Waste management installation

advertisement
MSW management in
Seville
and its surrounding area
IPPC Implementation
Experience
Seville June 12th 2012
1
Contents
 Presentation of the group
 Firms belonging to the group
 History
 Aborgase




Activities
Installations
Complex of Montemarta Cónica
IPPC implementation
 Other firms of the group
 Edifesa
 Tegner
 Energía sur de Europa
 Conclusions
 Contact information
2
IPPC implementation process presentation
1.
2.
3.
4.
5.
IPPC certification process summary
Overview of facilities
Audit Results
Actions carried out after audit
Mayor impacts of implementing the standard
3
1 - IPPC Certification Process
The
administration
The company
Development of process
description report
Correction of ”easily” corrigible
issues
May’05
Nov’05
Oct’07
Initial Integrated Environmental Permit
granting
Apr’08
Carried out audit
Autum’08
Jul’09
Proposal of plant modification
project
Accomplishment of plant
modification project
Discussion and agreement on final
process description report
Approved extension of Permit
Mar’10
Apr’11
Fulfillment of all IEP requirements
4
2 - Facilities Covered under IPPC Permit –
Montemarta Environmental Complex
4
Compost
processing
MSW Processing
5
3
Compost aging
area
Fermentation
wharehouse
6
Metal recycling
plant
Plastic recycling
plant
2
1
Gross MSW
processing
Weight
bridge
5
2 - Facilities Covered under IPPC Permit –
Montemarta Environmental Complex
Closed areas
2
Gas field
5
1
Leachate
treatment plants
Active landfill
4 Leachate pool
3
Landfill gas
power plant
Landfill
6
2 - Facilities Covered under IPPC Permit –
Montemarta Environmental Complex
Other waste
3
Construction and
demolition plant
2
1
Hospital waste
plant
Recycle
plant
7
3 - Audit Results
Classification
according to
Carried out on April
2008
Implemented
according to IPPC
standard
Verified 164 issues
Nature
 Procedure
 Technical
 Documents
 Immediate accomplishment
 134  in order
 30  no
conformities
Corrective measure
 Clarification required
 Immediate corrective action
 Beyond Aborgase scope
30
25
134
20
7
Immeditate
accomplsihment
9
Documents
6
7
Immediate
corrective action
15
30 No
conformities
30
10
11
Beyond Aborgase
scope
Tecnical
17
Clarification
required
5
0
3
According to nature
Procedures
According to corrective measure
8
Clarification required
3 - Audit Results
Solution beyond Aborgase scope
Immediate solution
1
Clinical Waste (RBS) admission procedure
2
Documented control plan
3
Risk assessment for MA by ECCM
4
Maintenance and Cleaning Plan
5
Recovery of potentially recoverable fractions
6
Previous treatment of green waste (PARK and GARDENS) , landfilling treatment procedure during technical shutdowns and weekends
7
Landfilling of potentially recoverable fractions
8
Basic characterization analysis clinical waste (RBS)
9
Temporary storage area for no admissible waste
10
Open air storage of recovered fractions, including compost
11
Green waste is neither ground nor composted
12
Clinic waste piling above 2 levels
13
Clinic waste labeling
14
Editing of landfill incidents book
15
Neither segregation nor storage of WEEE (waste electrical and electronic equipment)
16
Open containers of Hazardous Waste
17
Hazardous waste labeling
18
19
Hazardous Waste area signaling
Used oil storage without dike
20
There is neither specific HW loading area, nor draining in the HW storing area
21
PTL and engines emission points conditioning
22
Leachate collection wells in closed and active landfill bodies
23
Untreated clinic and HW leachate and cleaning water
24
Compost and recovered fraction open air storage
25
Meteorological data recording
26
Leachate analytics parameters
27
Autoclave monitoring results report
28
No previously treated waste landfilled report
29
Report of landfilled waste with no previous treatment
30
Summary of 2007 control plan
9
4 - Immediate solution (I)
No conformities
Improvement Action
Implications
Basic characterization
analysis clinical waste
(RBS)
Presented a suitability certificate of
analytical operations proposed in
standards used for this kind of waste
Increase in the current number of
records and work procedures
Justified the refuse of non admissible
waste according to procedure describe
in NC 1
Increase in controls
