France-UK-Ireland (FUI) Region 5th Stakeholder Group (SG) 26th November 2007, London Interconnector Operator (ICO) Update Simon McVeigh (NGIL) Jean-Gabriel Valentin (RTE) IFA Capacity Management System User Interface • The new system is proposed to be the sole commercial interface for Users for all IFA activity, including: – Conducting auctions – Users’ Mid-Channel Nominations (MCNs) – All general communications (results, ICEs, specifications, curtailments, general queries/notices etc) • IFA will require a single Mid-Channel Nomination – unlike current practice of nominating identical MCNs to both TSOs • Access to be via web-based format (secure, reliable, and using ETSO ECAN protocols) IFA Capacity Management System Next Steps • • • • Dec 07 March 08 *September 08 *October 08 Tenders invited Contract award Product testing Commercial operation *note – chosen Supplier capability will determine precise Go-Live date. • In spring 08 a further User workshop will be held to update Users on business process and interface issues. IFA Capacity Management System Project Timescales Task Duration Prepare Supplier Pre-Qualification 1 week (25 - 29/6) Arrange Regulators/ICOs meeting to agree way forward (deferred) 4 weeks (2 – 31/7) Supplier Pre-Qualification 3 weeks (31/7 – 21/8) Re-arrange Regulators/ICOs meeting. Agree ICO response. 3 Weeks (22/8 – 11/9) Regulators additional request for information and ‘go-ahead’. 4 Weeks (12/9 – 9/10) 25 Jun 07 Plan Commencement 2 Jul 07 Plan Assumption – Regulatory ‘Go’ 9 Oct 07 Actual – Regulatory ‘Go’ Prepare ITT & System Req’ments 6-8 weeks (10/10 – ) Issue ITT - ITT Period 5-6 weeks Assess Tenders and Approve 6 weeks Contract Award - System Delivery 21-29 weeks * Users’ systems/interface mods. 21-29 weeks * Industry testing 3-4 weeks Go-Live * Revised estimates based on Supplier Pre-Qual responses 26 Nov Dec 07 Mar 08 Oct 08 Plan Progress Plan Changes Potential Harmonisation Aspects • Losses 2000 2000 2700 1100 • Firmness 2400 2700 • Settlement 3000 1400 • Interconnector Transfer Limits (ITLs) • Use of I/C Fee 2400 870 1200 500 * Summer 2007 NTC values, as provided by RTE to ETSO Losses Potential Harmonisation Aspects GB Market Firm Connection IFA Mid Channel Nomination (MCN) French Market Firm Connection e.g. 1976 MW 2000 MW Capacity F2E & E2F e.g. 2024 MW 1.17% Loss NGIL Assets 1.17% Loss 4 x 500MW Circuits (Poles 1 – 4) Operated as 2 pairs of 1000MW (Bipoles 1 & 2) RTE Assets Losses Relevant Issues • GB Market ≠ French Market – GB: Market Participants responsible for losses – Fr: RTE pass through all losses (except IFA) to consumers • Direct Current ≠ Alternating Current – AC: System line loss small in meshed network – DC: System conversion losses notable • NGET (TSO) ≠ NGIL (ICO) – NGIL (Interconnector Licence) not permitted to trade energy; cannot mitigate or pass through energy exposure – NGET (Transmission Licence): to take on losses for another BSC party is not resolving an imbalance issue in GB Market; outside Licence Losses Potential Options IFA Mid Channel Nomination (MCN) IFA Nomination? F2E Only? Both directions? Capacity offered? IFA Nomination? E2F Only? Both directions? Capacity offered? 2000 MW Capacity F2E & E2F 1.17% Loss NGIL Assets 1.17% Loss RTE Assets Losses Potential Options • GB Market ≠ French Market – Harmonise GB & French market arrangements? • Direct Current ≠ Alternating Current – Appropriate to consider harmonisation of IFA with other French AC borders? • NGET (TSO) ≠ NGIL (ICO) – Consider varying NGIL’s Interconnector Licence / NGET’s Transmission Licence? • Users already factor losses into the value of IFA capacity – Purpose of harmonisation? Losses Conclusion • No change proposed to current losses arrangements on IFA Firmness Potential Harmonisation Aspects IFA (Direct Current) 2000 2000 2700 1100 2400 2700 3000 1400 2400 870 1200 500 * Summer 2007 NTC values, as provided by RTE to ETSO • • • • • • ATC = NTC = Rating F2E = E2F Capacity No Security Standards No circuit redundancy Reconcile at 100% Force Majeure 100% Other French AC Borders • • • • • • ATC ≤ NTC < Rating F2x ≠ x2F Capacity Security Standards applied Full circuit redundancy Reconcile at 110% Force Majeure 0% Current Compensation Practices ETSO Survey N Photo de l’Europe en juin 2006 NL IR B U K L L S DK (W) FI R COLOURS CODE DK (E) 110 % auction price 100 % auction price D Pl No compensation Other compensation CZ F CH SK A H No ex-ante allocation SL P E I MO No curtailment / no transmission rights allocated G Compensation Force Majeure ETSO Survey N Photo de l’Europe en juin 2006 NL IR B U K L L S DK (W) FI R COLOURS CODE DK (E) No compensation 100 % auction price D Pl No ex-ante allocation CZ F CH SK A H SL P E I MO G Firmness Relevant Issues • IFA Risk ≠ Risk on Other French AC Borders – No European Grid Code to cover DC IFA – UCTE Handbook covers Other French AC Borders – Appropriate to consider harmonisation in FUI region? • NGET (TSO) ≠ NGIL (ICO) – Firm NGIL-NGET Connection to Firm GB Market – NGIL (Interconnector Licence) not permitted to trade energy; cannot mitigate or pass through energy exposure – NGET (Transmission Licence): to take on risk for another BSC party is not resolving an imbalance issue in GB Market; outside Licence Firmness Options • IFA Risk ≠ Risk on Other French AC Borders – Consider harmonisation across ETSO – Network Access & Congestion Management Task Force • NGET (TSO) ≠ NGIL (ICO) – Consider varying NGIL’s Interconnector Licence / NGET’s Transmission Licence? • Who is best placed to mitigate curtailment? – Curtailment is typically in increments of 500MW – Curtailment is proportioned across all User MCNs NACM Task Force Firmness • Sub-group to Task Force led by E.On • Several interconnections to be studied – IFA, IFB, IFD, P-Cz, D-P, D-DW, B-NI, D-NI, D-CH • Analyse curtailments for 2006 CY data – Classified as caused by: • Internal AC Network • Interconnector assets Firmness Study on Interconnectors Draft Curtailment Data 2006 IFA Curtailment Commentary* 30 AC Borders 25 20 Asset related maintenance/faults have not curtailed cross-border capacity because of Security Standards (UCTE Handbook) therefore redundancy in interconnection capacity Unplanned Trips/ Reductions 15 Short-Notice Planned Outages 10 5 Annual Outages 0 B-NL D-DW D-NL D-CH D-F P-Cz P-SL P-VE SL-P Interconnector IFA Network * Discrete curtailment events shown (not duration) Switching transitions 500MW / 1000MW not listed individually Firmness Summary • CM Guideline – Optimisation of firmness – Combination of Firm & Non-Firm capacity allowed • Medium-Term Harmonisation Potential – ETSO NACM Task Force • Short-Term Harmonisation Potential – Firm & Non-Firm capacity • Include as option for settlement functionality in CMS specification • Consult IFA Users on combination of Firm/Non-Firm capacity Settlement & Invoicing Target Availability Product Quarter 2 (Apr-Jun) Monthly Products April May June Direction Target Availability (%) Actual Availability (%) E2F 93 94.0 F2E 93 94.6 Direction Target Availability (%) Actual Availability (%) E2F 95 94.5 F2E 95 95.0 E2F 95 98.6 F2E 95 98.5 E2F 90 89.8 F2E 90 90.2 Settlement & Invoicing Current & Proposed IFA Current • Products invoiced individually, with different payment terms • Products offered/invoiced at Target Availability, reconciled on last payment • Considers Users’ cash flow against IFA service delivery • Equivalent to 100% compensation IFA User Proposal • Consolidated monthly invoices for all products, harmonised payment terms • Products offered at 100% availability, reconciled monthly for outturn • Considers Users’ cash flow against IFA service delivery • Equivalent to 100% compensation Intraday Transfer Limits (ITLs) Current & Proposed IFA Current • ITLs set after D-1 nomination • ITLs do not impact Users’ Interconnector Entitlement (ICE) at D-1 • ITLs can restrict Users’ ability to re-nominate intraday if MCN < ICE IFA Proposal • ITLs set after D-1 nomination, before Intraday allocation • ITLs will not impact Users Interconnector Entitlement (ICE) at D-1 • CM Guideline (applying UIoSI/ UIoLI) will ensure MCN = ICE • Clarification underway regarding ITLs for intraday capacity Use of Interconnector Fee SO-SO Trades • NGET (TSO) ≠ NGIL (ICO) – NGIL cannot subsidise NGET, or vice versa – NGIL must levy a fee for ‘Use of Interconnector’ capability post gate closure • Options for Fee basis – Market-based • Associate with retro-direction D-1/intraday auction clearing price? • Associate with arbitrage value? – Non-market-based • Is there a market to participate in, post gate closure? • Product (I/C capability) is variable by nature – how to value? • No change proposed to current arrangements