CHAPTER VIII CPM-PERT Instructor : Lect.Volkan ÇETİNKAYA “A project is a series of activities directed to accomplishment of a desired objective.” Plan your work first…...then work your plan! PERT: (Project Evaluation and Review Technique CPM: (Critical Path Method) Building, Airport, Roadway and similar construction projects. Loading of new computer systems. Design of new products. Ship Constructing When will the project finish? Which critical activities are there?And not? What’s the probability of finishing the project in a definite term? Where is the project?Going on accurately? Is the project under or below the budget? Are there adequate resources for the completion of project? If it is planned to complete the project before planned time, How can it be done by least cost? CPM: For certain activities , it may be possible to decrease their completion times by spending more money.How does this affect the overall completion time of the project. PERT: It has probability, It is for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks. CPM: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction. Single estimate of activity time Deterministic activity times Used in Production management-for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to existance of past experience CPM’de faaliyetlerin süreleri kesin olarak bilinmektedir. PERT’te faaliyetlerin süre ve maliyetleri kesin olarak bilinmemekte, bu veriler rassal değişkenler olarak atanmaktadır. Dolayısıyla elde edilen kritik yol bir “olasılık kritik yolu”dur. PERT: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction. Multiple estimate of activity time Probabalistic activity times Used in Project Management-for non-repetitive jobs(research and development works) where the time and cost estimates tend to be quite uncertain. Advantages Limitations - Gantt charts are quite commonly - Do not clearly indicate details regarding the progress of activities used. They provide an easy graphical representation of when activities (might) take place. - Do not give a clear indication of interrelation ship between the separate activities Arrows: An arrow leads from tail to head directionally.It indicates ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes: A node is represented by a circle. It indicates EVENT, a point in time where one or more activities start and/or finish. Describe the project and important activities. Describe the relationships among facilities. Draw the project network. Determine time and cost of all activities. Compute the longest way(critical path) of the network. Use the network to plan, to schedule follow and control the project. A new founded company wants to design a product. Below the activities , priority relationships and activity durations were given. Draw the project network. Activity Predecessor Duration A: Construction of production lines - 8 B:Purchasing - 11 C: Production of semi finished product-1 A 10 D: Production of semi finished product-2 B 7 E: testing of semi finished product-2 D 13 C,E 15 F: Assembly □j = Earliest occurence time of event ‘j’ ∆j = Latest occurence time of event ‘j’ Dij = Duration of activity Forward Pass: (Earliest Occurence Times) The computations start at node 1 and advance recursively to end node n . Backward Pass : (Latest Occurence Times) Following the completion of the forward pass , the backward pass computations starts at node n and end at node 1. An activity(i,j) will be critical if it satisfies these 3 conditions. □i = ∆i □j = ∆j ∆j - ∆i = □j - □i = Dij Time Schedule for Example 3 Draw the project network Compute the critical path according to the data below Activity Predecessor Duration A: Construction of production lines - 8 B:Purchasing - 11 C: Production of semi finished product-1 A 10 D: Production of semi finished product-2 B 7 E: testing of semi finished product-2 D 13 C,E 15 F: Assembly PERT: Project Evaluation and Review Technique. Like CPM, but ist is a probabilistic model. In PERT, activities fall in to 3 categories: O : Optimistic P : Pessimistic M : Medium Average Completion Time = (O + 4M + P) /6 Standart Deviation = (P-O)/6 Variance = ( (P−O)/6 ))2 Let’s look at a project with 8 events and 11 activities. QUESTIONS: Draw the network of the project. Compute expected time and variance of each activity. Find critical path. Compute the standart deviation of dispersion proving expected time of project. What is the probability of completion of the project in 19 days or less than 19 days? Draw the network of the ship construction project. Compute expected time and variance of each activity. Find critical path. Compute the standart deviation of dispersion proving expected time of project. What is the probability of project completion in 36 weeks? Activity A B C D E F G H I J K Name Permissions Budget Preperation Draft Constructing Outer Installation Electrical Works Inner Installation Outer Painting Inner Painting Other Submittal TR İzinler Bütçe Hazırlık Draft Kaba İnşaat Dış Tesisat Elektrik İşleri İç Tesisat Dış Boya İç Boya Diğer İşler Teslim Processedor A,B C D D E G F,H H I,J O 2 2 2 5 3 3 5 2 4 2 2 M 3 2 3 7 4 5 6 3 5 3 3 P 4 2 7 9 11 10 10 4 6 4 4