9
Temporary storage area for
no admissible waste
12
Clinic waste piling above 2
levels
According to containers homologation,
they can be piled due to piling,
resistance and sealing tests
Continue with the same working
practice (no implication)
13
Clinic waste labeling
Improvements in the HW signaling
Slight improvement in the work
procedure. HW area adaptation
8
12
13
10
4 - Immediate solution (II)
No conformities
Improvement Action
Implications
Neither segregation nor
storage of WEEE
Studied commonly with IMS WEEE the
option of sending material. The option
is rejected due to the bad condition of
the waste
Stored and sent just the potentially
reused material (< 10 t/y)
22
Leachate collection wells in
closed and active landfill
bodies
The first leachate accumulation is
detected in 2011. Installed a pneumatic
system in order to pump it out
Continue with the same working
procedure. NO IMPLICATION
23
Untreated clinic and HW
leachate and cleaning
water
Analyzed waste water and discharged
to public sewage system is considered
Continue with the same working
procedure. NO IPMLICATION
15
22
11
4 - Clarification required (I)
No conformities
Improvement Action
Implications
1
Clinical Waste (RBS)
admission procedure
Development of an specific procedure
for the clinic waste admission and
acceptance
Increase in controls
2
Documented Environmental
Impacts control plan
Risk assessment for MA by
ECCM
Maintenance and Cleaning
Plan
Adapted the existing control plan to the
IPPC EIA requirements
Increase in controls
Presented Risk Evaluation to the
ECCMA
Increase in controls
Developed a maintenance and
cleaning program according to
specifications
Increase in current working procedure
records
3
4
12
4 - Clarification required (II)
14
16
17
18
19
20
No conformities
Improvement Action
Implications
Editing of landfill incidents
book
Open containers of
Hazardous Waste
Hazardous waste labeling
Incident book is edited, including use
instructions and custody responsible
Increase in controls
Hazardous Waste area
signaling
Used oil storage without
dike
There is neither specific
HW loading area, nor
draining in the HW storing
area
General improvement of the
loading area; adapting
tanks, and properly
signaling and labeling
Increase in controls
16-20
13
4 - Clarification required (III)
25/26
27
28
No conformities
Improvement Action
Implications
Meteorological data
recording
Created a record with meteorological
parameters obtained from the closest
National Network of Meteorological
Stations
Increase control and records
Leachate analytics
parameters
Autoclave monitoring
results report
Increase of numbers of characterized
parameters
Increase controls and records
Report with the result of parameters
monitoring control in the autoclave (P,
T, time) sent yearly to Environmental
Authority
Increase in controls and records
28
25
9 kms
14
4 - Clarification required (IV)
No conformities
Improvement Action
Implications
29
Report of landfilled waste
with no previous treatment
Yearly report recording waste
landfilled no previous treatment
Increase in controls
30
Summary of 2007 Control
Plan
Report with results of sanitary data
control to be sent to Environmental
Authority
Increase in controls
15
4 - Solution beyond Aborgase (I)
5
6
7
No conformities
Actions
Implications
Recovery of potentially
recoverable fractions
Designed a plant for bulky waste
treatment
Presented to local association a
cost assessment in order to
increase tipping fee
Constructed the first phase of the
bulky waste treatment plant
Designed a bulky waste treatment
plant
Constructed the first phase of the
bulky waste treatment plant
Desigend a revamping of MSW
recycling plant, with 5
authomatized sorting lines, aimed
at increasing capacit up to
maximum
After several modifications,
increase manual sorting lines and
optimized feeding and organic
fraction refining processes
Previous treatment of green
waste, landfilling treatment
procedure during technical
shutdowns and weekends
Landfilling of potentially
recoverable fractions
No increase in tipping fee
5
16
4 - Solution beyond Aborgase (II)
10
No conformities
Actions
Implications
Open air storage of
recovered fractions,
including compost
Cost study of covering the area
carried out
