea Hand-over and use
Total management process used when obtaining a building
System of contracting among client, designer, and contractor
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
To produce /create/perform a building a bridge a road
P r o j e c t
Has to be managed
Planning
Organising
Leading
Commanding
Controlling
Who will manage?
In which system ?
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Client
Project manager
Quantity surveyor
Engineer Architect Contractor(s)
Typical management structure with project manager
Client
Project co-ordinator
Quantity surveyor Engineer
Architect Contractor(s)
Typical management structure with project coordinator
(Roger Waterhouse)
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Client’s main decisions:
(Help: principal adviser)
Organisation for the Management of the Project
In-house project manager
In-house and external project management team
External project management
Organisation for Design and Construction
Traditional Design and build
Turnkey Package deal
Management
Construction Management
Management Contracting
Others
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy More complex projects
Lack of time
Need of change in procurement methods
Traditional Project Management
Client Client
Designer
Contractor
Project
Management
Preparation Design
Tender/bidding
Construction
Designer
Contractor
Preparation Design
Tender/bidding
Construction
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
„Improper choice or misunderstanding generate conflicts”
Traditional procurement system
Design and build, turnkey or others
Management type
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Long construction period
Consecutive organisation
Clear contracting relations
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Construction management
Management contracting
Project or management service contract and other variations
General characteristics
An organisation is employed to manage the project the construction
To coordinate the design with construction
Overlapping between design and construction
Series of tenders: work packages
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Client needs representation/protection by neutral expert
Traditional delivery system
Client
Designer
Contractor
Inspector
Supervisor
Q.S.
Design and build
Turnkey, Package deal
Client
Inspector
Supervisor
Contractor
Designer
Subcontractors
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Preparation Design
Tender Contract
Construction
Characteristics
Cost
Single point responsibility
Can be overlapped
Integrated design and construction
Client can be sure of maximum cost before final commitment
– Improves buildability
– Fits to constructor’s expertise, working condition, organisation
Thus costs should be lower shorter time on site
(Savings are not passed to the client in lower prices)
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Construction Management
CM
Client
Inspector
Supervisor
Management Contracting
Client
MC
Inspector
Supervisor
Designer Construction
Manager
Management
Contractor
Contractors Designer
Contractors
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Characteristics
Management team is involved at early stage
Design can be influenced (buildability)
Claims can be solved, delays reduced
Save time – series of tenders, work packages
Flexibility in design to suit the client to suit the budget
More risk in design – higher requirement in design
No assured final cost at the start of construction
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Responsibility for decision
Preparation Design
Traditional system
Tender
Cost
Construction is being started knowing the construction costs
Construction
Start
Preparation Design
Cost
Modern managerial typed system
Tender
Construction
Constriction is started without knowing the construction costs
Start
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Use of non-traditional delivery system can create greater risk of misunderstanding Scope of work / compensation are changing continuously
Innovative project delivery systems can blur the traditional roles and responsibilities of participants
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
To choose appropriate procurement system and appoint the manager as early possible for maximum benefit
Characteristics of the delivery system have to be understood by the participants
Contract has to contain reasonable allocation of activities, responsibilities and risk
All the participants have to recognise responsibilities, act in partnership
Budapest University of Technology and Economics Judit Gyulay
Department of Construction Technology and Management 05.06.2007
Building Procurement – Contract strategy
Proper choice and fully understanding of delivery system
Can help to reduce conflicts on construction projects