Proposed by ABORGASE,
expanded plastic treatment
warehouse
No coverage in the rest of storage
areas
11
Green waste is neither
ground nor composted
Designed a Bulky Waste treatment
plant, with a front grinder for green
waste (previous to composting)
Grinder in included in second
phase, which was not finally
accomplished
Compost and recovered
fraction open air storage
Carried out cost assessment of
covering all the required areas
Proposed by ABORGASE,
expanded plastic treatment
warehouse
24
No coverage in the rest of storage
areas
24
10
17
4 - Audit Results
1
Clinical Waste (RBS) admission procedure
done
2
Documented control plan
3
Risk assessment for MA by ECCMm
done
done
4
Maintenance and Cleaning Plan
done
5
Recovery of potentially recoverable fractions
6
Previous treatment of green waste , landfilling treatment procedure during technical shutdowns and weekends
7
Landfilling of potentially recoverable fractions
done
done
done
8
Basic characterization analysis clinical waste (RBS)
done
All no conformities found were finally
corrected, except 3 whose solution
exceeded ABORGASE scope; but
were partially solved
9
Temporary storage area for no admissible waste
10
Open air storage of recovered fractions, including compost
done
Partially
11
Green waste is neither ground nor composted
Partially
12
Clinic waste piling above 2 levels
done
13
Clinic waste labeling
done
14
Editing of landfill incidents book
done
15
Neither segregation nor storage of WEEE (waste electrical and electronic equipment)
done
16
Open containers of Hazardous Waste
done
17
Hazardous waste labeling
done
18
Hazardous Waste area signaling
done
19
Used oil storage without dike
20
There is neither specific HW loading area, nor draining in the HW storing area
done
done
21
PTL and engines emission points conditioning
done
22
Leachate collection wells in closed and active landfill bodies
done
23
Untreated clinic and HW leachate and cleaning water
24
Compost and recovered fraction open air storage
25
Meteorological data recording
done
26
Leachate analytics parameters
27
Autoclave monitoring results report
done
done
28
No previously treated waste landfilled report
done
29
Report of landfilled waste with no previous treatment
done
30
Summary of 2007 control plan
done18
done
Partially
5 - Major impacts - Operation and Investments
Operation Costs
Processing cots increases due to the
necessity of processing 100% of waste
and fostering by-products recovery
+12%
Landfill adaptation
costs
Expend costs for adapting landfills to
national legislation during 2011 - 2018
6,4 M€
Infrastructure
Environmental controls
General high increase in the level of
control and recording, which will be expend
during the landfill operating life plus the
post closure period (- 2046)
300.000 €/year
New Infrastructures
Bulky waste processing plant – phase 1
650.000 €
MSW plant expansion
1.900.000 €
By-products press expansion
140.000 €
IPPC Environmental Standard implementation has meant increase
on control and recording levels, higher operation cost for
processing 100% of incoming waste and additional investments in
landfill and processing plant
19
5 - Major impacts - Operation and Investments
Increase in controls
and records
Treat all waste and
maximize recovery
Landfill Standards
Post closure activity
20
Conclusions – IPPC Implementation
 The whole certification process has taken 6 years, being still alive
 The certification was completed successfully, being granted in October
2007, and extended in July 2009
 Out of a total 165 issues, just 30 were no conform
 7 were of immediate solution
 17 required discussion to really understand the situation and agree a feasible solution
 In 6 the solution exceeded ABORGASE scope, 3 were solved by means of extra investment
and in 2, were partially solved in agreement with the administration
 The implementation process, moreover 6 years of work, has implied
additional investments (9,4 M€), higher operation costs (+12%) and high
increase in number of controls and records
 The additional cost (investment and operation) are partially covered by
ABORGASE
 The IPPC has been a high challenge, but today we do a more responsible
and respectful waste management activity
21
Questions &
Answers
22
Download